# 522100273451
Unscheduled inspection
Start date: 2021-06-03, end date: —, duration: 15
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Nizhegorodskoi oblasti
Purpose of inspection: for the purpose of reviewing the appeal
No. 6398/zh-2021 dated 05/14/2021, containing information on the occurrence of harm to the life and health of citizens.
Based on the content of the appeal, it follows that an extraneous pungent odor is present in the apartment of the Aquamarine residential complex at the address: Nizhny Novgorod, Okskaya str., 3, sq. 237. Residents of the apartment (including children) have constant headaches, breathing difficulties, and a chronic runny nose. When opening the linoleum, the smell intensified.
The present odor occurs during the release of ammonia, which can lead to the emergence and spread of mass non-communicable diseases in children and adults. The applicant requests to conduct air tests for ammonia content in the entire apartment.
According to the test report No. 1280 submitted by the applicant dated 04/08/2021, performed by the IAC Research Institute of Chemistry of the National National University of Economics. Lobachevsky (unique number of the accreditation record in the register of accredited persons No. POCC RU.0001.51063) the ammonia content in the air of the room in the applicant's apartment was 0.66 mg/m3, with a hygienic standard of 0.2 mg/m3.
# 522004376457
Unscheduled inspection
Start date: 2020-03-18, end date: 2020-04-14, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Nizhegorodskoi oblasti
Purpose of inspection: in order to consider the appeals of vh 1835zh2020 from 17022020 1842zh2020 from 17022020 1985zh2020 from 19022020 2012zh2020 from 19022020 containing information about the threat of harm to the life and health of citizens
# 522004213106
Unscheduled inspection
Start date: 2020-01-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 521904116076
Unscheduled inspection
Start date: 2019-12-18, end date: 2020-01-18, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Nizhegorodskoi oblasti
Purpose of inspection: verification of the execution of the instructions on the elimination of identified violations 19021710 dated 27082019, the deadline for which expired on 25/12/2019. the order on the elimination of identified violations
# 521903970969
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-22, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Nizhegorodskoi oblasti
Purpose of inspection: for the purpose of considering the appeal of vh 12192j2019 dated 21102019 contains information about the facts of the threat of harm to the life and health of citizens in the apartment at the address Mr. Nizhny Novgorod Levoberezhnaya str. d 3 kv 133 there is an extraneous pungent odor the odor present may be the release of ammonia which can lead to the emergence and spread of mass non-communicable diseases of children and adults
# 521903019656
Unscheduled inspection
Start date: 2019-08-22, end date: 2019-09-18, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Nizhegorodskoi oblasti
Purpose of inspection: vx 9154j2019 from 09082019 and 9166j2019 from 09082019 containing information about the facts of the threat of harm to the life and health of citizens in the apartment at the address Mr. City Okskaya str. d 2 kv 178 there is a pungent odor that can lead to the emergence and spread of mass non-communicable diseases of children and adults The applicant requests to conduct a study of the air of the living room for the content of ammonia
# 521904186280
Unscheduled inspection
Start date: 2019-01-31, end date: 2019-02-27, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Nizhegorodskoi oblasti
Purpose of inspection: Control over the execution of a previously issued prescription
# 521801997018
Unscheduled inspection
Start date: 2018-10-23, end date: 2018-10-24, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out in order to verify compliance with the requirements of the regulations dated 26072018 51903020484 51903020485 issued to the developer Stroyservice LLC to assess the compliance of work and construction materials used in the construction process with the requirements of technical regulations norms and rules and design documentation The task of verification is to monitor compliance with the requirements of urban planning legislation and other regulatory legal acts in the field of construction fire sanitary epidemiological and other safety
# 521801908565
Unscheduled inspection
Start date: 2018-10-11, end date: —, duration: —
Authority: —
Purpose of inspection:
# 521800658190
Unscheduled inspection
Start date: 2018-09-13, end date: 2018-09-17, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out on the basis of notices from StartStroy LLC on the completion dates of works subject to inspection during the construction of the capital construction facility vh 4242 dated 04072018 on the elimination of violations during the construction of the capital construction facility vh 4126 dated 02072018 vh 4372 dated 09072018 of the approved inspection program for the capital construction facility and also in order to verify compliance with the requirements of the regulations dated 28052018 519030104107 issued to the developer LLC "StartStroy" dated 28052018 519030104119 issued to the general contractor LLC "NSK Region" to assess the compliance of work and construction materials used in the construction process with the requirements of technical regulations, norms and rules and design documentation, including during the construction phase installation of structures of the aboveground part The task of verification is to monitor compliance with the requirements of urban planning legislation and other normative legal acts in the field construction
# 521800338612
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-10, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out on the basis of the notification of LLC StartStroy on the elimination of violations during the construction of the capital construction facility vh 729 dated 19022018 the notification of LLC IC QUiD on the elimination of violations during the construction of the capital construction facility vh 887 dated 28022018 of the approved program of inspections for the capital construction facility in order to verify compliance with the requirements of the regulations dated 04122017 519030104378 issued to the developer LLC StartStroy" 519030104377 issued to the general contractor SK KViD LLC to assess the compliance of the work and the building materials used in the construction process with the requirements of technical regulations, norms and rules and design documentation, including during the construction stages installation of structures of the aboveground part monolithic frame installation of structures of the aboveground part enclosing structures The task of verification control over compliance with the requirements of urban planning legislation and other regulatory legal acts in the field of construction
