# 001903933964
Unscheduled inspection
Start date: 2019-11-05, end date: —, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001903020985
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-27, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: S celyu proverki hoda podgotovki obektov elektroenergetiki vo ispolnenie prikaza Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru ot 04072019 262 i porucheniya Pravitelstva Rossiiskoi Federacii ot 18012019g DKP9274 O kontrole hoda podgotovki obektov elektroenergetiki k rabote v osennezimnii period 20192020 godov» i proverki hoda podgotovki obektov teplosnabzheniya k rabote v osennezimnii period 20192020 godov vo ispolneniya prikaza Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru ot 04072019 261 i porucheniya Pravitelstva Rossiiskoi Federacii ot 19 iyunya 2019g VMP95084 O kontrole hoda podgotovki obektov elektroenergetiki k rabote v osennezimnii period 20192020 godov»
# 001800020516
Unscheduled inspection
Start date: 2018-02-19, end date: 2018-03-21, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka vypolneniya meropriyatii predusmotrennyh predpisaniem 200131 ot 13092017g
# 00160601737075
Unscheduled inspection
Start date: 2016-08-11, end date: 2016-09-07, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the progress of preparation of electric power and heat supply facilities for operation in the autumn-winter period of 2016-2017 on the basis of Rostechnadzor Order dated 17062016 229 On monitoring the progress of preparation and assessment of readiness of electric power and heat supply facilities for operation in the autumn-winter period of 2016-2017
# 001903933964
Unscheduled inspection
Start date: 2019-11-05, end date: 2019-12-02, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the implementation of the measures specified in the prescription, the deadlines for which have expired Tasks verification of the actual fulfillment of the mandatory requirements specified in the paragraphs of the prescription Subject verification of the actual fulfillment of the mandatory requirements specified in the paragraphs of the prescription within the established time frame
# 001903020985
Unscheduled inspection
Start date: 2019-09-02, end date: 2019-09-27, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: S celyu proverki hoda podgotovki obektov elektroenergetiki vo ispolnenie prikaza Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru ot 04072019 262 i porucheniya Pravitelstva Rossiiskoi Federacii ot 18012019g DKP9274 O kontrole hoda podgotovki obektov elektroenergetiki k rabote v osennezimnii period 20192020 godov» i proverki hoda podgotovki obektov teplosnabzheniya k rabote v osennezimnii period 20192020 godov vo ispolneniya prikaza Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru ot 04072019 261 i porucheniya Pravitelstva Rossiiskoi Federacii ot 19 iyunya 2019g VMP95084 O kontrole hoda podgotovki obektov elektroenergetiki k rabote v osennezimnii period 20192020 godov»
# 001801017780
Unscheduled inspection
Start date: 2018-09-10, end date: 2018-10-05, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation of electric power facilities for operation in the autumn-winter period 20182019 in accordance with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated 16072018 308 and the order of Deputy Prime Minister of the Russian Federation VL Mutko dated 26072018 VMP93773 "On monitoring the progress of preparation and assessment of the readiness of heat supply facilities for operation in the autumn-winter period 20182019"
# 001800020516
Unscheduled inspection
Start date: 2018-02-19, end date: 2018-03-21, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka vypolneniya meropriyatii predusmotrennyh predpisaniem 200131 ot 13092017g
# 00170801955168
Unscheduled inspection
Start date: 2017-09-04, end date: 2017-09-29, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: S celyu ispolneniya prikaza Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru ot 10 iyulya 2017g 256 «O kontrole hoda podgotovki obektov elektroenergetiki i teplosnabzheniya k rabote v osennezimnii period 20172018 godov» izdannogo na osnovanii porucheniya Zamestitelya Predsedatelya Pravitelstva Rossiiskoi Federacii ot 29 iyunya 2017g DKP94194
# 00160701096535
Unscheduled inspection
Start date: 2016-11-14, end date: 2016-12-09, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Verification of the fulfillment of the previously issued by the Yenisei Department of Rostechnadzor
# 00160601737075
Unscheduled inspection
Start date: 2016-08-11, end date: 2016-09-07, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: checking the progress of preparation of electric power and heat supply facilities for operation in the autumn-winter period of 2016-2017 on the basis of Rostechnadzor Order dated 17062016 229 On monitoring the progress of preparation and assessment of readiness of electric power and heat supply facilities for operation in the autumn-winter period of 2016-2017