Found 5 inspections:

# 22170701772135
Unscheduled inspection
Start date: 2017-07-06, end date: 2017-07-07, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: in order to verify the fulfillment of regulation 112GSN of 26052017 of the information contained in the notice on the elimination of violations during construction 3 of 23062017 bx 31VP3208 of 26062017 under Act 189GSN of 26052017 and the implementation of the inspection program of 09.012017, the objectives of this audit are the prevention detection and suppression of violations of legislation on urban development by the technical customer, including the requirements of technical regulations and design documentationsubject of this The verification is ch2 st54 of the GrK of the Russian Federation checking the compliance of the work and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used compliance with mandatory requirements for a construction permit and the requirements of parts 2 and 3 Articles 52 of the Urban Planning Code of the Russian Federation Federal Law No. 30122009 384 FZ "Technical Regulations on the safety of buildings and structures


# 22170701652804
Unscheduled inspection
Start date: 2017-05-25, end date: 2017-05-26, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: the purpose of the implementation of the program of inspections as well as verification of the information contained in the notice of completion dates for construction 572009 from 11052017 bx 31VP2208 from 11052017 The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development by the person carrying out the construction, including the requirements of technical regulations and design documentationthe subject of this audit is ch2 st54 GRK RF verification of compliance with the implementation works and construction materials used in the process of construction reconstruction of a capital construction facility as well as the results of such work to the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used compliance with mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal Law from 30122009384FZ "Technical regulations on the safety of buildings and structures


# 22170701541880
Unscheduled inspection
Start date: 2017-04-13, end date: —, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection:


# 22170701443928
Unscheduled inspection
Start date: 2017-03-09, end date: 2017-03-10, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: purpose verification of the information contained in the notice of elimination of violations of the task prevention detection and suppression of violations of the legislation on urban development the subject is to verify the completed construction of the object, checking the compliance of the work and the construction materials used in the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility compliance with the mandatory requirements for the availability of a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 22170701324989
Unscheduled inspection
Start date: 2017-01-23, end date: 2017-01-24, duration:
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: purpose verification of the information contained in the notice on the completion dates of the work to be verified tasks prevention detection and suppression of violations of the legislation on urban development by the technical customer, including the requirements of technical regulations and design documentationthe object is to verify the completed construction of the object, including checking the compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results such works meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, compliance with mandatory requirements for a construction permit and the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.