# 782101538691
Unscheduled inspection
Start date: 2021-12-01, end date: 2021-12-28, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements established by parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation
# 782101219191
Unscheduled inspection
Start date: 2021-10-18, end date: —, duration: 19
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Inspection of a capital construction facility completed. Completion of measures to meet the mandatory requirements of fire safety, sanitary and epidemiological safety, and environmental safety.
Determination of compliance of the constructed capital construction facility with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources.
# 782100370863
Unscheduled inspection
Start date: 2021-07-22, end date: —, duration: 10
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of work on facades, roofs, internal engineering networks and systems.
To determine whether the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including energy efficiency requirements, and comply with the requirements of Parts 2, 3, and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 782100370957
Unscheduled inspection
Start date: 2021-07-22, end date: —, duration: 10
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: Completion of work on the organization of the construction site in accordance with the PIC. Work on the construction of foundations and the construction of load-bearing structures of a zero-cycle building. To determine whether the work performed and the building materials used during the construction of a capital construction facility, as well as the results of such work, meet the requirements of the design documentation, including energy efficiency requirements, and comply with the requirements of Parts 2, 3, and 3.1 of art. 52 of the Urban Planning Code of the Russian Federation.
# 782100283391
Unscheduled inspection
Start date: 2021-04-23, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the completion of work on the construction and reconstruction of the capital construction facility specified in the notice of the developer (technical customer) on the completion of construction. The subject of this audit is compliance with mandatory requirements, including: compliance of the work performed and the building materials used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation; the objectives of this audit are: prevention, detection and suppression of violations of legislation on urban development, including technical regulations, and project documentation committed by the developer, technical customer (the person carrying out the construction).
# 782100027820
Unscheduled inspection
Start date: 2021-02-15, end date: 2021-04-12, duration: 19
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy Sankt-Peterburga
Purpose of inspection: purpose:
to determine the compliance of the constructed capital construction facility with the requirements of the design documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources
.:
Prevention, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of the project documentation performed during the construction and reconstruction of capital construction facilities.
object:
Inspection of the completed facility, including fire prevention measures, measures to ensure the sanitary and epidemiological welfare of the population, and environmental protection. Landscaping of the territory. Compliance with the regulation dated 02/05/2021 No.2/079Pr1-21
# 782005244289
Unscheduled inspection
Start date: 2020-11-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 782005181112
Unscheduled inspection
Start date: 2020-10-08, end date: 2020-11-04, duration: 20
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: determination of compliance of the constructed capital construction facility with the requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, as well as detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance of works performed during the construction of reconstruction of capital construction facilities with the requirements of technical regulations and other regulatory legal acts acts and project documentation
# 782004466800
Unscheduled inspection
Start date: 2020-08-03, end date: —, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection:
# 782004485278
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-09-09, duration: 18
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: Compliance with the requirements in the field of environmental protection provided for in the project documentation, prevention, as well as identification and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer, the customer, of compliance with the work performed during the construction reconstruction of capital construction facilities with the requirements of project documentation, compliance of the work performed at the capital construction facility with the requirements of project documentation in the field of environmental protection
# 782004445686
Unscheduled inspection
Start date: 2020-07-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 472004247588
Unscheduled inspection
Start date: 2020-03-23, end date: 2020-04-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Verification of TIN Group LLC's compliance with the requirements of the legislation of the Russian Federation in the field of shared-equity construction of apartment buildings and or other real estate objects and compliance with the requirements of the regulation dated 25102019 VD672019 on the elimination of violations of legislation on participation in shared-equity construction of apartment buildings and or other real estate objects
# 472004354724
Unscheduled inspection
Start date: 2020-03-12, end date: 2020-04-08, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation
# 782004310173
Unscheduled inspection
Start date: 2020-02-25, end date: 2020-03-24, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection: The purpose is to control the elimination of violations of fire safety requirements specified in the regulation on the elimination of identified violations of fire safety requirements dated 09082019 22456511, the deadline for which expired on 01022020the objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements to carry out systematic monitoring of the implementation of fire safety requirements The subject of this audit is compliance with fire safety requirements at the protection facility used operated by the organization in the course of carrying out its activities
# 472004262730
Unscheduled inspection
Start date: 2020-02-05, end date: 2020-03-03, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 781904193543
Unscheduled inspection
Start date: 2019-12-03, end date: 2019-12-27, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer
# 471903972917
Unscheduled inspection
Start date: 2019-11-07, end date: 2019-12-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 781904035949
Unscheduled inspection
Start date: 2019-11-12, end date: 2019-12-06, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer
# 781903959767
Unscheduled inspection
Start date: 2019-10-31, end date: 2019-11-26, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer
# 471903483393
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-10-25, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: suppression of violations of the requirements of the legislation of the Russian Federation in the field of shared-equity construction of apartment buildings and or other real estate objects when they are identified
