# 772101325859
Unscheduled inspection
Start date: 2021-11-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772101187529
Unscheduled inspection
Start date: 2021-10-13, end date: 2021-10-26, duration: 10
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100342860
Unscheduled inspection
Start date: 2021-07-12, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772100158697
Unscheduled inspection
Start date: 2021-04-20, end date: 2021-05-19, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: compliance of the work and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results such works meet the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipping the capital construction facility with metering devices for the energy resources used, including checking the elimination of violations of compliance of the completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772100176275
Unscheduled inspection
Start date: 2021-04-26, end date: 2021-04-28, duration: 3
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The purpose of the audit: carrying out control measures in connection with the verification of compliance with the instruction; The tasks of the audit: prevention, detection and suppression of violations of the requirements of project documentation, legislation on urban development by the audited person; The subject of the audit: verification of the elimination of violations specified in the instruction issued by Mosgosstroynadzor
# 772100074284
Unscheduled inspection
Start date: 2021-03-19, end date: 2021-04-15, duration: 20
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: The objectives of the audit: carrying out control measures in connection with the receipt of a notification from the developer (customer); The objectives of the audit: prevention, identification and suppression of violations of the requirements of project documentation, legislation on urban development by the person being checked; The subject of the audit: the fulfillment by the developer of the requirements of part 3.1 of Article 52 of the Urban Planning Code compliance with the performance of works and applied building materials during construction reconstruction of the capital construction facility, as well as the results of such work to the requirements of the design documentation, including the requirements of energy efficiency and the requirements of equipment of the capital construction facility with metering devices for energy resources used, including verification of the elimination of violations of compliance of completed works with the requirements of the design documentation identified during construction control and state construction supervision
# 772005187624
Unscheduled inspection
Start date: 2020-10-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004422706
Unscheduled inspection
Start date: 2020-06-01, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004433296
Unscheduled inspection
Start date: 2020-06-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004372101
Unscheduled inspection
Start date: 2020-03-23, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 772004309006
Unscheduled inspection
Start date: 2020-02-19, end date: 2020-03-19, duration: 20
Authority: Komitet goroda Moskvy po obespecheniyu realizacii investicionnyh proektov v stroitelstve i kontrolyu v oblasti dolevogo stroitelstva
Purpose of inspection: the purpose and objective of this audit is to verify compliance with the mandatory requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects. The subject of an unscheduled documentary audit is compliance with the requirements of legislation on participation in the shared construction of apartment buildings and or other real estate objects
# 772004237100
Unscheduled inspection
Start date: 2020-01-27, end date: —, duration: —
Authority: —
Purpose of inspection:
# 772004200336
Unscheduled inspection
Start date: 2020-01-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903907581
Unscheduled inspection
Start date: 2019-11-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 771903868600
Unscheduled inspection
Start date: 2019-10-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803472068
Unscheduled inspection
Start date: 2019-08-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77190803435289
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-24, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803399875
Unscheduled inspection
Start date: 2019-04-16, end date: 2019-04-29, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 77190803365538
Unscheduled inspection
Start date: 2019-03-11, end date: 2019-03-22, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77190803314062
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-01-26, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: verification of the elimination of violations specified in the order issued by Mosgosstroynadzor
# 77180803278528
Unscheduled inspection
Start date: 2018-11-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803247025
Unscheduled inspection
Start date: 2018-10-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803237978
Unscheduled inspection
Start date: 2018-09-26, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77180803190322
Unscheduled inspection
Start date: 2018-08-01, end date: 2018-08-10, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used