# 002004445130
Unscheduled inspection
Start date: 2020-07-02, end date: 2020-07-15, duration: 10
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted on the basis of the notice of joint stock company "Transmediterranea Siberia" about the end of reconstruction of capital construction object from 18062020 g 1806 3417263 from 19062020 Rin g the purpose of this check is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project документации7 the Subject of this test is to verify compliance of work and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 596 miles 649 inv 500098 Replacement pipe for passing through R Brovka km 61415 km 61430 OSN thread DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004435546
Unscheduled inspection
Start date: 2020-06-15, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004375940
Unscheduled inspection
Start date: 2020-03-27, end date: 2020-04-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 02122019 g 439Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project документации7 the Subject of this test is to verify compliance of work and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 428 miles 455 inv 500102 pipe Replacement on IMOP R Shudelka DOS n км44135 км443926 DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004375933
Unscheduled inspection
Start date: 2020-03-27, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004326329
Unscheduled inspection
Start date: 2020-03-31, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004296469
Unscheduled inspection
Start date: 2020-03-31, end date: 2020-04-27, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 14112019 g 433Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project of documentation of the Subject of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN Aleksandrovskozavodsk км17км325 inv 500294 pipe Replacement on IMOP lake km211 lake км282 palmarosa км208км3147 км3162км3224 of RESn DN 1000 Reconstruction" located at Tomsk oblast Alexandrovsky municipal district of Aleksandrovsky rural settlement as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004296447
Unscheduled inspection
Start date: 2020-03-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 002004185629
Unscheduled inspection
Start date: 2020-01-31, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 002004164969
Unscheduled inspection
Start date: 2020-01-31, end date: 2020-02-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 02122019 g 439Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 428 miles 455 inv 500102 pipe Replacement on IMOP R Shudelka км61415 km 61430 DOS n DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001903986999
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-12-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 10092019 g 428Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN "Aleksandrovskozavodsk" км669км686 inv 500297 pipe Replacement on IMOP R Ob of RESn км66905км6729 км67465км68542 DN 1000 Reconstruction" located at Tomsk oblast Shegarskiy rayon Trubchevskiy rural settlement in Tomsk district Murakowski rural settlement as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001903732113
Unscheduled inspection
Start date: 2019-10-04, end date: 2019-10-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out on the basis of the notice of completion of the construction of the capital construction facility of JSC Transneft Central Siberia dated 23092019 TCS031515106 bx 31319119 dated 24092019, the purpose of this inspection is to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the customer, as well as the person carrying out construction on the basis of a contract with the developer or the customer, the subject of this inspection The purpose of this work is to verify the compliance of the work performed and the construction materials used and the results during the reconstruction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km676km780 INV 500297 Pipe replacement km734km73516 Du1200 Reconstruction" as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation. documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the equipment requirements of the capital construction facility metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902941664
Unscheduled inspection
Start date: 2019-08-13, end date: 2019-08-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in accordance with the notice of completion of reconstruction of capital construction object JSC "Transmediterranea Siberia" 06082019 g 1819 1312982 from 06082019 Rin g the purpose of this check is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or by the customer the contractor further violations of the legislation on town-planning activities including project documents the Subject of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN "Aleksandrovskozavodsk" km 159 240 inv 500291 pipe Replacement 19907км 20262 km DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001902933933
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of the execution by JSC TRANSNEFT Central Siberia of the previously issued regulation 071820MT dated 31052018 under paragraph 1, the term of which expires The tasks of this audit are to monitor the execution by JSC Transneft Central Siberia of the previously issued regulation 071820MT dated 31052018 under paragraph 1, the term of which expires The subject of this audit is the execution by JSC Transneft Central Siberia of the previously issued regulation 071820MT dated 31052018 under paragraph 1 issued by an official of the Siberian Department of Rostechnadzor
# 001902826321
Unscheduled inspection
Start date: 2019-07-22, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902893669
Unscheduled inspection
Start date: 2019-07-26, end date: 2019-08-22, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: based on the notice of completion of the reconstruction of the capital construction facility of JSC TRANSNEFT Central Siberia dated 15072019 1719 vx 1311870 dated 16072019, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit The purpose of this work is to monitor the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by the Legislation of the Russian Federation. in parts 2, 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the reconstruction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km 676 km 780 inv 500297 Pipe replacement at the MN crossing over the Omutnaya river km 74073 km 74088 DN 1200 Reconstruction" located in the Tomsk region Tomsk district
