# 002005185182
Unscheduled inspection
Start date: 2020-10-28, end date: 2020-11-24, duration: 20
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring compliance of the performed works with the mandatory requirements of the project documentation requirements on energy saving and increase of energy efficiency in the construction of the facility "Reconstruction of nefaresearch Park FGKU Kombinat "March 8" 301610 Tula oblast g Hub KVL 5th St New five-year plan on the basis of 1 Notice of completion of reconstruction of capital construction object from 06102020Задачами of this review are to prevent detection and suppression approved developer by the customer and the person in charge of the construction on the basis of the contract with the developer by the customer breaches of the legislation on town-planning project of documentation of the Subject of this review is to check the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning Code of the Russian Federation further, the Code of the project documentation with the changes made in the project documentation in accordance with paragraphs 38 and 39 of article 49 of the Code and the information model, or if the formation and maintenance of information models are required in accordance with the requirements of the Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 of article 31 of 52 Code


# 001903976764
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-29, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the implementation of paragraphs 153 of the regulation of 19092019 161012R2019 during the reconstruction of the capital construction facility "Reconstruction of the oil reservoir park at FGKU combine "8marta" located at 301610 Tula region g Nodal KVL 5 Five-year street NovayAzachami of this audit are verification of the elimination by a legal entity of paragraphs 153 of the regulation of 19092019 161012R2019 The subject of this audit is the fulfillment by a legal entity of paragraphs 153 of the regulation of 19092019 161012R2019 19092019 161012R2019


# 001903244605
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-20, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the Order of the Federal Service for Environmental Technological and Nuclear Supervision M 261 dated 040720 9g "On monitoring the progress of preparation of heat supply facilities for operation in the autumn-winter period 20192020" on the basis of the instruction of the Government of the Russian Federation dated 19062019 M VMP95084


# 00170801916421
Unscheduled inspection
Start date: 2017-08-07, end date: 2017-08-11, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the progress of preparation of electric power and heat supply facilities for operation in the 2017-2018 OZP Order of the Federal Service for Environmental Technological and Nuclear Supervision 256 dated July 10, 2017 "On monitoring the progress of preparation of Electric Power and Heat Supply facilities for operation in the 20172018 OZP" issued in accordance with the instructions of Deputy Prime Minister of the Russian Federation DN Kozak dated June 29, 2017 DKP94194


# 00160700590786
Unscheduled inspection
Start date: 2016-08-29, end date: 2016-08-31, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of completed works in accordance with the notice of completion of the reconstruction of the capital construction facility


# 00160601683992
Unscheduled inspection
Start date: 2016-05-26, end date: —, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of documentation for compliance with legislation in the field of urban planning activities verification of completed works


# 00150600030884
Unscheduled inspection
Start date: 2015-08-17, end date: 2015-08-18, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation of electric power industry enterprises and heat supply facilities for work in the 2015-2016 OZP


# 712100122041
Unscheduled inspection
Start date: 2021-04-01, end date: 2021-04-15, duration: 11
Authority: Gosudarstvennaya zhilischnaya inspekciya Tulskoi oblasti
Purpose of inspection: execution of the order of the Deputy Chairman of the Government of the Russian Federation M.Sh.Khusnullin dated 02/22/2021 MX-P16-3531, order of the Deputy Minister of Construction and Housing and Communal Services of the Russian Federation - Chief State Housing Inspector of the Russian Federation M.B.Egorov dated 30.03.2021 No. 193/pr, prevention, detection and suppression of violations of the requirements for placing information in GIS housing and communal services, provided for by Federal Law No. 209-FZ dated 07/21/2014 "On the State Information System of Housing and Communal Services", compliance with mandatory requirements and (or) requirements established by municipal legal acts


# 002005185182
Unscheduled inspection
Start date: 2020-10-28, end date: 2020-11-24, duration: 20
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring compliance of the performed works with the mandatory requirements of the project documentation requirements on energy saving and increase of energy efficiency in the construction of the facility "Reconstruction of nefaresearch Park FGKU Kombinat "March 8" 301610 Tula oblast g Hub KVL 5th St New five-year plan on the basis of 1 Notice of completion of reconstruction of capital construction object from 06102020Задачами of this review are to prevent detection and suppression approved developer by the customer and the person in charge of the construction on the basis of the contract with the developer by the customer breaches of the legislation on town-planning project of documentation of the Subject of this review is to check the compliance of contractors and construction materials used in the construction process of reconstruction of capital construction object and the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning Code of the Russian Federation further, the Code of the project documentation with the changes made in the project documentation in accordance with paragraphs 38 and 39 of article 49 of the Code and the information model, or if the formation and maintenance of information models are required in accordance with the requirements of the Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 of article 31 of 52 Code


# 002004474104
Unscheduled inspection
Start date: 2020-08-03, end date: 2020-08-07, duration: 5
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to comply with the Order of the Federal Service for Environmental Technological and Nuclear Supervision No. 267 dated 08072020 "On monitoring the preparation of electric power and heat supply facilities for operation in the autumn-winter period of 2020-2021" on the basis of an instruction from the Government of the Russian Federation dated July 03, 2020 La YUBP97109


