# 221902676446
Unscheduled inspection
Start date: 2019-04-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 221902608365
Unscheduled inspection
Start date: 2019-03-28, end date: —, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection:
# 221802030816
Unscheduled inspection
Start date: 2018-10-29, end date: 2018-10-30, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: To establish that this audit is carried out in order to verify the information contained in the notice on the elimination of violations during the construction of a capital construction facility bn dated 24102018 bx 31VP5653 dated 24102018 The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development activities committed by the developer, including the requirements of project documentation The subject of this audit is ch2 st54 GrK RF verification of compliance with the execution of works and the construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work to the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used compliance with mandatory requirements for a construction permit and the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 221801695933
Unscheduled inspection
Start date: 2018-09-26, end date: 2018-09-26, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: To establish that this audit is carried out in order to verify the information contained in the notice on the elimination of violations 3 of 17092018 bx 31VP4932 of 17092018 The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development activities committed by the developer, including the requirements of project documentation The subject of this audit is ch2 st54 GrK RF checking the compliance of the work and the construction materials used in in the process of construction, reconstruction of the capital construction facility, as well as the results of such work, the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal Law No. 30122009 384 FZ "Technical Regulations on Safety buildings and structures of the Russian Federation
# 221800623570
Unscheduled inspection
Start date: 2018-08-13, end date: —, duration: —
Authority: —
Purpose of inspection:
# 22170802927854
Unscheduled inspection
Start date: 2017-12-06, end date: 2017-12-06, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: in order to verify the information contained in the notice bn of 22112017 bx 31VP5932 of 22112017 on the completion of construction, the tasks of this audit are to prevent identify and suppress violations of the legislation on urban development by the developer, including the requirements of technical regulations and design documentationthe subject of this audit is to verify the compliance of the work and the construction materials used during the construction of a capital construction facility as well as the results such works meet the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, availability of a construction permit and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 22170802859021
Unscheduled inspection
Start date: 2017-11-13, end date: 2017-12-08, duration: —
Authority: Gosudarstvennaya inspekciya truda v Altaiskom krae
Purpose of inspection: consideration of the memo submitted by the State labor Inspector for labor protection on verification of information about industrial accidents received from a medical institution details of document 3362217PV dated 16102017the tasks of this audit are to ensure compliance with and protection of labor rights and freedoms of citizens including the right to safe working conditions ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms. The purpose of this check is to note the necessary compliance with mandatory requirements and or requirements established by municipal legal acts
# 22170701776141
Unscheduled inspection
Start date: 2017-07-18, end date: 2017-07-19, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Altaiskomu krayu
Purpose of inspection: this audit is carried out in order to monitor the implementation of the issued order dated 23112016 on the elimination of the identified violation of land legislation, the deadline for which expires. The objectives of this audit are to ensure compliance with land legislation requirements for the protection and use of land. The subject of this audit is the fulfillment of the instructions of state control and supervision bodies
# 22170701675629
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-07-03, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Altaiskomu krayu
Purpose of inspection: control over the execution of the regulation GPN 2221105 of 22062016
# 22170701614509
Unscheduled inspection
Start date: 2017-05-10, end date: 2017-05-16, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Altaiskomu krayu
Purpose of inspection: verification of compliance with the completeness and reliability of the documents submitted by the license applicant and the information in the application bx 01 dated 04052017 for the renewal of a license for activities in the field of using ionizing radiation sources generating, except if these sources are used in medical activities, the objectives of this check are the prevention detection suppression of violations of legislation in the field of sanitary and epidemiological welfare of the population compliance with the information contained in the application and documents of the legal entity a person or an individual entrepreneur on granting the legal status of a special permit license for the right to carry out certain types of activities or permit approval for other legally significant actions if conducting an appropriate unscheduled inspection of a legal entity individual entrepreneur is provided for by the rules for granting the legal status of a special permit license issuance of a permit approval of mandatory requirements as well as data on these legal entities and individual entrepreneurs contained in the the unified State Register of Legal entities the unified State Register of individual entrepreneurs and other federal information resources
# 22170701652817
Unscheduled inspection
Start date: 2017-05-26, end date: 2017-05-26, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: purpose verification of the information contained in the notice on the suspension of construction of the capital construction facility bx 31vp2365 dated 17052017the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development activities, including the requirements of technical regulations and design documentationthe subject of this audit is ch2 st54 GRK RF checking the compliance of work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work, the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used, compliance with mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation Federal Law No. 30122009 384 FZ "Technical Regulations on the Safety of buildings and structures
# 22170701520320
Unscheduled inspection
Start date: 2017-04-11, end date: 2017-05-11, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Altaiskomu krayu
Purpose of inspection: control over the execution of the regulation GPN 1791100 of 28042016
# 22170701469371
Unscheduled inspection
Start date: 2017-03-17, end date: 2017-03-17, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: purpose verification of the information contained in the notice on the completion dates of the works to be verified tasks prevention detection and suppression of violations of the legislation on urban planning activities the subject is to verify the completed construction of the object checking the compliance of the work and the construction materials used in the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and requirements equipment of the capital construction facility with metering devices for energy resources used compliance with mandatory requirements for a construction permit and the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 22170701407273
Unscheduled inspection
Start date: 2017-02-13, end date: 2017-03-15, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Altaiskomu krayu
Purpose of inspection: p 1 h 5 art 61 of the Federal Law of 21121994 g 69 On fire safety
# 00170701369319
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-02-24, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of compliance with the regulation of 30092016 24AG067
# 22160701271719
Unscheduled inspection
Start date: 2016-12-23, end date: 2016-12-23, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: purpose verification of the information contained in the notice of completion of construction tasks prevention detection and suppression of violations of legislation on urban planning activities the subject is to verify the completed construction of the object, checking the compliance of the work and construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including energy efficiency requirements and equipment requirements of the capital construction facility compliance with the mandatory requirements for the availability of a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 22160701213135
Unscheduled inspection
Start date: 2016-11-24, end date: 2016-12-21, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Altaiskomu krayu
Purpose of inspection: Control over the execution of the instruction GPN 4761292 of 24112015 on the elimination of violations of fire safety requirements on carrying out measures to ensure fire safety at protection facilities and to prevent the threat of fire Prevention detection and suppression of violations by legal entities, their managers and other officials, individual entrepreneurs, their authorized representatives at protection facilities mandatory requirements of legislation in the field of fire safety regulations of the GPN bodies
# 22160701213134
Unscheduled inspection
Start date: 2016-11-24, end date: —, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Altaiskomu krayu
Purpose of inspection:
# 22160701126267
Unscheduled inspection
Start date: 2016-11-22, end date: 2016-11-23, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Altaiskomu krayu
Purpose of inspection: this audit is conducted in accordance with p2 h6 and h8 st711 of the Land Code of the Russian Federation on the basis of the act of administrative inspection of the object of land relations 215 dated 10102016 the objectives of this audit are to ensure compliance with land legislation requirements for the protection and use of land 6 The subject of this audit is compliance with mandatory requirements established by land legislation
# 22160601692696
Unscheduled inspection
Start date: 2016-08-10, end date: 2016-09-06, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Altaiskomu krayu
Purpose of inspection: control over the execution of a previously issued prescription for the elimination of violations of fire safety requirements