# 001902783666
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Purpose control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 03198MT dated 22042019, the deadline for which expired 07062019 Task control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 03198MT dated 22042019, the deadline for which expired 07062019 Subject is the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 03198MT dated 22042019 by an official of the Siberian Rostechnadzor Management
# 001902783632
Unscheduled inspection
Start date: 2019-06-10, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001902702024
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-06-07, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Based on the Notice of JSC Transneft Central Siberia on the completion of the construction of a capital construction facility dated 22042019 TCC03146076 bx 3139204 dated 23042019, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit is monitoring of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and with the requirements for equipping a capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by the parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the reconstruction of the capital construction facility "MN Igolskotalovoeparable" km 231km 337 inv 500287 Pipe replacement km 29972km 30704 km 31496km 31599 DN 500 Reconstruction" located at the address Tomsk region Kargasoksky district Parabelsky district
# 001902531782
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to implement the Inspection Program approved by the Deputy Head of the Siberian Department of Rostechnadzor on 03/12/2018, 389 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, the subject of this inspection is to verify the compliance of the work and the construction materials used and the results during the reconstruction of the capital construction facility "MN Igolskotalovoeparabel" km 231km 337 inv 500287 Pipe replacement km 29972km 30704 km 31496km 31599 DN 500 Reconstruction" as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the fulfillment of the requirements of parts 2 3 and 3_1 Articles 52 of the Urban Planning Code of the Russian Federation
# 001902531754
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to implement the Inspection Program approved by the Deputy Head of the Siberian Directorate of Rostechnadzor on 03/12/2018, 388 The objectives of this inspection are to prevent, identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, and the subject of this inspection is to verify the compliance of the work and the construction materials used and the results during the reconstruction of the capital construction facility ""MH "Alexandrovsko-Anzhero-Sudzhensk" km 780km 8178 INV 500223 Pipe replacement at the crossing of the Ruchey river km 78287 DN 1200 Reconstruction" as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the fulfillment of the requirements Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902531699
Unscheduled inspection
Start date: 2019-02-25, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001802162888
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-12-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor
# 001802081121
Unscheduled inspection
Start date: 2018-11-07, end date: 2018-12-04, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities and project documentation committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor
# 001802032240
Unscheduled inspection
Start date: 2018-10-31, end date: 2018-11-26, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of the capital construction facility of the Alexandrovsko-Anzherosudzhensk KM 676780 INV 500297 Pipe replacement km 734km 73516 DN 1200 Reconstruction" located at the address Tomsk region Tomsk district based on the inspection program dated 111018 385
# 001800632929
Unscheduled inspection
Start date: 2018-08-20, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001800632928
Unscheduled inspection
Start date: 2018-08-20, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 001802032099
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of the Alexandrovsko-Anzherosudzhensk capital construction facility km 260355 INV 500285 Pipe replacement km 31802km 32705 DN 1000 Reconstruction located at the address Tomsk region Kargasok district on the basis of the completion notice dated 010718g 3181
# 001800567683
Unscheduled inspection
Start date: 2018-07-24, end date: 2018-08-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the Alexandrovskaya RVS20000 m3 33 inv200188 Reconstruction capital construction facility located at the address Alexandrovsky District Alexandrovsky rural Settlement of NPS Alexandrovskaya, Tomsk Region, based on the inspection program approved by the Deputy head of the Siberian Department of Rostechnadzor 2971
# 001800567705
Unscheduled inspection
Start date: 2018-07-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00180803042354
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility "MH Alexandrovskoangerosudzhensk" km 240km260 inv 500165 Pipe replacement km 25201km 25490 Reconstruction" located at the address Tomsk region Kargasok district Kargasok forestry Kargasok district forestry tract "Kargasokskoye"
# 00180803042352
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the construction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km 159km 240 inv 500291 Pipe replacement km 21721km 22142 DN 1200 Reconstruction" located at the address Tomsk region Alexandrovsky district Oktyabrskoye rural settlement on the basis of the inspection program approved by the Deputy Head of the Siberian Department of Rostechnadzor 345
# 00180803042348
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility "MN "Alexandrovskoangerosudzhensk" km 325km159 inv 500164 Pipe replacement km 733km 7393 km 7735km 7853 DU1200RESTRUCTION" located at the address Tomsk region Alexandrovsky district Alexandrovskoye rural settlement
# 00180803042340
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km 260355 INV 500285 Pipe replacement km 31802km 32705 DN 1000 Reconstruction" located in the Tomsk region Kargasok district
# 00180803042369
Unscheduled inspection
Start date: 2018-01-24, end date: 2018-02-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km 260355 INV 500285 Pipe replacement km 30242km 31691 DN 1200 Reconstruction" located in the Tomsk region Kargasok district
# 00170802992746
Unscheduled inspection
Start date: 2017-12-14, end date: 2017-12-27, duration: —
Authority: Federalnaya sluzhba po veterinarnomu i fitosanitarnomu nadzoru