# 002004406209
Unscheduled inspection
Start date: 2020-05-13, end date: 2020-06-09, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the completed works with the design documentation requirements for energy saving and energy efficiency improvement during the construction of the capital construction facility "Reconstruction of the oil reservoir park at FGKU Combine "March 8" located at 301610 Tula region, Uzlovaya kvl 5 Five-year-old Novaya Street on the basis of the verification program, the tasks of this check are the prevention, identification and suppression of violations committed by the developer, the customer and a person carrying out construction on the basis of a contract with a developer or customer for violations of legislation on urban planning activities, including design documentationthe subject of this audit is to verify the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which the requirements of energy efficiency The efficiency requirements also do not apply to the equipment of the capital construction facility with metering devices for the energy resources used


# 001903976764
Unscheduled inspection
Start date: 2019-11-18, end date: 2019-11-29, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of monitoring the implementation of paragraphs 153 of the regulation of 19092019 161012R2019 during the reconstruction of the capital construction facility "Reconstruction of the oil reservoir park at FGKU combine "8marta" located at 301610 Tula region g Nodal KVL 5 Five-year street NovayAzachami of this audit are verification of the elimination by a legal entity of paragraphs 153 of the regulation of 19092019 161012R2019 The subject of this audit is the fulfillment by a legal entity of paragraphs 153 of the regulation of 19092019 161012R2019 19092019 161012R2019


# 001903244605
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-20, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the Order of the Federal Service for Environmental Technological and Nuclear Supervision M 261 dated 040720 9g "On monitoring the progress of preparation of heat supply facilities for operation in the autumn-winter period 20192020" on the basis of the instruction of the Government of the Russian Federation dated 19062019 M VMP95084


# 001902975204
Unscheduled inspection
Start date: 2019-08-23, end date: 2019-09-19, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the compliance of the completed works with the design documentation requirements for energy saving and energy efficiency improvement during the construction of the capital construction facility "Reconstruction of the oil reservoir park at FGKU Combine "March 8" located at 301610 Tula region, Uzlovaya kvl 5 Five-year-old Novaya Street on the basis of the verification program, the tasks of this check are the prevention, identification and suppression of violations committed by the developer, the customer and a person carrying out construction on the basis of a contract with a developer or customer for violations of legislation on urban planning activities, including design documentationthe subject of this audit is to verify the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility as well as the results of such work with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which the requirements of energy efficiency The efficiency requirements also do not apply to the equipment of the capital construction facility with metering devices for the energy resources used


# 711800418339
Unscheduled inspection
Start date: 2018-06-04, end date: 2018-07-02, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Tulskoi oblasti
Purpose of inspection: this audit is conducted in order to monitor compliance by the federal state-owned institution "Combine on March 8" of the Office of the Federal Agency for State Reserves for the Central Federal District and its officials with the instructions of the Main Directorate of the Ministry of Emergency Situations of Russia for the Tula Region dated 03072017 On the 23rd the objectives of this audit are this audit is conducted in order to monitor compliance by a legal entity and an individual entrepreneur with the established requirements and measures in the field of civil defense, as well as verification of the fulfillment by the federal state-owned institution "Combine on March 8" of the Management of the Federal Agency for State Reserves for the Central Federal District and its officials of the measures specified in the order of the Main Directorate of the Ministry of Emergency Situations of Russia for the Tula Region dated 03072017 On the 23rd, the subject of this audit is to verify the fulfillment of the order of the state control supervision body


# 71170802782914
Unscheduled inspection
Start date: 2017-11-13, end date: —, duration:
Authority:
Purpose of inspection:


# 00170801916421
Unscheduled inspection
Start date: 2017-08-07, end date: 2017-08-11, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the progress of preparation of electric power and heat supply facilities for operation in the 2017-2018 OZP Order of the Federal Service for Environmental Technological and Nuclear Supervision 256 dated July 10, 2017 "On monitoring the progress of preparation of Electric Power and Heat Supply facilities for operation in the 20172018 OZP" issued in accordance with the instructions of Deputy Prime Minister of the Russian Federation DN Kozak dated June 29, 2017 DKP94194


# 71170701399059
Unscheduled inspection
Start date: 2017-02-20, end date: —, duration:
Authority:
Purpose of inspection:


# 00160700590786
Unscheduled inspection
Start date: 2016-08-29, end date: 2016-08-31, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of completed works in accordance with the notice of completion of the reconstruction of the capital construction facility


# 00160601683992
Unscheduled inspection
Start date: 2016-05-26, end date: —, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of documentation for compliance with legislation in the field of urban planning activities verification of completed works


# 00150600030884
Unscheduled inspection
Start date: 2015-08-17, end date: 2015-08-18, duration:
Authority: Priokskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation of electric power industry enterprises and heat supply facilities for work in the 2015-2016 OZP