# 001903931057
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-20, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment by a legal entity, an individual entrepreneur, of an order previously issued by the state construction supervision authority to eliminate violations of mandatory requirements based on a notice of elimination of violations for the capital construction facility "Development of the Zapadnoerginsky field of Bushes 12 DNS with UPSV Communication Corridors" DNS with UPSV Stage 2 Project code 8440P" The objectives of this audit are verification of the elimination by a legal entity of an identified violation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 001903097095
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-20, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the fulfillment by a legal entity of an individual entrepreneur of the points of the instruction previously issued by the state construction supervision authority on the elimination of identified violations of mandatory requirements during the construction of the reconstruction of the capital construction facility "Expansion of the UPSV at the Orekhovsky LU Orekhovoermakovsky deposit cipher 216" verification of the elimination by a legal entity of the identified violation specified in the paragraphs of the instruction compliance with the instructions of the state control bodies of supervision of municipal control bodies
# 001903931057
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-11-20, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment by a legal entity, an individual entrepreneur, of an order previously issued by the state construction supervision authority to eliminate violations of mandatory requirements based on a notice of elimination of violations for the capital construction facility "Development of the Zapadnoerginsky field of Bushes 12 DNS with UPSV Communication Corridors" DNS with UPSV Stage 2 Project code 8440P" The objectives of this audit are verification of the elimination by a legal entity of an identified violation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 001903705835
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-15, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the fulfillment by a legal entity of an individual entrepreneur of the points of the instruction previously issued by the state construction supervision authority on the elimination of identified violations of mandatory requirements during the construction of the reconstruction of the capital construction facility "Development of the Zapadnoerginsky GTPP field code 25014 stage 2" verification of the elimination by a legal entity of the identified violation specified in the paragraphs of the instruction compliance with the instructions of the state control bodies of supervision of municipal control bodies
# 001903705288
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-15, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the fulfillment by a legal entity, an individual entrepreneur, of an order previously issued by the state construction supervision authority to eliminate identified violations of mandatory requirements based on a notice of elimination of violations for the capital construction facility "Development of the Zapadnoerginsky GTPP field Stage 2 Project code 25014". The objectives of this audit are to verify that the legal entity eliminates the identified violation. The subject of this audit is compliance with the regulations of state control bodies, supervision bodies of municipal control
# 001903703599
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-15, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment by a legal entity, an individual entrepreneur, of an order previously issued by the state construction supervision authority to eliminate violations of mandatory requirements based on a notice of elimination of violations for the capital construction facility "Development of the Zapadnoerginsky field of Bushes 12 DNS with UPSV Communication Corridors" DNS with UPSV Stage 1 Project code 8440" The objectives of this audit are verification of the elimination by a legal entity of an identified violation The subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 001903703872
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-15, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the fulfillment by a legal entity, an individual entrepreneur, of an order previously issued by the state construction supervision authority to eliminate identified violations of mandatory requirements based on a notice of elimination of violations for the capital construction facility "Development of the Zapadnoerginsky GTPP field Stage 1 Project code 25014" The objectives of this audit are to verify that the legal entity eliminates the identified violation. The subject of this audit is compliance with the regulations of state control bodies, supervision bodies of municipal control
# 001903897937
Unscheduled inspection
Start date: 2019-10-28, end date: 2019-11-18, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to verify the completed construction of the capital construction facility "NPS4 LPDS Yuzhny Balyk Nefteyuganskoe UMN Reconstruction Stage 1 NPS4 Reconstruction Power supply System" on the basis of a completion notice in order to monitor the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility. The purpose of this audit is to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts. The subject of this audit is the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used the availability of a building permit and the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of this Code
# 001903097095
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-09-20, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the fulfillment by a legal entity of an individual entrepreneur of the points of the instruction previously issued by the state construction supervision authority on the elimination of identified violations of mandatory requirements during the construction of the reconstruction of the capital construction facility "Expansion of the UPSV at the Orekhovsky LU Orekhovoermakovsky deposit cipher 216" verification of the elimination by a legal entity of the identified violation specified in the paragraphs of the instruction compliance with the instructions of the state control bodies of supervision of municipal control bodies