# 002005239483
Unscheduled inspection
Start date: 2020-12-03, end date: 2020-12-23, duration: 15
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora DV Kolegovym ot 11112020 3502020Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenennyh stroitelnyh materialov v processe rekonstrukcii obekta kapitalnogo stroitelstva «Rashody na meropriyatiya po povysheniyu urovnya obustroistva avtomobilnyh dorog federalnogo znacheniya Ustroistvo stacionarnogo elektricheskogo osvescheniya na avtomobilnoi doroge R402 TyumenYAlutorovskIshimOmsk na uchastke km 480+950 km 482+900 g Tyukalinsk km 486+000 km 486+820 g Tyukalinsk km 534165 km 536+770 np Bekeshevo Omskaya oblast» raspolozhennogo Omskaya oblast Tyukalinskii raion a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002005187396
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-30, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora ot 18092020 g 464Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Rashody na meropriyatiya po povysheniyu urovnya obustroistva avtomobilnyh dorog federalnogo znacheniya Ustroistvo stacionarnogo elektricheskogo osvescheniya na avtomobilnoi doroge R256 «CHuiskii trakt» Novosibirsk Barnaul GornoAltaisk granica s Mongoliei na uchastkah km 55+970 km 56+400 km 57+785 km 58+220 km 70+300 km 70+600 km 75+010 i km 75+970 km 78+950 km 79+280 km 79+885 km 81+222» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002005144081
Unscheduled inspection
Start date: 2020-10-05, end date: 2020-10-23, duration: 15
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Rekonstrukciya avtomobilnoi dorogi R255 «Sibir» NovosibirskKemerovoKrasnoyarskIrkutsk na uchastke km 149+700km 158+200 Kemerovskaya oblast» raspolozhennogo po adresu Kemerovskaya oblast YUrginskii raion na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora AA Pleshivcevym 2503419 ot 02102019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 002005144079
Unscheduled inspection
Start date: 2020-10-05, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002005144073
Unscheduled inspection
Start date: 2020-10-05, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004473766
Unscheduled inspection
Start date: 2020-08-04, end date: 2020-08-31, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya na osnovanii Izvescheniya ob okonchanii stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva 1 ot 28072020 vh 3418765 ot 28072020Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Rekonstrukciya stroitelstvo avtomobilnoi dorogi M51 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity na uchastke km 1392 km 1422 Novosibirskaya oblast» 1 etap a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002004475094
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-09-11, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the Inspection Program approved by the Deputy Head of the Siberian Directorate of Rostechnadzor dated 03072020 449the purpose of this inspection is to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, the subject of this inspection is to verify the compliance of the work and the construction materials used in during the construction of the capital construction facility "Construction and reconstruction of sections of the highway R254 Irtysh ChelyabskKurganOmskNovosibirsk Reconstruction of the highway R254 Irtysh ChelyabskKurganOmskNovosibirsk on the site km 1072+000 km 1077+000" as well as the results of such work according to the requirements of the project documentation approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the equipment requirements of the capital construction facility construction with metering devices for the energy resources used, the availability of a construction permit, the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004251946
Unscheduled inspection
Start date: 2020-01-31, end date: 2020-02-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 27062019 g 293Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentacii7 Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo avtomobilnoi dorogi M52 «CHuiskii trakt» ot Novosibirska cherez Biisk do granicy s Mongoliei na uchastke NovosibirskLinevo 1 etap km 14 km 34 Novosibirskaya oblast» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 001903978883
Unscheduled inspection
Start date: 2019-11-21, end date: 2019-12-18, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 27062019 g 293Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo avtomobilnoi dorogi M52 «CHuiskii trakt» ot Novosibirska cherez Biisk do granicy s Mongoliei na uchastke NovosibirskLinevo 1 etap km 14 km 34 Novosibirskaya oblast» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 001903080326
Unscheduled inspection
Start date: 2019-10-07, end date: 2019-10-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva Stroitelstvo avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 481+500km 486+000 Kemerovskaya oblast raspolozhennogo po adresu Kemerovskaya oblast Mariinskii raion na osnovanii na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora AA Pleshivcevym 2502419 ot 26082019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 001902883623
Unscheduled inspection
Start date: 2019-07-22, end date: 2019-08-16, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 27062019 355Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the construction process of capital construction object "Construction and reconstruction of the road M53 M55 M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita Reconstruction of the construction of the road M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita on a plot of 1392 km km 1422 Novosibirsk oblast" stage 1" as well as the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation further, the Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the Code and the information model, or if the formation and maintenance of information models are required in accordance with the requirements of the Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources the presence of a building permit compliance with the requirements of parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001902779597
Unscheduled inspection
Start date: 2019-06-10, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001801540728
Unscheduled inspection
Start date: 2018-09-13, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800626076
Unscheduled inspection
Start date: 2018-07-25, end date: 2018-08-21, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of the law on urban development by the person carrying out the construction, including the requirements of technical regulations of project documentation. the construction materials used and the results during the reconstruction of the capital construction facility, as well as the results of such work, the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 00170802776677
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-11-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: S celyu kontrolya sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity na uchastke km 1392 km 1422 Novosibirskaya oblast» 2 etap raspolozhennogo po adresu Novosibirskaya oblast na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora 2821 ot 10022015 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701845269
Unscheduled inspection
Start date: 2017-08-07, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701841210
Unscheduled inspection
Start date: 2017-08-01, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701841195
Unscheduled inspection
Start date: 2017-08-01, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701684860
Unscheduled inspection
Start date: 2017-06-01, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701621617
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-26, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: celikontrol sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstvazadachi preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciipredmetsootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701451895
Unscheduled inspection
Start date: 2017-03-10, end date: 2017-04-06, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: objectives monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation requirements for energy conservation and energy efficiency improvement tasks prevention detection and suppression of violations of legislation on urban development by the developer and technical customer, including the requirements of technical regulations of project documentationsubject compliance of work performed and applied building materials as well as the results of such work with the requirements of technical regulations of project documentation This includes the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation.
# 00170701308891
Unscheduled inspection
Start date: 2017-01-23, end date: 2017-02-03, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Vypolnenie proveryaemym licom predpisaniya ot 30 sentyabrya 2016 goda 2502172 Sibirskogo upravleniya Rostehnadzora
# 00160701048871
Unscheduled inspection
Start date: 2016-10-31, end date: 2016-11-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celi kontrol sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnostiZadachi preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmet sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00160700323516
Unscheduled inspection
Start date: 2016-09-06, end date: 2016-09-30, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora v sootvetstvii s programmoi provedeniya proverok ot 19012015 goda 293 korrektirovkaZadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00160601410325
Unscheduled inspection
Start date: 2016-01-11, end date: 2016-01-29, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of state construction supervision
# 422100187401
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: 14
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva: «Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M-51, M-53, M-55 «Baikal» - ot CHelyabinska cherez Kurgan, Omsk, Novosibirsk, Kemerovo, Krasnoyarsk, Irkutsk, Ulan-Ude do CHity. Rekonstrukciya avtomobilnoi dorogi R-255 «Sibir» Novosibirsk-Kemerovo-Krasnoyarsk-Irkutsk na uchastke km 149+700-km 158+200, Kemerovskaya oblast», raspolozhennogo po adresu: Kemerovskaya oblast, YUrginskii raion, na osnovanii Programmy provedeniya proverok, utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Pleshivcevym A.A. ot 02.10.2019 № 25-034-19.
Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie, vyyavlenie i presechenie dopuschennyh zastroischikom, zakazchikom, a takzhe licom, osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom (dalee - podryadchik), narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, proektnoi dokumentacii.
Predmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolnenie rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii),
# 422100187386
Unscheduled inspection
Start date: 2021-05-11, end date: —, duration: 14
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva: «Stroitelstvo avtomobilnoi dorogi R-255 «Sibir» Novosibirsk - Kemerovo-Krasnoyarsk-Irkutsk na uchastke km 481+500-km 486+000, Kemerovskaya oblast», raspolozhennogo po adresu: Kemerovskaya oblast, Mariinskii raion, na osnovanii Programmy provedeniya proverok, utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Pleshivcevym A.A. ot 26.08.2019 № 25-024-19.
Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie, vyyavlenie i presechenie dopuschennyh zastroischikom, zakazchikom, a takzhe licom, osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom (dalee - podryadchik), narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, proektnoi dokumentacii.
Predmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolnenie rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 422100133583
Unscheduled inspection
Start date: 2021-04-08, end date: 2021-04-21, duration: 7
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka provoditsya na osnovanii izvescheniya ob okonchanii stroitelstva № 1 ot 31.03.2021 (vh. № 343/4550 ot 01.04.2021).
Zadachami nastoyaschei proverki yavlyaetsya: preduprezhdenie, vyyavlenie i presechenie dopuschennyh zastroischikom, zakazchikom, a takzhe licom, osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom (dalee podryadchik), narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, v tom chisle proektnoi dokumentacii.
Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe rekonstrukcii obekta kapitalnogo stroitelstva «Rashody na meropriyatiya po povysheniyu urovnya obustroistva avtomobilnyh dorog federalnogo znacheniya. Ustroistvo stacionarnogo elektricheskogo osvescheniya na avtomobilnoi doroge R-402 Tyumen-YAlutorovsk-Ishim-Omsk na uchastke km 480+950 - km 482+900 (g. Tyukalinsk), km 486+000 - km 486+820 (g. Tyukalinsk), km 534-165 km 536+770 (n.p. Bekeshevo), Omskaya oblast, raspolozhennogo: Omskaya oblast, Tyukalinskii raion, a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.
# 422000068969
Unscheduled inspection
Start date: 2021-03-17, end date: 2021-03-25, duration: 7
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya na osnovanii postupleniya Izvescheniya ot 05.03.2021 №1 ob okonchanii stroitelstva (rekonstrukcii) obekta kapitalnogo stroitelstva (ot 09.03.2021 vh. № 341/2563).
Zadachei nastoyaschei proverki yavlyaetsya: preduprezhdenie, vyyavlenie i presechenie dopuschennyh zastroischikom, zakazchikom, a takzhe licom, osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom, narushenii zakonodatelstva o gradostroitelnoi deyatelnosti, proektnoi dokumentacii.
Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Rashody na meropriyatiya po povysheniyu urovnya obustroistva avtomobilnyh dorog federalnogo znacheniya. Ustroistvo stacionarnogo elektricheskogo osvescheniya na avtomobilnoi doroge R-255 «Sibir» Novosibirsk-Kemerovo-Krasnoyarsk-Irkutsk na uchastke km 53+350 – km 62+100 (r.p. Moshkovo), Novosibirskaya oblast», a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15, 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii (s uchetom izmenenii, vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii) i (ili) informacionnoi modeli (v sluchae, esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii), v tom chisle trebovaniyam energeticheskoi effektivnosti (za isklyucheniem obektov kapitalnogo stroitelstva, na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya) i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov; nalichiya razresheniya na stroitelstvo; vypolneniya trebovanii, ustanovlennyh chastyami 2, 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii.
# 542100094337
Unscheduled inspection
Start date: 2021-02-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002005239483
Unscheduled inspection
Start date: 2020-12-03, end date: 2020-12-23, duration: 15
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora DV Kolegovym ot 11112020 3502020Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenennyh stroitelnyh materialov v processe rekonstrukcii obekta kapitalnogo stroitelstva «Rashody na meropriyatiya po povysheniyu urovnya obustroistva avtomobilnyh dorog federalnogo znacheniya Ustroistvo stacionarnogo elektricheskogo osvescheniya na avtomobilnoi doroge R402 TyumenYAlutorovskIshimOmsk na uchastke km 480+950 km 482+900 g Tyukalinsk km 486+000 km 486+820 g Tyukalinsk km 534165 km 536+770 np Bekeshevo Omskaya oblast» raspolozhennogo Omskaya oblast Tyukalinskii raion a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002005187396
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-30, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora ot 18092020 g 464Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Rashody na meropriyatiya po povysheniyu urovnya obustroistva avtomobilnyh dorog federalnogo znacheniya Ustroistvo stacionarnogo elektricheskogo osvescheniya na avtomobilnoi doroge R256 «CHuiskii trakt» Novosibirsk Barnaul GornoAltaisk granica s Mongoliei na uchastkah km 55+970 km 56+400 km 57+785 km 58+220 km 70+300 km 70+600 km 75+010 i km 75+970 km 78+950 km 79+280 km 79+885 km 81+222» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002005187416
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-30, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora ot 18092020 g 463Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Rashody na meropriyatiya po povysheniyu urovnya obustroistva avtomobilnyh dorog federalnogo znacheniya Ustroistvo stacionarnogo elektricheskogo osvescheniya na avtomobilnoi doroge R255 «Sibir» NovosibirskKemerovoKrasnoyarskIrkutsk na uchastke km 53+350 km 62+100 rp Moshkovo Novosibirskaya oblast» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002005144081
Unscheduled inspection
Start date: 2020-10-05, end date: 2020-10-23, duration: 15
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Rekonstrukciya avtomobilnoi dorogi R255 «Sibir» NovosibirskKemerovoKrasnoyarskIrkutsk na uchastke km 149+700km 158+200 Kemerovskaya oblast» raspolozhennogo po adresu Kemerovskaya oblast YUrginskii raion na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora AA Pleshivcevym 2503419 ot 02102019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 002005144079
Unscheduled inspection
Start date: 2020-10-05, end date: 2020-10-23, duration: 15
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva Stroitelstvo avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 481+500km 486+000 Kemerovskaya oblast raspolozhennogo po adresu Kemerovskaya oblast Mariinskii raion na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora AA Pleshivcevym 2502419 ot 26082019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 002005144073
Unscheduled inspection
Start date: 2020-10-05, end date: 2020-10-23, duration: 15
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 436+000km 465+000 obhod g Mariinska Kemerovskaya oblast raspolozhennogo po adresu RF Kemerovskaya oblast zemli Mariinskogo i CHebulinskogo raiona na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora MV Serbinovichem 4201415 ot 06052019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 002004473766
Unscheduled inspection
Start date: 2020-08-04, end date: 2020-08-31, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya na osnovanii Izvescheniya ob okonchanii stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva 1 ot 28072020 vh 3418765 ot 28072020Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Rekonstrukciya stroitelstvo avtomobilnoi dorogi M51 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity na uchastke km 1392 km 1422 Novosibirskaya oblast» 1 etap a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002004475681
Unscheduled inspection
Start date: 2020-08-24, end date: 2020-09-18, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 30042020 g 293Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo avtomobilnoi dorogi M52 «CHuiskii trakt» ot Novosibirska cherez Biisk do granicy s Mongoliei na uchastke Novosibirsk Linevo 1 etap km 14 km 34 Novosibirskaya oblast» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002004475094
Unscheduled inspection
Start date: 2020-08-17, end date: 2020-09-11, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the Inspection Program approved by the Deputy Head of the Siberian Directorate of Rostechnadzor dated 03072020 449the purpose of this inspection is to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, the subject of this inspection is to verify the compliance of the work and the construction materials used in during the construction of the capital construction facility "Construction and reconstruction of sections of the highway R254 Irtysh ChelyabskKurganOmskNovosibirsk Reconstruction of the highway R254 Irtysh ChelyabskKurganOmskNovosibirsk on the site km 1072+000 km 1077+000" as well as the results of such work according to the requirements of the project documentation approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the equipment requirements of the capital construction facility construction with metering devices for the energy resources used, the availability of a construction permit, the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004443553
Unscheduled inspection
Start date: 2020-06-30, end date: 2020-07-28, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 30042020 g 293Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo avtomobilnoi dorogi M52 «CHuiskii trakt» ot Novosibirska cherez Biisk do granicy s Mongoliei na uchastke Novosibirsk Linevo 1 etap km 14 km 34 Novosibirskaya oblast» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 002004413000
Unscheduled inspection
Start date: 2020-05-25, end date: 2020-06-22, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 30042020 g 355Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the construction process of capital construction object "Construction and reconstruction of the road M53 M55 M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita Reconstruction of the construction of the road M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita on a plot of 1392 km km 1422 Novosibirsk oblast" stage 1" as well as the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation further, the Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the Code and the information model, or if the formation and maintenance of information models are required in accordance with the requirements of the Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources the presence of a building permit compliance with the requirements of parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 542004298425
Unscheduled inspection
Start date: 2020-02-18, end date: —, duration: —
Authority: Ministerstvo prirodnyh resursov i ekologii Novosibirskoi oblasti
Purpose of inspection:
# 002004252141
Unscheduled inspection
Start date: 2020-01-31, end date: 2020-02-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 27062019 355Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project документации7 the Subject of this test is to verify compliance of work and construction materials used in the construction process of capital construction object "Construction and reconstruction of the road M53 M55 M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita Reconstruction of the construction of the road M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita on a plot of 1392 km km 1422 Novosibirsk oblast" stage 1" as well as the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation further, the Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the Code and the information model, or if the formation and maintenance of information models are required in accordance with the requirements of the Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources the presence of a building permit compliance with the requirements of parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004251946
Unscheduled inspection
Start date: 2020-01-31, end date: 2020-02-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 27062019 g 293Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentacii7 Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo avtomobilnoi dorogi M52 «CHuiskii trakt» ot Novosibirska cherez Biisk do granicy s Mongoliei na uchastke NovosibirskLinevo 1 etap km 14 km 34 Novosibirskaya oblast» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 001903995508
Unscheduled inspection
Start date: 2019-12-02, end date: 2019-12-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Rekonstrukciya avtomobilnoi dorogi R255 «Sibir» NovosibirskKemerovoKrasnoyarskIrkutsk na uchastke km 149+700km 158+200 Kemerovskaya oblast» raspolozhennogo po adresu Kemerovskaya oblast YUrginskii raion na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora AA Pleshivcevym 2503419 ot 02102019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 001903978883
Unscheduled inspection
Start date: 2019-11-21, end date: 2019-12-18, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 27062019 g 293Predmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo avtomobilnoi dorogi M52 «CHuiskii trakt» ot Novosibirska cherez Biisk do granicy s Mongoliei na uchastke NovosibirskLinevo 1 etap km 14 km 34 Novosibirskaya oblast» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 15_2 i 15_3 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 3_8 i 3_9 stati 49 Gradostroitelnogo kodeksa Rossiiskoi Federacii i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Gradostroitelnogo kodeksa Rossiiskoi Federacii v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichiya razresheniya na stroitelstvo vypolneniya trebovanii ustanovlennyh chastyami 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 551904036000
Unscheduled inspection
Start date: 2019-11-28, end date: 2019-12-24, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Omskoi oblasti
Purpose of inspection: kontrol ispolneniya predpisaniya po ustraneniyu narushenii ustanovlennyh trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii ot 21052018 4 srok ispolneniya kotorogo ustanovlen do 01122019 goda
# 001903978951
Unscheduled inspection
Start date: 2019-11-19, end date: 2019-12-16, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 27062019 355Zadachei nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Rekonstrukciya stroitelstvo avtomobilnoi dorogi M51 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity na uchastke km 1392 km 1422 Novosibirskaya oblast» 1 etap» a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s chastyami 15 152 i 153 stati 48 Gradostroitelnogo kodeksa Rossiiskoi Federacii dalee Kodeks proektnoi dokumentacii s uchetom izmenenii vnesennyh v proektnuyu dokumentaciyu v sootvetstvii s chastyami 38 i 39 stati 49 Kodeksa i ili informacionnoi modeli v sluchae esli formirovanie i vedenie informacionnoi modeli yavlyayutsya obyazatelnymi v sootvetstvii s trebovaniyami Kodeksa v tom chisle trebovaniyam energeticheskoi effektivnosti za isklyucheniem obektov kapitalnogo stroitelstva na kotorye trebovaniya energeticheskoi effektivnosti ne rasprostranyayutsya i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii
# 001903080326
Unscheduled inspection
Start date: 2019-10-07, end date: 2019-10-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva Stroitelstvo avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 481+500km 486+000 Kemerovskaya oblast raspolozhennogo po adresu Kemerovskaya oblast Mariinskii raion na osnovanii na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora AA Pleshivcevym 2502419 ot 26082019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 001903080049
Unscheduled inspection
Start date: 2019-10-07, end date: 2019-10-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 436+000km 465+000 obhod g Mariinska Kemerovskaya oblast raspolozhennogo po adresu RF Kemerovskaya oblast zemli Mariinskogo i CHebulinskogo raiona na osnovanii na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora MV Serbinovichem 4201415 ot 06052019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 001902967359
Unscheduled inspection
Start date: 2019-08-19, end date: 2019-09-13, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora Kolegovym DV ot 27062019 g 293
# 001902883623
Unscheduled inspection
Start date: 2019-07-22, end date: 2019-08-16, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 27062019 355Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the construction process of capital construction object "Construction and reconstruction of the road M53 M55 M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita Reconstruction of the construction of the road M51 "Baikal" from Chelyabinsk through Kurgan, Omsk, Novosibirsk, Kemerovo, the Krasnoyarsk, Irkutsk, Ulan-Ude to Chita on a plot of 1392 km km 1422 Novosibirsk oblast" stage 1" as well as the results of such work requirements approved in accordance with paragraphs 152 and 153 of 15 of article 48 of the town planning code of the Russian Federation further, the Code project documentation to reflect changes made to the project documentation in accordance with paragraphs 38 and 39 of article 49 of the Code and the information model, or if the formation and maintenance of information models are required in accordance with the requirements of the Code, including the requirements of energy efficiency with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources the presence of a building permit compliance with the requirements of parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001902779597
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora za obektom kapitalnogo stroitelstva Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 436+000km 465+000 obhod g Mariinska Kemerovskaya oblast raspolozhennogo po adresu RF Kemerovskaya oblast zemli Mariinskogo i CHebulinskogo raiona na osnovanii na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravleniya Rostehnadzora MV Serbinovichem 4201415 ot 06052019 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 001802162865
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-21, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: proverka provoditsya s celyu ispolneniya Programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora AT Mironenko ot 01052015 g 220202 Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom zakazchikom a takzhe licom osuschestvlyayuschim stroitelstvo na osnovanii dogovora s zastroischikom ili zakazchikom dalee podryadchik narushenii zakonodatelstva o gradostroitelnoi deyatelnosti proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 436+000km 465+000 obhod g Mariinska Kemerovskaya oblast» a takzhe rezultatov takih rabot proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 3 i 3_1 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 001802090045
Unscheduled inspection
Start date: 2018-11-15, end date: 2018-12-12, duration: —
Authority: Upravlenie gosudarstvennogo aviacionnogo nadzora i nadzora za obespecheniem transportnoi bezopasnosti po Sibirskomu federalnomu okrugu Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu gosudarstvennogo kontrolya nadzora za soblyudeniem trebovanii zakonodatelstva Rossiiskoi Federacii po obespecheniyu transportnoi bezopasnosti na osnovanii p 1 ch 2 st 10 Federalnogo zakona ot 26122008 294FZ «O zaschite prav yuridicheskih lic i individualnyh predprinimatelei pri osuschestvlenii gosudarstvennogo kontrolya nadzora i municipalnogo kontrolya» v svyazi s istecheniem sroka ispolneniya predpisanii ZS 20170610132DH ot 10082017 ZS 20170610133DH ot 10082017 ZS 20170610134DH ot 10082017 ZS 20170610158DH ot 24082017 vydannogo FKU «Sibupravtodor» srok ispolneniya kotoryh istek 06112018 zadachei nastoyaschei proverki yavlyaetsya provedenie meropriyatii po nadzoru v chasti vypolneniya FKU «Sibupravtodor» trebovanii zakonodatelstva Rossiiskoi Federacii po obespecheniyu transportnoi bezopasnosti 7 Predmetom nastoyaschei proverki yavlyaetsya soblyudenie FKU «Sibupravtodor» trebovanii v oblasti obespecheniya transportnoi bezopasnosti po vypolneniyu predpisanii ZS 20170610132DH ot 10082017 ZS 20170610133DH ot 10082017 ZS 20170610134DH ot 10082017 ZS 20170610158DH ot 24082017 i prinyatym po nim meram
# 001801540728
Unscheduled inspection
Start date: 2018-09-13, end date: 2018-10-05, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of the law on urban development by the person carrying out the construction, including the requirements of technical regulations of project documentation. the construction materials used and the results during the reconstruction of the capital construction facility, as well as the results of such work, the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001800626076
Unscheduled inspection
Start date: 2018-07-25, end date: 2018-08-21, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of the law on urban development by the person carrying out the construction, including the requirements of technical regulations of project documentation. the construction materials used and the results during the reconstruction of the capital construction facility, as well as the results of such work, the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001800387697
Unscheduled inspection
Start date: 2018-05-28, end date: 2018-06-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of the law on urban development by the person carrying out the construction, including the requirements of technical regulations of project documentation. the construction materials used and the results during the reconstruction of the capital construction facility, as well as the results of such work, the requirements of technical regulations and project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001800341099
Unscheduled inspection
Start date: 2018-05-07, end date: 2018-05-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity Stroitelstvo i rekonstrukciya uchastkov avtomobilnoi dorogi R255 «Sibir» Novosibirsk KemerovoKrasnoyarskIrkutsk na uchastke km 436+000km 465+000 obhod g Mariinska Kemerovskaya oblast» a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov nalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 551800319914
Unscheduled inspection
Start date: 2018-04-23, end date: 2018-05-21, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Omskoi oblasti
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya Predpisaniya po ustraneniyu narushenii v chasti vypolneniya trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii prirodnogo i tehnogennogo haraktera ot 28082017 3 zadachami nastoyaschei proverki yavlyayutsya proverka soblyudeniya trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii
# 551800200440
Unscheduled inspection
Start date: 2018-02-28, end date: 2018-03-28, duration: —
Authority: ZapadnoSibirskoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Cel osuschestvlenie gosudarstvennogo kontrolya nadzora po vypolneniyu predpisaniya ot 26012018 13 srok ispolneniya do 05022018 Zadacha proverka vypolneniya obyazatelnyh trebovanii pri vypolnenii predpisaniya Predmet vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora organov municipalnogo kontrolya
# 551800078740
Unscheduled inspection
Start date: 2018-01-17, end date: 2018-01-26, duration: —
Authority: ZapadnoSibirskoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyu osuschestvlenie gosudarstvennogo kontrolya nadzora sootvetstviya normativnym trebovaniyam k ekspluatacionnomu sostoyaniyu dopustimomu po usloviyam obespecheniya bezopasnosti dorozhnogo dvizheniya avtomobilnoi dorogi obschego polzovaniya federalnogo znacheniya A320 «OmskCHerlakgranica respubliki Kazahstana» v granicah naselennogo punkta Irtysh CHerlakskogo municipalnogo raiona Omskoi oblasti na osnovanii obrascheniya Omskoi oblastnoi pravozaschitnoi obschestvennoi organizacii «Spravedlivost» v lice predsedatelya pravleniya Roledera DV ot 28122017 vhod 8676 v sootvetstvii s motivirovannym predstavleniem ot 11012018 Zadachami nastoyaschei proverki yavlyayutsya proverka vypolneniya obyazatelnyh trebovanii k ekspluatacionnomu sostoyaniyu dopustimomu po usloviyam obespecheniya bezopasnosti dorozhnogo dvizheniya avtomobilnoi dorogi obschego polzovaniya federalnogo znacheniya A320 «OmskCHerlakgranica respubliki Kazahstana» v granicah naselennogo punkta Irtysh CHerlakskogo municipalnogo raiona Omskoi oblasti Predmetom nastoyaschei proverki yavlyaetsya otmetit nuzhnoe po predotvrascheniyu prichineniya vreda zhizni zdorovyu grazhdan
# 55180803061712
Unscheduled inspection
Start date: 2018-01-17, end date: —, duration: —
Authority: ZapadnoSibirskoe Mezhregionalnoe upravlenie gosudarstvennogo avtodorozhnogo nadzora Federalnoi sluzhby po nadzoru v sfere transporta
Purpose of inspection: Nastoyaschaya proverka provoditsya s celyuosuschestvlenie gosudarstvennogo kontrolya nadzora sootvetstviya normativnym trebovaniyam k ekspluatacionnomu sostoyaniyu dopustimomu po usloviyam obespecheniya bezopasnosti dorozhnogo dvizheniya avtomobilnoi dorogi obschego polzovaniya federalnogo znacheniya A320 «OmskCHerlakgranica respubliki Kazahstana» v granicah naselennogo punkta Irtysh CHerlakskogo municipalnogo raiona Omskoi oblasti na osnovanii obrascheniya Omskoi oblastnoi pravozaschitnoi obschestvennoi organizacii «Spravedlivost» v lice predsedatelya pravleniya Roledera DV ot 28122017 vhod 8676 v sootvetstvii s motivirovannym predstavleniem ot 11012018Zadachami nastoyaschei proverki yavlyayutsya proverka vypolneniya obyazatelnyh trebovanii k ekspluatacionnomu sostoyaniyu dopustimomu po usloviyam obespecheniya bezopasnosti dorozhnogo dvizheniya avtomobilnoi dorogi obschego polzovaniya federalnogo znacheniya A320 «OmskCHerlakgranica respubliki Kazahstana» v granicah naselennogo punkta Irtysh CHerlakskogo municipalnogo raiona Omskoi oblasti
# 00170802776631
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-11-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: S celyu kontrolya sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity na uchastke km 1392 km 1422 Novosibirskaya oblast» 1 etap raspolozhennogo po adresu Novosibirskaya oblast na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora 2821 ot 10022015 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170802776677
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-11-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: S celyu kontrolya sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstva «Stroitelstvo i rekonstrukciya avtomobilnoi dorogi M51 M53 M55 «Baikal» ot CHelyabinska cherez Kurgan Omsk Novosibirsk Kemerovo Krasnoyarsk Irkutsk UlanUde do CHity na uchastke km 1392 km 1422 Novosibirskaya oblast» 2 etap raspolozhennogo po adresu Novosibirskaya oblast na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora 2821 ot 10022015 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701845269
Unscheduled inspection
Start date: 2017-08-07, end date: 2017-08-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu kontrolya sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstva «Avtomobilnaya doroga R255 «Sibir» Novosibirsk Kemerovo Krasnoyarsk Irkutsk na uchastke km 436+000 km 465+000 obhod g Mariinska Kemerovskaya oblast» raspolozhennogo po adresu Kemerovskaya oblast zemli Mariinskogo i CHebulinskogo raiona na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora ot 01052015 g 220202 Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva «Avtomobilnaya doroga R255 «Sibir» Novosibirsk Kemerovo Krasnoyarsk Irkutsk na uchastke km 436+000 km 465+000 obhod g Mariinska Kemerovskaya oblast» a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701841210
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: S celyu kontrolya sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstva na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora 2821 ot 10022015 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701841195
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: C celyu kontrolya sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstva na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora 2821 ot 10022015 g Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 55170701831988
Unscheduled inspection
Start date: 2017-07-27, end date: 2017-08-23, duration: —
Authority: Upravlenie gosavtodornadzora po Omskoi oblasti
Purpose of inspection: osuschestvlenie gosudarstvennogo kontrolya nadzora po vypolneniyu predpisaniya ot 27062017 348 proverka vypolneniya trebovanii normativnopravovyh i normativnotehnicheskih aktov pri vypolnenii predpisaniya vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora
# 55170701715897
Unscheduled inspection
Start date: 2017-06-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00170701684860
Unscheduled inspection
Start date: 2017-06-01, end date: 2017-06-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: celikontrol sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstvazadachipreduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciipredmetsootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701621617
Unscheduled inspection
Start date: 2017-05-29, end date: 2017-06-26, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: celikontrol sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstvazadachi preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciipredmetsootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701555804
Unscheduled inspection
Start date: 2017-04-24, end date: 2017-05-19, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu kontrolya sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnosti pri stroitelstve obekta kapitalnogo stroitelstva «Avtomobilnaya doroga R255 «Sibir» Novosibirsk Kemerovo Krasnoyarsk Irkutsk na uchastke km 436+000 km 465+000 obhod g Mariinska Kemerovskaya oblast» raspolozhennogo po adresu Kemerovskaya oblast zemli Mariinskogo i CHebulinskogo raiona na osnovanii programmy provedeniya proverok utverzhdennoi zamestitelem rukovoditelya Sibirskogo upravlenie Rostehnadzora ot 01052015 g 220202 Zadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva «Avtomobilnaya doroga R255 «Sibir» Novosibirsk Kemerovo Krasnoyarsk Irkutsk na uchastke km 436+000 km 465+000 obhod g Mariinska Kemerovskaya oblast» a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 00170701451895
Unscheduled inspection
Start date: 2017-03-10, end date: 2017-04-06, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: objectives monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation requirements for energy conservation and energy efficiency improvement tasks prevention detection and suppression of violations of legislation on urban development by the developer and technical customer, including the requirements of technical regulations of project documentationsubject compliance of work performed and applied building materials as well as the results of such work with the requirements of technical regulations of project documentation This includes the requirements of energy efficiency and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation.
# 00170701308891
Unscheduled inspection
Start date: 2017-01-23, end date: 2017-02-03, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Vypolnenie proveryaemym licom predpisaniya ot 30 sentyabrya 2016 goda 2502172 Sibirskogo upravleniya Rostehnadzora
# 00160701048871
Unscheduled inspection
Start date: 2016-10-31, end date: 2016-11-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celi kontrol sootvetstviya vypolnennyh rabot obyazatelnym trebovaniyam tehnicheskih reglamentov inyh normativnyh pravovyh aktov proektnoi dokumentacii trebovaniyam po energosberezheniyu i povysheniyu energeticheskoi effektivnostiZadachi preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmet sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 70160700915935
Unscheduled inspection
Start date: 2016-10-04, end date: 2016-10-31, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: na osnovanii programmy provedeniya proverok ot 19082016 9616PP1 izvescheniya ob okonchanii stroitelstva ot 27092016
# 00160700323516
Unscheduled inspection
Start date: 2016-09-06, end date: 2016-09-30, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: s celyu osuschestvleniya gosudarstvennogo stroitelnogo nadzora v sootvetstvii s programmoi provedeniya proverok ot 19012015 goda 293 korrektirovkaZadachami nastoyaschei proverki yavlyaetsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom tehnicheskim zakazchikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii tehnicheskih reglamentov proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya sootvetstvie vypolneniya rabot i primenennyh stroitelnyh materialov i rezultatov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovnalichie razresheniya na stroitelstvo vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo Kodeksa Rossiiskoi Federacii
# 70160700061945
Unscheduled inspection
Start date: 2016-08-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160601410325
Unscheduled inspection
Start date: 2016-01-11, end date: 2016-01-29, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of state construction supervision