# 342105340051
Unscheduled inspection
Start date: 2021-02-01, end date: 2021-03-01, duration: 20
Authority: Gosudarstvennaya inspekciya truda v Volgogradskoi oblasti
Purpose of inspection: Implementation of federal state supervision over compliance by a legal entity or individual entrepreneur with the mandatory requirements of labor legislation and other regulatory legal acts containing labor law norms, ensuring the implementation of state guarantees of labor rights and freedoms of citizens, creating favorable working conditions, protecting the rights and interests of employees and employers; to prevent harm to the life and health of employees; notification to the Company Limited liability Company " Pipeline coatings and technologies"vh. no. 34/6-99-20- FROM 17.12.2020 about the accident, motivated presentation of the chief State Labor Inspector (Labor Protection) Dimova N.P.


# 34160701189605
Unscheduled inspection
Start date: 2016-12-01, end date: 2016-12-09, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose of the assessment is to assess the conformity of the Facility with the requirements of technical regulations of other regulatory legal acts and project documentation. The purpose of this audit is to ensure that the Facility meets the requirements of technical regulations of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements regarding the compliance of construction works, their results and the construction materials used with the requirements of technical regulations of project documentation


# 34160700810706
Unscheduled inspection
Start date: 2016-10-28, end date: 2016-11-03, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose of the assessment is to assess the conformity of the Facility with the requirements of technical regulations of other regulatory legal acts and project documentation. The purpose of this audit is to ensure that the Facility meets the requirements of technical regulations of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements regarding the compliance of construction works, their results and the construction materials used with the requirements of technical regulations of project documentation


# 34160601722695
Unscheduled inspection
Start date: 2016-07-19, end date: 2016-07-27, duration:
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to assess the compliance of activities carried out at the Facility with the requirements of the urban planning legislation of the Russian Federation as well as energy efficiency requirements and equipment requirements of the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation tasks prevention detection and suppression of violations of the legislation of the Russian Federation, including technical regulations and project documentation Subject compliance with mandatory requirements in relation to compliance construction works, their results and the construction materials used, the requirements of technical regulations, design documentation, the availability of a construction permit, and the fulfillment of established requirements for admission to construction work