Purpose of inspection: execution of the Rosselkhoznadzor order No. 16032017 252 issued in accordance with the instruction of Deputy Chairman of the Government of the Russian Federation AV Dvorkovich dated 02032017 ADP111304, the objectives of this audit are to assess the compliance of the activities of JSC Transneft Central Siberia with the requirements of the legislation of the Russian Federation in the field of veterinary medicine, to take measures to prevent violations of mandatory requirements of the legislation of the Russian Federation, to verify compliance with mandatory requirements and or requirements established by municipal legal acts
# 00170802831116
Unscheduled inspection
Start date: 2017-11-20, end date: 2017-12-15, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the construction of the capital construction facility NPS Alexandrovskaya RVS20000 m3 33 inv200188 Reconstruction located at the address of the Tomsk region Alexandrovsky district Alexandrovsky rural settlement NPS Alexandrovskaya
# 00170701837882
Unscheduled inspection
Start date: 2017-08-07, end date: 2017-08-18, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The real test is part of the state construction supervision in the construction, reconstruction and capital repair of facilities referred to in paragraph 51 article 6 of the town planning code of the Russian Federation with the exception of objects in respect of which the exercise of state construction supervision of the decrees of the President of the Russian Federation assigned to other Federal bodies of Executive power 10001515438Установить that the real test is conducted to monitor compliance of the performed works with the mandatory requirements of technical regulations of other regulatory legal acts of the design documentation requirements on energy saving and increase of energy efficiency in the construction of capital construction object MN "Aleksandrovskoe Anzherosudzhensk" PS "Parabel" Technological pipelines inv 300046 Reconstruction located at the address Tomsk oblast Parabel district Beregovoy rural district production site of NPS on the basis of the notification of completion of construction ТЦС031510448 from 210717гЗадачами of this review is to prevent detection and suppression approved developer technical customer violations of the legislation on town-planning activities including the requirements of technical regulations of this project documentlibraries check alleycatallies of work and application of building materials and results in the process of reconstruction of capital construction object MN "Aleksandrovskoe Anzherosudzhensk" PS "Parabel" Technological pipelines inv 300046 Reconstruction and the results of such work to the requirements of technical regulations and project documentation including requirements for energy efficiency and the requirements of the equipment of a capital construction object metering devices used energy resourcevalue permission to stroitelstvoimoti requirements of parts 2 and 3 of article 52 of the town planning code of the Russian Federation
# 00170701598861
Unscheduled inspection
Start date: 2017-06-05, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701548333
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the availability and compliance of permitting design and executive documentation with the requirements of the Urban Planning Code of the Russian Federation and other regulatory documents, as well as the requirements of other regulatory legal acts of the Russian Federation and regulatory legal acts of federal executive authorities subject to mandatory execution during construction reconstruction and major repairs of capital construction facilities, verification of the availability of regulatory and technical documentation, verification of the compliance of completed works with the requirements of technical regulations, norms and rules of other regulatory legal acts acts and project documentation during the reconstruction of the capital construction facility
# 00170701548318
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the availability and compliance of permitting design and executive documentation with the requirements of the Urban Planning Code of the Russian Federation and other regulatory documents, as well as the requirements of other regulatory legal acts of the Russian Federation and regulatory legal acts of federal executive authorities subject to mandatory execution during construction reconstruction and major repairs of capital construction facilities, verification of the availability of regulatory and technical documentation, verification of the compliance of completed works with the requirements of technical regulations, norms and rules of other regulatory legal acts acts and project documentation during the reconstruction of the capital construction facility
# 00170701548312
Unscheduled inspection
Start date: 2017-04-17, end date: 2017-04-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the availability and compliance of permitting design and executive documentation with the requirements of the Urban Planning Code of the Russian Federation and other regulatory documents, as well as the requirements of other regulatory legal acts of the Russian Federation and regulatory legal acts of federal executive authorities subject to mandatory execution during construction reconstruction and major repairs of capital construction facilities, verification of the availability of regulatory and technical documentation, verification of the compliance of completed works with the requirements of technical regulations, norms and rules of other regulatory legal acts acts and project documentation during the reconstruction of the capital construction facility
# 00170701440121
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of the capital construction facility.
# 00170701440100
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to control the compliance of the completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of the capital construction facility.
# 00170701440090
Unscheduled inspection
Start date: 2017-03-13, end date: —, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 00170701440079
Unscheduled inspection
Start date: 2017-03-13, end date: 2017-03-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The inspection is carried out in order to monitor the implementation of regulation 2505239 of November 30, 2016 on the elimination of identified offenses, the deadline for which has expired.
# 00160601709558
Unscheduled inspection
Start date: 2016-07-11, end date: 2016-08-05, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of state construction supervision
# 00150600114621
Unscheduled inspection
Start date: 2015-02-10, end date: 2015-03-11, duration: —
Authority: Mezhregionalnoe upravlenie 81 Federalnogo medikobiologicheskogo agentstva
Purpose of inspection: monitoring the implementation of the previously issued instruction on the elimination of identified violations 139 dated 15052012, the deadline for which has expired
# 002004445130
Unscheduled inspection
Start date: 2020-07-02, end date: 2020-07-15, duration: 10
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted on the basis of the notice of joint stock company "Transmediterranea Siberia" about the end of reconstruction of capital construction object from 18062020 g 1806 3417263 from 19062020 Rin g the purpose of this check is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project документации7 the Subject of this test is to verify compliance of work and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 596 miles 649 inv 500098 Replacement pipe for passing through R Brovka km 61415 km 61430 OSN thread DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004441358
Unscheduled inspection
Start date: 2020-07-20, end date: 2020-08-14, duration: 20
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in accordance with the notice of joint stock company "Transmediterranea Siberia" about the end of reconstruction of capital construction object from 08062020 g 2061 Rin 3416886 from 10062020 zadacha of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project of documentation of the Subject of this review is to check the compliance of contractors and construction materials used in the process of reconstruction of capital construction object "MN Aleksandrovskozavodsk км17км325 inv 500294 pipe Replacement on IMOP lake km211 lake км282 palmarosa км208км3147 км3162км3224 of RESn DN 1000 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 702004417157
Unscheduled inspection
Start date: 2020-06-09, end date: 2020-07-07, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: Objectives of the prevention and detection and suppression of violations of urban planning legislation when conducting an unscheduled on-site documentary inspection based on the inspection program 1320PP1 of 19052020 Tasks prevention and detection and suppression of violations of urban planning legislationsubject compliance with mandatory requirements and or requirements established by municipal legal acts compliance with the performance of works and applied building materials during construction reconstruction of a capital construction facility as well as the results of such the requirements of the project documentation approved in accordance with Parts 15 152 and 153 of Article 48 of this Code, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of this Code and or the information model if the formation and maintenance of the information model are mandatory in accordance with the requirements of this Code, including energy requirements with the exception of capital construction facilities to which energy efficiency requirements do not apply, and the requirements for equipping a capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements of Parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 702004442386
Unscheduled inspection
Start date: 2020-06-25, end date: 2020-07-23, duration: —
Authority: Gosudarstvennaya inspekciya truda v Tomskoi oblasti
Purpose of inspection: Federal State supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms registration number of the function 10001244260
# 002004435546
Unscheduled inspection
Start date: 2020-06-15, end date: 2020-06-25, duration: 10
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: based on the notice of the Joint Stock company Transneft Central Siberia on the completion of the reconstruction of the capital construction facility dated 01062020 1061 bx 3416488 dated 02062020, the purpose of this audit is to prevent identify and suppress violations of legislation on urban development activities by the developer, the customer, as well as the person carrying out construction on the basis of a contract with the developer or the customer, the purpose of this audit is to verify the compliance of the work and the construction materials used during the reconstruction of the capital construction facility "MN Alexandrovskoangerosudzhensk km 159km 240 inv 500291 Pipe replacement at the Rnartinskaya km 1965 DN 1200 Reconstruction crossing" as well as the results of such work to the requirements of the project documentation approved in accordance with Parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Development Code of the Russian Federation and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Development Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with appliances accounting for the energy resources used, the availability of a construction permit, and compliance with the requirements set out in Parts 2, 3, and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 702004390892
Unscheduled inspection
Start date: 2020-04-06, end date: 2020-05-06, duration: —
Authority: Gosudarstvennaya inspekciya truda v Tomskoi oblasti
Purpose of inspection: Federal State supervision over compliance with labor legislation and other regulatory legal acts containing labor law norms registration number of the function 10001244260
# 002004375940
Unscheduled inspection
Start date: 2020-03-27, end date: 2020-04-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 02122019 g 439Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project документации7 the Subject of this test is to verify compliance of work and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 428 miles 455 inv 500102 pipe Replacement on IMOP R Shudelka DOS n км44135 км443926 DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004375933
Unscheduled inspection
Start date: 2020-03-27, end date: 2020-04-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 27092019 g 429Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project документации7 the Subject of this test is to verify compliance of work and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 596 miles 649 inv 500098 Replacement pipe for passing through R Brovka km 61415 km 61430 OSN thread DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004326329
Unscheduled inspection
Start date: 2020-03-31, end date: 2020-04-27, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV 438Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN Aleksandrovskozavodsk km 159км 240 inv 500291 pipe Replacement on the crossing martinska km 1965 DN 1200 Reconstruction" located at Tomsk oblast Alexandrovsky municipal district novonikol rural settlement as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004296469
Unscheduled inspection
Start date: 2020-03-31, end date: 2020-04-27, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 14112019 g 433Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project of documentation of the Subject of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN Aleksandrovskozavodsk км17км325 inv 500294 pipe Replacement on IMOP lake km211 lake км282 palmarosa км208км3147 км3162км3224 of RESn DN 1000 Reconstruction" located at Tomsk oblast Alexandrovsky municipal district of Aleksandrovsky rural settlement as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 002004296447
Unscheduled inspection
Start date: 2020-03-31, end date: 2020-04-27, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 10092019 g 428Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN "Aleksandrovskozavodsk" км669км686 inv 500297 pipe Replacement on IMOP R Ob of RESn км66905км6729 км67465км68542 DN 1000 Reconstruction" located at Tomsk oblast Shegarskiy rayon Trubchevskiy rural settlement in Tomsk district Murakowski rural settlement as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 702004141469
Unscheduled inspection
Start date: 2020-01-13, end date: 2020-02-07, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention as well as detection and suppression of violations of urban planning legislation during an unscheduled documentary inspection based on the notice of the beginning of construction 320 dated 22112019 task prevention as well as detection and suppression of violations of urban planning legislation The subject of this inspection is compliance with mandatory requirements or requirements established by municipal legal acts of conformity of work and applied building materials during the construction reconstruction of a capital construction facility and as well as the results of such work, the requirements of the project documentation for the availability of a construction permit, compliance with the requirements of parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004185629
Unscheduled inspection
Start date: 2020-01-31, end date: 2020-02-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the Inspection Program approved by Kolegov DV, Deputy Head of the Siberian Department of Rostechnadzor, dated 29082019. 426the purpose of this inspection is to prevent identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer. The subject of this inspection is to verify the compliance of the work performed and the applied construction materials during the construction of the capital construction facility "NPS Parabel RVSP20000 m3 7 inv 200165 Reconstruction" as well as the results of such work according to the requirements of the project documentation approved in accordance with Parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation If the formation and maintenance of an information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements established by parts 2 3 and 3_1 Articles 52 of the Urban Planning Code of the Russian Federation
# 002004164969
Unscheduled inspection
Start date: 2020-01-31, end date: 2020-02-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 02122019 g 439Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 428 miles 455 inv 500102 pipe Replacement on IMOP R Shudelka км61415 km 61430 DOS n DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001903986881
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-12-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the real test is conducted for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 27092019 g 429Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the process of reconstruction of capital construction object "MN "Aleksandrovskozavodsk" km 596 miles 649 inv 500098 Replacement pipe for passing through R Brovka km 61415 km 61430 OSN thread DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001903986999
Unscheduled inspection
Start date: 2019-11-26, end date: 2019-12-20, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: for the purpose of execution of the Program inspections approved by the Deputy head of the Siberian Department of Rostechnadzor Kolejowym DV from 10092019 g 428Задачей of this review is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or customer of violations of the legislation on town-planning project documentlibraries of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN "Aleksandrovskozavodsk" км669км686 inv 500297 pipe Replacement on IMOP R Ob of RESn км66905км6729 км67465км68542 DN 1000 Reconstruction" located at Tomsk oblast Shegarskiy rayon Trubchevskiy rural settlement in Tomsk district Murakowski rural settlement as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001903626876
Unscheduled inspection
Start date: 2019-10-01, end date: 2019-10-11, duration: —
Authority: Federalnaya sluzhba po akkreditacii
Purpose of inspection: This audit is conducted in order to verify that the accredited person has eliminated the inconsistencies specified in the notification of the Federal Accreditation Service for the Siberian Federal District dated 26072019 SFO1265ND "On sending a list of inconsistencies with the accreditation criteria based on the results of the provision of public services for the confirmation of competence" as well as compliance with the requirements of paragraph 42 regarding compliance in the accredited person's activities with the requirements of the quality management system established in the Manual in terms of quality and developed in accordance with the requirements of sub-paragraphs b of paragraph 497 of subparagraph a of paragraph 499 of paragraph 48 of sub-paragraphs b of paragraph 497 of subparagraph a of paragraph 499 of the Order of the Ministry of Economic Development of the Russian Federation dated 30052014 326 "On approval of Accreditation Criteria, a list of documents confirming the applicant's compliance with accredited criteria and a list of documents in the field of standardization, compliance with the requirements of which applicants and accredited persons ensure their compliance with the accreditation criteria." The objectives of this audit are to ensure compliance with the requirements of the legislation of the Russian Federation for the activities of accredited persons, including Federal Law No. 412 FZ dated 28122013 "On Accreditation in the National Accreditation System" and Order No. 326 of the Ministry of Economic Development of the Russian Federation dated 30052014 "On Approval of the Criteria for Accreditation of the List of documents Confirming the Applicant's Compliance with the Accredited Person the criteria of accreditation and the list of documents in the field of standardization, compliance with the requirements of which by applicants accredited persons ensures their compliance with the criteria of accreditation"The subject of this audit is compliance with mandatory requirements
# 701903840859
Unscheduled inspection
Start date: 2019-10-21, end date: 2019-11-18, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention as well as detection and suppression of violations of urban planning legislation during an unscheduled on-site documentary inspection based on the notice of completion of construction 1910 dated 01102019 inspection program 419PP1 dated 29012019 task prevention as well as detection and suppression of violations of urban planning legislation The subject of this inspection is compliance with mandatory requirements or requirements established by municipal legal acts of conformity of work and applied building materials during construction reconstruction of the capital construction facility as well as the results of such work, the requirements of the project documentation for the availability of a construction permit, compliance with the requirements of parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001903732113