# 781903012093
Unscheduled inspection
Start date: 2019-09-16, end date: 2019-10-11, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: compliance with the project documentation
# 471903616901
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-10-04, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 781903016217
Unscheduled inspection
Start date: 2019-08-26, end date: —, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection:
# 471902866449
Unscheduled inspection
Start date: 2019-07-10, end date: 2019-08-06, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 781902874514
Unscheduled inspection
Start date: 2019-07-11, end date: 2019-08-07, duration: —
Authority: Sluzhba gosudarstvennogo stroitelnogo nadzora i ekspertizy SanktPeterburga
Purpose of inspection: prevention, as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other normative legal acts and project documentation committed by the developer, the customer, the person carrying out construction on the basis of an agreement with the developer or the customer
# 781902873774
Unscheduled inspection
Start date: 2019-07-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902845326
Unscheduled inspection
Start date: 2019-07-01, end date: 2019-07-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902761149
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-07-01, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902712027
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-06-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of the audit is to verify the application of citizens, including individual entrepreneurs, legal entities, information from public authorities, officials of the state supervisory authority, local governments, and the media. The subject of this audit is compliance with mandatory requirements, including compliance with the performance of work and the construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work with technical requirements. regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the technical customer, and the person carrying out the construction, including technical regulations and project documentation
# 471902675783
Unscheduled inspection
Start date: 2019-04-24, end date: 2019-05-28, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation
# 471902612930
Unscheduled inspection
Start date: 2019-03-28, end date: 2019-04-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of the audit is to verify the application of citizens, including individual entrepreneurs, legal entities, information from public authorities, officials of the state supervisory authority, local governments, and the media. The subject of this audit is compliance with mandatory requirements, including compliance with the performance of work and the construction materials used during construction, reconstruction of a capital construction facility, as well as the results of such work with technical requirements. regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer, the technical customer, and the person carrying out the construction, including technical regulations and project documentation
# 471902490583
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Objective and comprehensive review of the appeal of Gr Smirnova M vh GR2922019 dated 25.012019 regarding the violation by TIN Group LLC of legislation on participation in the shared construction of apartment buildings and or other real estate objects during the construction of an apartment building at the address Leningrad region Vsevolozhsky district Kudrovo massif site 2 block 4 site 47 suppression of violations of the requirements of the legislation of the Russian Federation in the field of shared upon detection, compliance with the mandatory requirements established by the Federal Law of 30122004 214 FZ On Participation in the Shared Construction of Apartment Buildings and or Other Real Estate Objects and on Amendments to Certain Legislative Acts of the Russian Federation and other Regulatory Legal Acts of the Russian Federation adopted in accordance with it.
# 471902488655
Unscheduled inspection
Start date: 2019-02-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471902503561
Unscheduled inspection
Start date: 2019-02-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 781902431792
Unscheduled inspection
Start date: 2019-01-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471802281487
Unscheduled inspection
Start date: 2018-12-06, end date: 2019-01-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 471802089577
Unscheduled inspection
Start date: 2018-11-12, end date: 2018-12-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of the audit is to verify the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of identified violations. The subject of this audit is compliance with mandatory requirements, including compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency requirements and equipment requirements of the facility capital construction accounting devices for used energy resources comply with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 471802066662
Unscheduled inspection
Start date: 2018-09-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 471801609451
Unscheduled inspection
Start date: 2018-09-19, end date: 2018-10-16, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the technical customer, the person carrying out the construction
# 781800289901
Unscheduled inspection
Start date: 2018-04-13, end date: 2018-05-15, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g SanktPeterburgu
Purpose of inspection: The purpose is to implement the instruction of the Government of the Russian Federation dated March 28, 2018 DMP41776. The objectives of this audit are to identify, suppress and prevent possible violations of fire safety requirements, and systematically monitor compliance with fire safety requirements. The subject of this audit is compliance with fire safety requirements at a protection facility used and operated by an organization in the course of its activities.
# 47170803022895
Unscheduled inspection
Start date: 2017-12-25, end date: 2018-01-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of the work at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used. 2 and 3 Articles 52 of the Urban Planning Code of the Russian Federation
# 47170701516232
Unscheduled inspection
Start date: 2017-04-05, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:
# 47170701481800
Unscheduled inspection
Start date: 2017-03-23, end date: 2017-04-19, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on the completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements equipment of the capital construction facility with metering devices for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation
# 47170701358474
Unscheduled inspection
Start date: 2017-02-06, end date: 2017-03-07, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on the completion of construction The subject of this audit is compliance with mandatory requirements including compliance of the work and the construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation including energy efficiency requirements and requirements equipment of the capital construction facility with accounting devices for the energy resources used, compliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation