# 772100421683
Unscheduled inspection
Start date: 2021-08-06, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772100267145
Unscheduled inspection
Start date: 2021-06-07, end date: 2021-06-25, duration: 14
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the implementation of the audit program; The tasks of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements design documentation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of design documentation identified during construction control and state construction supervision
# 772005187595
Unscheduled inspection
Start date: 2020-10-16, end date: 2020-10-30, duration: 11
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the audit program The tasks of the audit are to prevent identify and suppress violations of the requirements of the design documentation of the legislation on urban development by the audited person The subject of verification is the compliance of the work and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for energy resources used, including checking the elimination of violations of compliance of completed works with the requirements of project documentation identified during construction control and state construction supervision
# 772004416853
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-05, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for energy resources used
# 772004337779
Unscheduled inspection
Start date: 2020-03-06, end date: 2020-03-20, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the receipt of a notification from the developer of the customer's task of verification, to prevent the identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, to check and verify the elimination of violations specified in the order issued by Mosgosstroynadzor
# 771904144228
Unscheduled inspection
Start date: 2019-12-25, end date: 2020-01-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit are to carry out control measures in connection with the implementation of the verification program verification tasks prevention identification and suppression of violations of the requirements of the design documentation of the legislation on urban planning activity by the audited person, subject to verification of compliance of the work and construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the design documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for energy resources used
# 77180803193829
Unscheduled inspection
Start date: 2018-08-06, end date: 2018-08-14, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803214919
Unscheduled inspection
Start date: 2018-08-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803162562
Unscheduled inspection
Start date: 2018-06-14, end date: 2018-06-21, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77180803102590
Unscheduled inspection
Start date: 2018-03-15, end date: 2018-03-15, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803058874
Unscheduled inspection
Start date: 2018-01-16, end date: 2018-01-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170802771790
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-10-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170801918031
Unscheduled inspection
Start date: 2017-08-18, end date: 2017-08-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701794787
Unscheduled inspection
Start date: 2017-07-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701657259
Unscheduled inspection
Start date: 2017-05-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701547244
Unscheduled inspection
Start date: 2017-04-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701443376
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-17, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77170701341934
Unscheduled inspection
Start date: 2017-01-30, end date: —, duration: —
Authority: —
Purpose of inspection: