Found 15 inspections:

# 142101435720
Unscheduled inspection
Start date: 2021-12-09, end date: 2021-12-22, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: Inspections in connection with notification No. b/n dated December 01, 2021 (ex. No. 9386 dated December 02, 2021) received by the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia) on the completion of construction and reconstruction of the capital construction facility: a) compliance of the built object of capital construction with the requirements of project documentation, including the requirements of energy efficiency and the requirements of the equipment of a capital construction object metering devices of energy resources; b) the removal of the developer, a technical coordinator, a person engaged in the construction, identified during the construction control and implementation of state construction supervision of all violations of the completed works to the requirements of normative legal acts and project documentation; C) the design documentation related to the execution of all construction works, and building materials (products), prevention, detection and suppression approved developer, technical coordinator and the person performing the construction on the basis of an agreement with the developer or the customer (hereinafter the contractor), violations of the legislation on town-planning activities, including project documentation, compliance with mandatory requirements and (or) the requirements established by municipal legal acts; the conformity of the information contained in the notice of initiation of certain types of entrepreneurial activities, the mandatory requirements; compliance of the information contained in the statement and the documents of the legal entity or the individual entrepreneur on the legal status, special permission (license) to carry out certain types of activities or authorization (approval) on the exercise of other legal actions, if the conducting unscheduled inspections of the legal entity, individual entrepreneur provided the rules for the provision of legal status, a special permit (license), authorization (approval) of the mandatory requirements, as well as data about the specified legal entities and individual entrepreneurs, contained in the unified state register of legal entities, the unified state register of individual entrepreneurs and other Federal information resources; implementation of the requirements of the state control (supervision) bodies and municipal control; events: to prevent harm to the life and health of citizens, harm to animals, plants, the environment, cultural heritage sites (historical and cultural monuments) of the peoples of the Russian Federation, museum objects and museum collections included in the Museum Fund of the Russian Federation, especially valuable, including unique, documents of the Archival Fund of the Russian Federation, documents, of special historical, scientific, and cultural significance, which are part of the national library fund; to prevent the occurrence of natural and man-made emergencies; to ensure the security of the state; to eliminate the consequences of causing such harm


# 142101297403
Unscheduled inspection
Start date: 2021-11-19, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection:


# 142105317730
Unscheduled inspection
Start date: 2021-02-20, end date: 2021-03-09, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha (YAkutiya)
Purpose of inspection: inspections in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha (Yakutia), on May 21, 2020, compliance with the mandatory requirements in the field of construction and applied building materials (products), the established procedure for construction and reconstruction of the facility during the construction of the capital construction facility. capital construction


# 142005254807
Unscheduled inspection
Start date: 2020-11-19, end date: —, duration:
Authority:
Purpose of inspection:


# 142005226150
Unscheduled inspection
Start date: 2020-11-12, end date: 2020-11-25, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The subject of the inspection is checked in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha Yakutia on May 21, 2020. During the construction of a capital construction facility, the developer, the technical customer, the person carrying out the construction, meets the mandatory requirements in the field of construction and the construction materials used, products of the established procedure for the construction and reconstruction of a capital construction facility 1 compliance with the performance of work and the construction materials used during the construction of the reconstruction of the capital construction facility as well as the results of such work, the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of the requirements of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 142005214003
Unscheduled inspection
Start date: 2020-11-12, end date: 2020-11-25, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The subject of the inspection is checked in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Republic of Sakha Yakutia on May 21, 2020. During the construction of a capital construction facility, the developer, the technical customer, the person carrying out the construction, meets the mandatory requirements in the field of construction and the construction materials used, products of the established procedure for the construction and reconstruction of a capital construction facility 1 compliance with the performance of work and the construction materials used during the construction of the reconstruction of the capital construction facility as well as the results of such work, the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model if the formation and maintenance of the requirements of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation


# 142004429211
Unscheduled inspection
Start date: 2020-06-17, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 142004372460
Unscheduled inspection
Start date: 2020-03-25, end date: 2020-04-21, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Saha YAkutiya
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms


# 141903947819
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-22, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: In order to verify the actual elimination of previously identified violations during the construction of a capital construction facility, which were prescribed for elimination by regulation 3419 of September 27, 2019, the objectives of this audit are to prevent, identify and suppress violations of urban planning legislation committed by the customer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The verification is to note the necessary 1 compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or if the formation and maintenance of an information model are mandatory in accordance with the requirements of this Code, including energy efficiency requirements, with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping the capital construction facility with metering devices for energy resources used2 the availability of a construction permit 3 compliance with the requirements of parts 23 and 31 of Article 52 Urban Planning Code of the Russian Federation


# 141903947777
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-22, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: The purpose of the verification checks in accordance with the inspection plan approved by the Director of the office of the state construction and housing supervision Yan 15 July 2019 compliance during the construction of capital construction object developer technical customer entity engaged in the construction of obligatory requirements in the field of construction and construction materials used goods of the established order of construction, reconstruction of capital construction object Objectives of this review are to prevent detection and suppression approved developer technical customer and the person in charge of the construction on the basis of the contract with the Builder or by the customer the contractor further violations of the legislation on town-planning activities including technical regulations and project documentation of the Subject of this review is necessary to note 1 of the compliance of contractors and apply building materials in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of this Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of this Code or information model in the case of the formation and maintenance of information models are required in accordance with the requirements of this Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy ресурсов2 have permission to construction of 3 compliance parts 23 and 31 of article 52 of the town planning code of the Russian Federation


# 141903519688
Unscheduled inspection
Start date: 2019-09-16, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 141903519708
Unscheduled inspection
Start date: 2019-09-16, end date: —, duration:
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:


# 141902928502
Unscheduled inspection
Start date: 2019-08-08, end date: —, duration:
Authority:
Purpose of inspection:


# 141800080251
Unscheduled inspection
Start date: 2018-02-13, end date: —, duration:
Authority:
Purpose of inspection:


# 141800054581
Unscheduled inspection
Start date: 2018-01-31, end date: 2018-03-01, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Saha YAkutiya
Purpose of inspection: Protection of the rights and interests of employees in connection with harm to the life and health of an employee


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.