# 521800374279
Unscheduled inspection
Start date: 2018-05-24, end date: 2018-05-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out on the basis of notices from StartStroy LLC on the elimination of violations during the construction of the capital construction facility vx 95 dated 12012018 on the completion dates of works subject to inspection during the construction of the capital construction facility vx 625 dated 12022018 of the approved inspection program for the capital construction facility and also in order to verify compliance with the requirements of the regulation dated 30112017 519030104373 issued to the developer StartStroy LLC assessment of compliance of work and construction materials used in the construction process with the requirements of technical regulations norms and rules and design documentation, including during the construction phase installation of structures of the underground part The task of verification is to monitor compliance with the requirements of urban planning legislation and other normative legal acts in the field of construction
# 521800012935
Unscheduled inspection
Start date: 2018-01-31, end date: 2018-02-02, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out on the basis of notices from StartStroy LLC on the elimination of violations during the construction of the capital construction facility vh 5785 dated 04122017 on the completion dates of works to be checked during the construction of the capital construction facility vh 93 dated 12012018 and also in order to verify compliance with the requirements of the regulation dated 16112017 519030104362 issued to the developer LLC StartStroy to assess the conformity of work and applied construction materials in the construction process meet the requirements of technical regulations norms and rules and design documentation, including during the construction phase of the aboveground structure, the task of verification is to monitor compliance with the requirements of urban planning legislation and other regulatory legal acts in the field of construction
# 52170802774166
Unscheduled inspection
Start date: 2017-11-15, end date: 2017-11-16, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: verification in order to verify compliance with the requirements of the regulation from 04072017 519030104162 issued to the developer LLC StartStroy to assess the compliance of work and construction materials used in the construction process with the requirements of technical regulations norms and rules and design documentation The task of verification is to monitor compliance with the requirements of urban planning legislation and other regulatory legal acts in the field of construction
# 52170701797993
Unscheduled inspection
Start date: 2017-07-19, end date: 2017-07-21, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out on the basis of notices from StartStroy LLC on the elimination of violations during the construction of the capital construction facility vh 1783 from 19042017 on the completion date of works to be checked during the construction of the capital construction facility vh 2475 from 06062017 and also in order to verify compliance with the requirements of the regulations from 10042017 51903010498 to the contractor NSK Region LLC 51903010497 issued to the developer StartStroy LLC assessment of compliance of the work and the construction materials used in the construction process with the requirements of technical regulations norms and rules and design documentation, including during the construction phase of the aboveground structure, the task of verification control over compliance with the requirements of urban planning legislation and other normative legal acts in the field of construction and other safety
# 52170701811664
Unscheduled inspection
Start date: 2017-07-28, end date: 2017-08-01, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out on the basis of notices from StartStroy LLC on the elimination of violations during the construction of the capital construction facility vx 1650 from 13042017 of the approved program of inspections for the capital construction facility, as well as in order to verify compliance with the requirements of the regulations from 24032017 51903010480 issued to the general contractor GC "Creator" 51903010481 issued to the developer LLC "StartStroy" assessment of compliance with the work performed and applied construction materials in the construction process to the requirements of technical regulations norms and rules and design documentation, including during the construction phase of the network of engineering and technical support in PM of internal and external networks and landscaping, the task of checking control over compliance with the requirements of urban planning legislation and other normative legal acts in the field of construction and other safety
# 52170701693282
Unscheduled inspection
Start date: 2017-06-16, end date: 2017-06-19, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out in order to verify compliance with the requirements of the regulations from 18042017 51903020487 51903020488 519030104111 issued to the developer to the technical customer, the person carrying out the construction of LLC StartStroy, assessment of compliance of work and construction materials used in the construction process with the requirements of technical regulations norms and rules and design documentationthe task of verification is monitoring compliance with the requirements of urban planning legislation and other normative legal acts in the field of construction of fire sanitary and epidemiological and other security
# 52170701687055
Unscheduled inspection
Start date: 2017-06-14, end date: 2017-06-15, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Nizhegorodskoi oblasti
Purpose of inspection: the inspection is carried out in order to verify the fulfillment of the requirements of the regulations from 13042017 519030104110 51903020484 51903020483 issued to the developer to the technical customer, the person carrying out the construction of LLC StartStroy, to assess the compliance of work and construction materials used in the construction process with the requirements of technical regulations norms and rules and design documentationthe task of verification is to monitor compliance with the requirements of urban planning legislation and other normative legal acts in the field of construction of fire sanitary and epidemiological and other security