Found 12 inspections:

# 161903846147
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-11-12, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or an individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Written appeal of a citizen 167534619 of 27092019


# 161903846096
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-11-12, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Written appeal of a citizen 167534519 of 27092019


# 161903846002
Unscheduled inspection
Start date: 2019-10-14, end date: 2019-11-12, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Written appeal of a citizen 167535019OB dated 27092019


# 161903845047
Unscheduled inspection
Start date: 2019-10-14, end date: —, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection:


# 161902849616
Unscheduled inspection
Start date: 2019-06-26, end date: 2019-07-23, duration:
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: Implementation of federal State supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms Letter from the law enforcement agency 16465719PV dated 21052019


# 161902437945
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-01-21, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: determining the fact of execution of the order dated 04/122018 1519031801, the deadline for which expired on 07.012019, and drawing up an act based on the results of the inspection, warning, as well as detecting and suppressing violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of violations of compliance with the requirements of technical regulations, other regulatory legal acts and project documentation, carried out during the construction of the capital construction facility. state control supervision of municipal control bodies


# 161902437820
Unscheduled inspection
Start date: 2019-01-21, end date: 2019-01-22, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 26112018, case 151120180016, the prevention and detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with mandatory requirements or requirements established by municipal legal acts


# 161802178991
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-04, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program dated 26112018, case 151120180016, the prevention and detection and suppression of violations committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, compliance with mandatory requirements or requirements established by municipal legal acts


# 161801914472
Unscheduled inspection
Start date: 2018-10-11, end date: 2018-10-12, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 20042018 case 151120180016 prevention as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, as well as compliance with mandatory requirements or requirements established by municipal legal acts, committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer


# 161800635481
Unscheduled inspection
Start date: 2018-08-22, end date: 2018-08-23, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 20042018 case 151120180016 prevention as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, as well as compliance with mandatory requirements or requirements established by municipal legal acts, committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer


# 161800517639
Unscheduled inspection
Start date: 2018-07-09, end date: —, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection:


# 161800332862
Unscheduled inspection
Start date: 2018-05-03, end date: 2018-05-04, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: Determination of the compliance of the completed works applied during the construction and reconstruction of the capital construction facility of building materials and the results of such work with the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping capital construction facilities with metering devices for energy resources used, verification of the construction permit, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation in accordance with the inspection program from 20042018 case 151120180016 prevention as well as detection and suppression of violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, as well as compliance with mandatory requirements or requirements established by municipal legal acts, committed by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.