Unscheduled inspection
Start date: 2019-10-04, end date: 2019-10-31, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out on the basis of the notice of completion of the construction of the capital construction facility of JSC Transneft Central Siberia dated 23092019 TCS031515106 bx 31319119 dated 24092019, the purpose of this inspection is to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the customer, as well as the person carrying out construction on the basis of a contract with the developer or the customer, the subject of this inspection The purpose of this work is to verify the compliance of the work performed and the construction materials used and the results during the reconstruction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km676km780 INV 500297 Pipe replacement km734km73516 Du1200 Reconstruction" as well as the results of such work with the requirements of the project documentation approved in accordance with Parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation. documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the equipment requirements of the capital construction facility metering devices for used energy resources, the availability of a construction permit, and the fulfillment of the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 701903250948
Unscheduled inspection
Start date: 2019-09-09, end date: 2019-10-04, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: Purpose Prevention as well as detection and suppression of violations of urban planning legislation during an unscheduled on-site documentary inspection based on the notice of completion of construction 1908 dated 19082019 inspection program 519PP1 dated 29.012019 task prevention as well as detection and suppression of violations of urban planning legislation subject to compliance with mandatory requirements or requirements established by municipal legal acts for the performance of works and the construction materials used during the construction reconstruction of a capital construction facility as well as the results of such work, the requirements of the project documentation for the availability of a construction permit, compliance with the requirements of parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902941731
Unscheduled inspection
Start date: 2019-08-13, end date: 2019-09-09, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out on the basis of the notice of completion of the reconstruction of the capital construction facility of JSC TRANSNEFT Central Siberia dated 06082019 2819 vx 31315890 dated 07082019. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the customer, as well as the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, including among the project documentation, the subject of this audit is to verify the compliance of the work performed and the building materials used during the construction of the capital construction facility "NPS Alexandrovskaya RVSP20000 28 inv200187 Reconstruction" as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation. documentation in accordance with Parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, if the formation and maintenance of the information model are mandatory in accordance with the requirements of the Urban Planning Code of the Russian Federation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the equipment requirements of the capital construction facility metering devices for used energy resources, the availability of a construction permit, and compliance with the requirements established by Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902941664
Unscheduled inspection
Start date: 2019-08-13, end date: 2019-08-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in accordance with the notice of completion of reconstruction of capital construction object JSC "Transmediterranea Siberia" 06082019 g 1819 1312982 from 06082019 Rin g the purpose of this check is to prevent detection and suppression approved developer by the customer and a person engaged in construction on the basis of the contract with the Builder or by the customer the contractor further violations of the legislation on town-planning activities including project documents the Subject of this review is to check the compliance of contractors and construction materials used in the construction process of the object of capital construction "MN "Aleksandrovskozavodsk" km 159 240 inv 500291 pipe Replacement 19907км 20262 km DN 1200 Reconstruction" as well as the results of such work requirements approved in accordance with parts 15 and 15_2 15_3 of article 48 of the town planning code of the Russian Federation project documentation to reflect changes made to the project documentation in accordance with paragraphs 3_8 and 3_9 article 49 of the town planning code of the Russian Federation or of the information model in the case of the formation and maintenance of information models are required in accordance with the requirements of the town planning code of the Russian Federation including the energy efficiency standards with the exception of capital construction objects, for which the energy performance requirements shall not apply and the requirements of the equipment of a capital construction object metering devices of energy resources to the presence of a building permit requirements established in parts 2 and 3 3_1 of article 52 of the town planning code of the Russian Federation
# 001902933933
Unscheduled inspection
Start date: 2019-08-01, end date: 2019-08-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose of the execution by JSC TRANSNEFT Central Siberia of the previously issued regulation 071820MT dated 31052018 under paragraph 1, the term of which expires The tasks of this audit are to monitor the execution by JSC Transneft Central Siberia of the previously issued regulation 071820MT dated 31052018 under paragraph 1, the term of which expires The subject of this audit is the execution by JSC Transneft Central Siberia of the previously issued regulation 071820MT dated 31052018 under paragraph 1 issued by an official of the Siberian Department of Rostechnadzor
# 001902826321
Unscheduled inspection
Start date: 2019-07-22, end date: 2019-08-16, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: based on the Notice of JSC Transneft Central Siberia on the completion of the construction of a capital construction facility dated 17062019 TCC03159179 bx 31310170 dated 23042019, the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor, the subject of this audit The purpose of this work is to monitor the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by the Legislation of the Russian Federation. parts 2, 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the reconstruction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km 780km 8178 inv 500223 Pipe replacement at the crossing of the Ruchey km 78287 DN 1200 Reconstruction" located at the address Tomsk region Alexandrovsky district Kargasok district Parabelstky district Kolpashevsky district Chainsky district Molchanovsky district Krivosheinsky district Shegarsky district Tomsk district
# 001902893669
Unscheduled inspection
Start date: 2019-07-26, end date: 2019-08-22, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: based on the notice of completion of the reconstruction of the capital construction facility of JSC TRANSNEFT Central Siberia dated 15072019 1719 vx 1311870 dated 16072019, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit The purpose of this work is to monitor the compliance of the work performed and the construction materials used during the construction reconstruction of the capital construction facility, as well as the results of such work, with the requirements of the design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by the Legislation of the Russian Federation. in parts 2, 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the reconstruction of the capital construction facility "MN Alexandrovskoangerosudzhensk" km 676 km 780 inv 500297 Pipe replacement at the MN crossing over the Omutnaya river km 74073 km 74088 DN 1200 Reconstruction" located in the Tomsk region Tomsk district
# 701902851553
Unscheduled inspection
Start date: 2019-07-08, end date: 2019-08-02, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention and detection and suppression of violations of urban planning legislation during an unscheduled on-site inspection based on the notice of completion of construction 5191 dated 01072019 inspection program 1119PP1 dated 11042019 task prevention and detection and suppression of violations of urban planning legislation compliance with mandatory requirements or requirements established by municipal legal acts of conformity of work and applied building materials during construction reconstruction of the facility capital construction as well as the results of such work, the requirements of the project documentation for the availability of a construction permit, compliance with the requirements of parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 701902851480
Unscheduled inspection
Start date: 2019-07-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 701902851340
Unscheduled inspection
Start date: 2019-07-08, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001902783666
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Purpose control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 03198MT dated 22042019, the deadline for which expired 07062019 Task control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 03198MT dated 22042019, the deadline for which expired 07062019 Subject is the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 03198MT dated 22042019 by an official of the Siberian Rostechnadzor Management
# 001902783641
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Purpose control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 04198MT dated 22042019, the deadline for which expired 07062019 Task control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 04198MT dated 22042019, the deadline for which expired 07062019 Subject is the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 04198MT dated 22042019 by an official of the Siberian Rostechnadzor Management
# 001902783632
Unscheduled inspection
Start date: 2019-06-10, end date: 2019-06-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Purpose control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 02198MT dated 22042019, the deadline for which expired 07062019 Task control of the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 02198MT dated 22042019, the deadline for which expired 07062019 Subject is the execution of JSC "Transneft Central Siberia" paragraph 1 of the previously issued regulation 02198MT dated 22042019 by an official of the Siberian Rostechnadzor Management
# 001902702024
Unscheduled inspection
Start date: 2019-05-13, end date: 2019-06-07, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Based on the Notice of JSC Transneft Central Siberia on the completion of the construction of a capital construction facility dated 22042019 TCC03146076 bx 3139204 dated 23042019, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit is monitoring of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and with the requirements for equipping a capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by the parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the reconstruction of the capital construction facility "MN Igolskotalovoeparable" km 231km 337 inv 500287 Pipe replacement km 29972km 30704 km 31496km 31599 DN 500 Reconstruction" located at the address Tomsk region Kargasoksky district Parabelsky district
# 701902742517
Unscheduled inspection
Start date: 2019-05-23, end date: 2019-07-04, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention and detection and suppression of violations of urban planning legislation during an unscheduled on-site inspection based on the notice of completion of construction reg 8917OC1 dated 22052019 Inspection program 8917PP1 dated 18122017 task prevention and detection and suppression of violations of urban planning legislation subject compliance with mandatory requirements or requirements established by municipal legal acts compliance of work and applied construction materials in the process construction reconstruction of the capital construction facility as well as the results of such work, the requirements of the project documentation for the availability of a construction permit, compliance with the requirements of parts 2 3 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 701902663203
Unscheduled inspection
Start date: 2019-04-22, end date: —, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection:
# 701902573687
Unscheduled inspection
Start date: 2019-03-18, end date: 2019-04-12, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention and detection and suppression of violations of urban planning legislation during an unscheduled documentary inspection based on the notice of the start of construction 319 dated 01032019 task prevention and detection and suppression of violations of urban planning legislation subject to compliance with mandatory requirements or requirements established by municipal legal acts of compliance with the performance of works and applied building materials during construction reconstruction of a capital construction facility as well as The results of such work are required by the technical regulations of the project documentation, the availability of a construction permit, and compliance with the requirements of parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 701902589779
Unscheduled inspection
Start date: 2019-03-25, end date: —, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection:
# 701902493573
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-04-01, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention and detection and suppression of violations of urban planning legislation during an unscheduled documentary inspection based on the notice of the start of construction 119 dated 23.012019 reg number 419NS1 dated 23.012019 task prevention and detection and suppression of violations of urban planning legislation The subject of this inspection is compliance with mandatory requirements or requirements established by municipal legal acts of conformity of work and applied building materials in the construction process, reconstruction of the capital construction facility, as well as the results of such work, meet the requirements of technical regulations, project documentation, construction permits, and compliance with the requirements of Parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 701902493567
