Found 2 inspections:

# 662201524657
Unscheduled inspection
Start date: 2022-01-24, end date: 2022-02-04, duration: 12
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this inspection is carried out in order to verify compliance with the requirements of Regulation No. 29-14-29/169 dated December 27, 2021, issued by Fly Construction Company LLC, the purpose of this inspection is to carry out regional state construction supervision. The subject of this audit is: the fulfillment of the previously issued instruction on the elimination of identified violations of mandatory requirements dated 12/27/2021 No. 29-14-29/169, issued by LLC Construction Company Fly.


# 662101500524
Unscheduled inspection
Start date: 2021-12-21, end date: 2021-12-29, duration: 7
Authority: Departament gosudarstvennogo zhilischnogo i stroitelnogo nadzora Sverdlovskoi oblasti
Purpose of inspection: To establish that this audit is conducted in order to verify the arguments of the received application from no. , The purpose of this audit is to carry out regional state construction supervision. The subject of this audit is: checking the compliance of the work performed and the building materials used during the construction of the capital construction facility "Three-section residential building of variable number of storeys No. 6 (No. 15A, 15B, 15B according to ROM) with built-in non-residential public premises and a part of the built-in attached in axes DP'-IP-15P-KP-21P-GP of an underground single-level parking lot with an integrated transformer substation (No. 18 according to ROM) is the 1st sub–stage of the 2nd stage of the 3rd stage of construction", located at Yekaterinburg, on Mashinnaya and Tkachey Streets, as well as the results of such work according to the requirements approved in accordance with parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation Russian Federation design documentation (subject to changes made to the design documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation) and (or) the information model (if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation), including energy efficiency requirements (with the exception of capital construction facilities, which are not subject to energy efficiency requirements) and the requirements for equipping the capital construction facility with metering devices for energy resources used; availability of a construction permit; and compliance with the requirements established by parts 2, 3, and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation.


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.