# 002004254137
Unscheduled inspection
Start date: 2020-02-18, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 222100141849
Unscheduled inspection
Start date: 2021-04-05, end date: 2021-04-30, duration: 20
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: This inspection is carried out in order to carry out regional state housing supervision in the Altai Territory to ensure the placement of complete and reliable information about persons providing housing and communal services, persons providing services and performing major repairs, persons managing apartment buildings, in order to implement the provisions of Articles 159 and 160 of the Housing Code from 07/01/2021 Russian Federation, pursuant to the order of the Chief State Housing Inspector of the Russian Federation dated 03/30/2021 No. 193/pr, instructions of the Government of the Russian Federation dated 03/22/2021 No. MX-P-16-3531. The objectives of this audit are to prevent, identify and suppress violations of mandatory requirements. The subject of this audit is the supervision of compliance with mandatory requirements for:
- placement of information in the state information system of housing and communal services
# 422100051449
Unscheduled inspection
Start date: 2021-03-15, end date: 2021-04-09, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is conducted in order to verify the fulfillment of the points previously issued by the Municipal Unitary Enterprise Teplovik in the order dated September 28, 2020 No. P16-342-2062, the deadline for which expired on December 28, 2020;
the purpose of this audit is to assess the completeness of measures to eliminate violations by the Municipal Unitary Enterprise Teplovik, its head and other officials, requirements specified in the previously issued order of the Siberian Rostechnadzor Department dated September 28, 2020 No. P16-342-2062, the deadline for which expired on December 28, 2020.
# 002004254137
Unscheduled inspection
Start date: 2020-02-18, end date: 2020-03-18, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The audit is carried out in order to monitor the implementation of the instructions issued earlier to the municipal unitary enterprise Teplovik of the Mikhailovsky district of the Altai Territory dated September 27, 2019 021606615 items 48 to 59 on the elimination of identified violations, the deadline for which has expired. The objectives of this audit are to assess the completeness of measures to eliminate violations by the municipal unitary enterprise Teplovik of the Mikhailovsky district of the Altai Territory by its head and other officials of the requirements specified in the previously issued instruction of the Siberian Directorate of Rostechnadzor dated September 27, 2019 021606615 items 48 to 59, the deadlines for which expired on September 27 and December 27, 2019. The purpose of this audit is to comply with the instruction of the Siberian Directorate of Rostechnadzor dated September 27, 2019 021606615 items 48 to 59
# 001902992815
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-27, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 261 "On monitoring the progress of preparation of heat supply facilities for operation in the autumn-winter period of 2019 2020" issued on the basis of the instruction of the Government of the Russian Federation dated June 19, 2019 VMP95084 execution of the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 04072019 262 "On control the progress of preparation of electric power facilities for operation in the autumn winter period of 2019 2020" issued on the basis of the order of the Government of the Russian Federation dated June 18, 2019, DKP94982THE tasks of this audit are to verify the technical condition and safe operation of heat supply facilities in order to monitor the progress of preparations for operation in the autumn winter period of 2019 2020