# 00170802832533
Unscheduled inspection
Start date: 2017-10-12, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the readiness of the municipality for the heating period in accordance with the "Plan of inspections by the Northwestern Department of Rostechnadzor of the readiness of municipalities for the heating period 2017-2018" approved by the Order of the Department 2111od dated 31082017 posted on the Internet on the official website of the Northwestern Department of Rostechnadzor, the tasks of this audit are the implementation of control over the measures taken by the municipality to meet the requirements for readiness for the heating period of mandatory requirements
# 00160701245717
Unscheduled inspection
Start date: 2016-12-05, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Assessment of the readiness of the municipality for the heating period in accordance with the Plan of inspections of the Northwestern Department of Rostechnadzor of the readiness of municipalities for the heating period 20162017 approved by the Order of the department 206od of 31082016
# 00160701107193
Unscheduled inspection
Start date: 2016-10-24, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the measures taken by the municipality to meet the requirements for readiness for the heating period
# 00160700936217
Unscheduled inspection
Start date: 2016-09-14, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the measures taken by a legal entity to eliminate violations of mandatory requirements
# 00160601559425
Unscheduled inspection
Start date: 2016-03-18, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the measures taken by a legal entity to eliminate violations of mandatory requirements
# 00150601253953
Unscheduled inspection
Start date: 2015-09-18, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: osuschestvlenie kontrolya za prinyatymi yuridicheskim licom merami po ustraneniyu narushenii obyazatelnyh trebovanii v svyazi s istecheniem sroka ispolneniya predpisaniya 2711595PR ot 27032015
# 782202016226
Unscheduled inspection
Start date: 2022-05-11, end date: —, duration: 10
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: compliance by organizations and citizens with fire safety requirements in buildings, premises, structures, linear objects, territories, and land plots owned and/or used by organizations and citizens and subject to fire safety requirements, as well as assessment of their compliance with fire safety requirements: Article 19 of Federal Law No. 69-FZ dated December 21, 1994 "On Fire Safety", paragraph 9 of Part 1 of Article 14 of Federal Law No. 131-FZ dated 06.10.2003 "On General Principles of Organization of Local Self-Government in the Russian Federation", Part 4 of Article 6, Articles 62, 63, 65, 68, 90 of Federal Law No. 123-FZ dated 22.07.2008 "Technical Regulations on Requirements fire safety", points 48, 70, 71, 73, 74, 75, 76 Rules of fire protection in the Russian Federation, approved by Decree of the Government of the Russian Federation dated 09/16/2020 No. 1479, paragraphs 414, 418 Rules of Fire protection in the Russian Federation, approved by Decree of the Government of the Russian Federation dated 09/16/2020 No. 1479
# 782100820263
Unscheduled inspection
Start date: 2021-10-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 782100327358
Unscheduled inspection
Start date: 2021-07-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004469287
Unscheduled inspection
Start date: 2020-07-27, end date: 2020-08-21, duration: 8
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction metering devices for energy resources used to meet the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction, the purpose of checking the execution of the issued instruction on the elimination of violations identified by the subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State Expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and design objectives of this audit are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction in including technical regulations and project documentation
# 472004337189
Unscheduled inspection
Start date: 2020-03-05, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 472004384157
Unscheduled inspection
Start date: 2020-03-26, end date: 2020-04-10, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu vypolneniya porucheniya zamestitelya predsedatelya Pravitelstva Rossiiskoi Federacii VV Abramchenko VAP115pr ot 06022020zadachami nastoyaschei proverki yavlyayutsya vyyavlenie presechenie i preduprezhdenie vozmozhnyh narushenii trebovanii pozharnoi bezopasnosti osuschestvlenie obyazatelnyh trebovanii pozharnoi bezopasnostiPredmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii pozharnoi bezopasnosti
# 471903999442
Unscheduled inspection
Start date: 2019-10-07, end date: 2019-11-01, duration: —
Authority: Gosudarstvennaya inspekciya truda v Leningradskoi oblasti
Purpose of inspection: Implementation of federal state supervision over the employer's compliance with labor legislation and other regulatory legal acts containing labor law norms
# 471903765157
Unscheduled inspection
Start date: 2019-09-30, end date: 2019-10-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902966346
Unscheduled inspection
Start date: 2019-08-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902966371
Unscheduled inspection
Start date: 2019-08-14, end date: 2019-09-10, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: This audit is conducted in order to comply with the protocol of the operational meeting of the Security Council of the Russian Federation dated 300-52019, approved by the President of the Russian Federation on 06062019. The objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements, and systematically monitor compliance with fire safety requirements. The purpose of this audit is to comply with mandatory fire safety requirements
# 471902624085
Unscheduled inspection
Start date: 2019-04-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471800251411
Unscheduled inspection
Start date: 2018-04-02, end date: 2018-04-27, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: execution of the order of the Deputy Chairman of the Government of the Russian Federation A. Khloponin AHP98184 dated 07122017 compliance with mandatory fire safety requirements
# 47170802940010
Unscheduled inspection
Start date: 2017-12-01, end date: 2017-12-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 00170802832533
Unscheduled inspection
Start date: 2017-10-12, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: assessment of the readiness of the municipality for the heating period in accordance with the "Plan of inspections by the Northwestern Department of Rostechnadzor of the readiness of municipalities for the heating period 2017-2018" approved by the Order of the Department 2111od dated 31082017 posted on the Internet on the official website of the Northwestern Department of Rostechnadzor, the tasks of this audit are the implementation of control over the measures taken by the municipality to meet the requirements for readiness for the heating period of mandatory requirements
# 47170801916444
Unscheduled inspection
Start date: 2017-07-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160701245717
Unscheduled inspection
Start date: 2016-12-05, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Assessment of the readiness of the municipality for the heating period in accordance with the Plan of inspections of the Northwestern Department of Rostechnadzor of the readiness of municipalities for the heating period 20162017 approved by the Order of the department 206od of 31082016
# 00160701107193
Unscheduled inspection
Start date: 2016-10-24, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the measures taken by the municipality to meet the requirements for readiness for the heating period
# 00160700936217
Unscheduled inspection
Start date: 2016-09-14, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the measures taken by a legal entity to eliminate violations of mandatory requirements
# 00160601559425
Unscheduled inspection
Start date: 2016-03-18, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Monitoring the measures taken by a legal entity to eliminate violations of mandatory requirements
# 00150601253953
Unscheduled inspection
Start date: 2015-09-18, end date: —, duration: —
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: osuschestvlenie kontrolya za prinyatymi yuridicheskim licom merami po ustraneniyu narushenii obyazatelnyh trebovanii v svyazi s istecheniem sroka ispolneniya predpisaniya 2711595PR ot 27032015