Found 48 inspections:

# 00160701237780
Unscheduled inspection
Start date: 2016-11-09, end date: —, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 77170802770192
Unscheduled inspection
Start date: 2017-10-24, end date: 2017-10-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170802770191
Unscheduled inspection
Start date: 2017-10-24, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802719240
Unscheduled inspection
Start date: 2017-10-10, end date: —, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection:


# 77170802138508
Unscheduled inspection
Start date: 2017-09-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77170802588480
Unscheduled inspection
Start date: 2017-09-28, end date: 2017-10-25, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Zaschita prav i interesov rabotnikov v svyazi s postupleniem v Inspekciyu obrascheniya rabotnika ot 11092017 g 73742417OB po voprosam oplaty truda


# 77170801917433
Unscheduled inspection
Start date: 2017-08-18, end date: 2017-08-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701884313
Unscheduled inspection
Start date: 2017-08-14, end date: 2017-08-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170801953362
Unscheduled inspection
Start date: 2017-08-31, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701847792
Unscheduled inspection
Start date: 2017-08-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701786524
Unscheduled inspection
Start date: 2017-07-10, end date: 2017-08-04, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Zaschita prav i interesov rabotnikov v svyazi s rassmotreniem ranee vydannogo predpisaniya ot 10052017 g 71417917OB727753


# 77170701710937
Unscheduled inspection
Start date: 2017-06-15, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77170701710936
Unscheduled inspection
Start date: 2017-06-15, end date: 2017-06-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701700681
Unscheduled inspection
Start date: 2017-06-09, end date: 2017-06-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701689513
Unscheduled inspection
Start date: 2017-06-07, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701689510
Unscheduled inspection
Start date: 2017-06-07, end date: 2017-06-20, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701739982
Unscheduled inspection
Start date: 2017-06-23, end date: 2017-07-20, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Zaschita prav i interesov rabotnikov v svyazi s postupleniem v Inspekciyu obrascheniya rabotnika ot 20062017 g 72340317OB po voprosu oplaty truda


# 77170701601620
Unscheduled inspection
Start date: 2017-05-15, end date: —, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection:


# 77170701537136
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-05-17, duration:
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Zaschita prav i interesov rabotnikov v svyazi s postupleniem v Inspekciyu obrascheniya rabotnika ot 05042017 g 71417917OB po voprosam oplaty truda


# 77170701521711
Unscheduled inspection
Start date: 2017-04-06, end date: 2017-04-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701508046
Unscheduled inspection
Start date: 2017-03-31, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701497423
Unscheduled inspection
Start date: 2017-03-31, end date: 2017-04-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701497433
Unscheduled inspection
Start date: 2017-03-30, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77170701497528
Unscheduled inspection
Start date: 2017-03-29, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701375272
Unscheduled inspection
Start date: 2017-02-09, end date: 2017-02-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77170701375271
Unscheduled inspection
Start date: 2017-02-09, end date: —, duration:
Authority:
Purpose of inspection:


# 77170701347292
Unscheduled inspection
Start date: 2017-02-01, end date: 2017-02-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701347291
Unscheduled inspection
Start date: 2017-02-01, end date: 2017-02-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701347372
Unscheduled inspection
Start date: 2017-02-01, end date: 2017-02-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701347371
Unscheduled inspection
Start date: 2017-02-01, end date: 2017-02-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77170701347369
Unscheduled inspection
Start date: 2017-02-01, end date: 2017-02-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77160701227541
Unscheduled inspection
Start date: 2016-12-12, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701227537
Unscheduled inspection
Start date: 2016-12-12, end date: 2016-12-23, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor


# 77160701211540
Unscheduled inspection
Start date: 2016-12-12, end date: 2016-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160701208800
Unscheduled inspection
Start date: 2016-12-12, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701208798
Unscheduled inspection
Start date: 2016-12-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77160701208797
Unscheduled inspection
Start date: 2016-12-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77160701208796
Unscheduled inspection
Start date: 2016-12-12, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:


# 77160701208795
Unscheduled inspection
Start date: 2016-12-12, end date: 2016-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160701208794
Unscheduled inspection
Start date: 2016-12-12, end date: 2016-12-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used


# 77160701208793
Unscheduled inspection
Start date: 2016-12-12, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701215031
Unscheduled inspection
Start date: 2016-12-09, end date: 2017-01-12, duration:
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: kontrol za soblyudeniem polozhenii Federalnogo zakona ot 30122004 214FZ


# 00160701237780
Unscheduled inspection
Start date: 2016-11-09, end date: —, duration:
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ot 29 fevralya 2016 g 3104316Zadachami nastoyaschei proverki yavlyayutsyaOsuschestvlenie kontrolya za prinyatymi OAO «Moskovskii kombinat hleboproduktov» merami po ispolneniyu predpisaniya ot 29 fevralya 2016 g 3104316 i soblyudeniyu obyazatelnyh trebovanii promyshlennoi bezopasnostiPrinyatie mer po ustraneniyu narushenii obyazatelnyh trebovanii v sluchae ih vyyavleniya i po privlecheniyu k otvetstvennosti lic dopustivshih narusheniya trebovanii Federalnyh zakonov i inyh normativnyh pravovyh aktov Predmetom nastoyaschei proverki yavlyaetsya vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora


# 77160701070342
Unscheduled inspection
Start date: 2016-11-02, end date: —, duration:
Authority:
Purpose of inspection:


# 77160701050106
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used


# 77160701050096
Unscheduled inspection
Start date: 2016-10-25, end date: 2016-10-28, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: the audit is carried out in order to ensure that the capital construction facility meets the requirements of technical regulations and design documentation on the basis of an approved verification program. The objectives of this audit are to prevent, identify and suppress violations of technical regulations and design documentation committed by the person being audited. The subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations design documentation, including requirements for energy efficiency and requirements for the equipment of the capital construction facility with metering devices for energy resources used


# 77160700155601
Unscheduled inspection
Start date: 2016-09-07, end date: 2016-09-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 559116 ot 15062016


# 77160700155582
Unscheduled inspection
Start date: 2016-09-07, end date: 2016-09-16, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: proverka provoditsya s celyu ustranenie narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom na osnovanii postupivshego izvescheniya ot zastroischika zakazchika ili lica osuschestvlyayuschego stroitelstvo ob ustranenii narusheniiZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh proveryaemym licom narushenii tehnicheskih reglamentov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka ustraneniya narushenii ukazannyh v predpisanii vydannom Mosgosstroinadzorom 558416 ot 15062016


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.