# 002004469910
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-08-21, duration: 20
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of a capital construction facility on the basis of the completion notice 1 dated July 13, 2020 in order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of mandatory The subject of this audit is the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements set out in Parts 2 3 and 3_1 of Article 52 of this Code
# 001903919616
Unscheduled inspection
Start date: 2019-11-12, end date: 2019-11-25, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the previously issued instruction of the North Ural Rostechnadzor Department 597759P dated November 07, 2018
# 00170802831437
Unscheduled inspection
Start date: 2017-11-13, end date: 2017-12-08, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspections of a capital construction facility completed on the basis of completion notice No. 1 dated October 10, 2017 in order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility. The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code. The Code
# 00150601463881
Unscheduled inspection
Start date: 2015-10-13, end date: 2015-11-02, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment of the previously issued instruction of the North Ural Rostechnadzor Department 592613 dated 04062015
# 892100188120
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: 4
Authority: Departament prirodno-resursnogo regulirovaniya‚ lesnyh otnoshenii i razvitiya neftegazovogo kompleksa YAmalo-Neneckogo avtonomnogo okruga
Purpose of inspection: To establish that this inspection is carried out in order to monitor the implementation of the instruction on the elimination of identified violations dated 05/30/2019 4-T (hereinafter referred to as the Instruction), previously issued by PURGAZ CJSC.
The purpose of this audit is to verify the elimination of previously identified violations of the forest legislation of the Russian Federation.
The subject of this check is to verify the fulfillment of the Prescription.
# 002004469910
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-08-21, duration: 20
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of a capital construction facility on the basis of the completion notice 1 dated July 13, 2020 in order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility. The objectives of this inspection are to prevent identify and suppress violations of mandatory The subject of this audit is the compliance of the work performed and the building materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements set out in Parts 2 3 and 3_1 of Article 52 of this Code
# 722004239696
Unscheduled inspection
Start date: 2020-05-12, end date: 2020-05-15, duration: —
Authority: Departament prirodnoresursnogo regulirovaniya lesnyh otnoshenii i razvitiya neftegazovogo kompleksa YAmaloNeneckogo avtonomnogo okruga
Purpose of inspection: The purpose is to monitor the implementation of paragraph 1 of the regulation on the elimination of identified violations of 30052019 4T. The task is to verify the elimination of previously identified violations of the forest legislation of the Russian Federation and ensure that a legal entity complies with the mandatory requirements of the legislation of the Russian Federation in the field of forest relations in the course of its activities
# 001903919616
Unscheduled inspection
Start date: 2019-11-12, end date: 2019-11-25, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the fulfillment of the previously issued instruction of the North Ural Rostechnadzor Department 597759P dated November 07, 2018
# 721902865733
Unscheduled inspection
Start date: 2019-05-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902492908
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-25, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the fulfillment of an earlier issued prescription from 21112018 597760P
# 891800049019
Unscheduled inspection
Start date: 2018-01-29, end date: 2018-02-26, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po YAmaloNeneckomu avtonomnomu okrugu
Purpose of inspection: compliance with the requirements of Order No. 1098 of the Federal Service for Supervision of Consumer Rights Protection and Human Welfare dated 241117 "On the implementation of the List of Instructions of the President of the Russian Federation dated 15112017 Pr2319"
# 89170803022568
Unscheduled inspection
Start date: 2017-12-22, end date: 2018-01-26, duration: —
Authority: Federalnaya sluzhba po trudu i zanyatosti
Purpose of inspection: This audit is conducted in order to protect the rights and interests of employees in connection with the receipt of information from the State Institution of the Department of the Pension Fund of the Russian Federation for the Yamalo-Nenets Autonomous District about insurers who have concluded civil law contracts with insured persons from 03072017 597110 the tasks of this audit are supervision over compliance with mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms assessment of compliance of the Company's activities with mandatory labor requirements legislation and other normative legal acts containing norms of labor law protection of labor rights and freedoms of employees of the Company prevention of violations of mandatory requirements of labor legislation and other normative legal acts containing norms of labor law The purpose of this audit is to note the necessary compliance with mandatory requirements or requirements established by municipal legal acts to prevent harm to the life health of citizens harm to animals plants the environment
# 00170802831437
Unscheduled inspection
Start date: 2017-11-13, end date: 2017-12-08, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: inspections of a capital construction facility completed on the basis of completion notice No. 1 dated October 10, 2017 in order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of a capital construction facility. The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this audit is the compliance of the work performed and the building materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code. The Code
# 00170701571877
Unscheduled inspection
Start date: 2017-05-22, end date: 2017-06-19, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection program 57148 dated 16012017 for the capital construction facility "Development of the southern section of the Cenomanian deposit of the Gubkinskoye oil and gas condensate field Cluster of gas wells 37". The objectives of this inspection are to prevent, identify and suppress violations of mandatory requirements of regulatory documents and legislative acts
# 00150601463881
Unscheduled inspection
Start date: 2015-10-13, end date: 2015-11-02, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the fulfillment of the previously issued instruction of the North Ural Rostechnadzor Department 592613 dated 04062015