# 772100161798
Unscheduled inspection
Start date: 2021-04-22, end date: 2021-05-19, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Moskovskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms (10001244260)
# 111903923464
Unscheduled inspection
Start date: 2019-11-06, end date: 2019-11-08, duration: —
Authority: Pechorskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of the audit is to monitor the implementation of the instruction issued by the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of the capital construction facility dated 03102019 250316uh1977105the tasks of the audit are to verify the elimination by the legal entity of the violations identified in the instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of the capital construction facility dated 03102019 250316UH1977105THE subject of the audit is the fulfillment by the legal entity of the instruction of the Pechora Department of Rostechnadzor on the elimination of violations during the construction of the reconstruction of the capital construction facility construction of the reconstruction of the capital construction facility from 03102019 250316Uh1977105 P
# 141902641444
Unscheduled inspection
Start date: 2019-04-22, end date: 2019-05-06, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: In order to verify, in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Russian Federation on November 16, 2018, compliance with the mandatory requirements in the field of construction and the applied building materials and products of the established procedure for the construction and reconstruction of the capital construction facility during the construction by the developer, the technical customer, the person carrying out the construction, the established procedure for the construction and reconstruction of the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations committed by the customer as well as by a person carrying out construction on the basis of a contract with the developer or with the customer, hereinafter referred to as the contractor, violations of legislation on urban planning activities, including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts 1 compliance with the performance of work and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used 2 the availability of a construction permit 3 compliance with the requirements of parts 23 and 316 of Article 52 of the Urban Planning Code of the Russian Federation
# 141902497262
Unscheduled inspection
Start date: 2019-02-11, end date: 2019-02-22, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: In order to verify, in accordance with the inspection program approved by the head of the Department of State Construction and Housing Supervision of the Russian Federation on November 16, 2018, compliance with the mandatory requirements in the field of construction and the applied building materials and products of the established procedure for the construction and reconstruction of the capital construction facility during the construction by the developer, the technical customer, the person carrying out the construction, the established procedure for the construction and reconstruction of the capital construction facility, the objectives of this audit are to prevent, identify and prevent violations committed by the customer as well as by a person carrying out construction on the basis of a contract with the developer or with the customer, hereinafter referred to as the contractor, violations of legislation on urban planning activities, including technical regulations and project documentation, the subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts 1 compliance with the performance of work and the construction materials used during construction, reconstruction of a capital construction facility, as well as the results of the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for the energy resources used 2 the availability of a construction permit 3 compliance with the requirements of parts 23 and 316 of Article 52 of the Urban Planning Code of the Russian Federation