Unscheduled inspection
Start date: 2019-03-04, end date: 2019-04-01, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: purpose prevention and detection and suppression of violations of urban planning legislation during an unscheduled documentary inspection based on the notice of the start of construction 219 dated 23.012019 reg number 519NS1 dated 23.012019 task prevention and detection and suppression of violations of urban planning legislation subject to compliance with mandatory requirements or requirements established by municipal legal acts of conformity of work and applied building materials during the construction reconstruction of the facility capital construction as well as the results of such work, the requirements of technical regulations, project documentation, construction permits, and compliance with the requirements of parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902531782
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to implement the Inspection Program approved by the Deputy Head of the Siberian Department of Rostechnadzor on 03/12/2018, 389 The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, the subject of this inspection is to verify the compliance of the work and the construction materials used and the results during the reconstruction of the capital construction facility "MN Igolskotalovoeparabel" km 231km 337 inv 500287 Pipe replacement km 29972km 30704 km 31496km 31599 DN 500 Reconstruction" as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the fulfillment of the requirements of parts 2 3 and 3_1 Articles 52 of the Urban Planning Code of the Russian Federation
# 001902531754
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to implement the Inspection Program approved by the Deputy Head of the Siberian Directorate of Rostechnadzor on 03/12/2018, 388 The objectives of this inspection are to prevent, identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, and the subject of this inspection is to verify the compliance of the work and the construction materials used and the results during the reconstruction of the capital construction facility ""MH "Alexandrovsko-Anzhero-Sudzhensk" km 780km 8178 INV 500223 Pipe replacement at the crossing of the Ruchey river km 78287 DN 1200 Reconstruction" as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, the fulfillment of the requirements Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation
# 001902531699
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Based on the Notice of JSC Transneft Central Siberia on the completion of the construction of a capital construction facility dated 12022019 TCS03142131 bx 3132503 dated 13022019, the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this audit is monitoring of compliance of work performed and construction materials used during the construction reconstruction of a capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements, with the exception of capital construction facilities for which energy efficiency requirements do not apply, and with the requirements for equipping a capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements established by the parts 2 3 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation during the reconstruction of the capital construction facility "MN Igolskotalovoeparable" km 337km 3977 inv 500288 Pipe replacement with PPMN r Sochiga km 377 DN 500 Reconstruction" located at the address Tomsk region Kargasok district Parabel district
# 001902531792
Unscheduled inspection
Start date: 2019-02-25, end date: 2019-03-23, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order to implement the Inspection Program approved by the Deputy Head of the Siberian Department of Rostechnadzor dated 10122018, the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, the subject of this inspection is to verify the compliance of the work and the applied building materials and the results during the reconstruction of the capital construction facility "MH Alexandrovskoangerosudzhensk" km 159240 INV 500291 Pipe replacement km 19907km 20262 DN 1200 Reconstruction" as well as the results of such work, the requirements of the design documentation, including the requirements for energy efficiency and the requirements for equipping the capital construction facility with metering devices for energy resources used, the availability of a construction permit, compliance with the requirements of Parts 2 3 and 3_1 Article 52 of the Urban Planning Code of the Russian Federation
# 861902498006
Unscheduled inspection
Start date: 2019-02-08, end date: 2019-03-07, duration: —
Authority: Sluzhba po kontrolyu i nadzoru v sfere ohrany okruzhayuschei sredy obektov zhivotnogo mira i lesnyh otnoshenii HantyMansiiskogo avtonomnogo okruga YUgry
Purpose of inspection: This audit is conducted in order to fully comprehensively and objectively review the facts of violations of environmental legislation in connection with the threat of harm to the environment, taking into account the reasoned submission of the head of the Nizhnevartovsk Department of Nature Supervision of Yugra, Bruskov VAish3102ish431 dated 04022019. The objectives of this audit are to ensure compliance with the requirements of forest legislation in the Nizhnevartovsk district of the Khanty-Mansiysk Autonomous Okrug of Yugra.
# 701902462003
Unscheduled inspection
Start date: 2019-01-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001802298222
Unscheduled inspection
Start date: 2018-12-10, end date: 2018-12-28, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the fulfillment by JSC TRANSNEFT Central Siberia of the previously issued regulation 071820MT paragraph 4. The objectives of this inspection are to verify compliance by JSC Transneft Central Siberia with the requirements of legislation in the field of industrial safety during the operation of explosive and fire-hazardous production facilities, technical devices of buildings and structures. The subject of this inspection is compliance with the regulations of state control bodies, supervision bodies, municipal control bodies
# 001802162888
Unscheduled inspection
Start date: 2018-11-28, end date: 2018-12-25, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities, including project documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor
# 001802081121
Unscheduled inspection
Start date: 2018-11-07, end date: 2018-12-04, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: prevention detection and suppression of violations of the legislation on urban planning activities and project documentation committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor
# 001802032240
Unscheduled inspection
Start date: 2018-10-31, end date: 2018-11-26, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of the project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of the capital construction facility of the Alexandrovsko-Anzherosudzhensk KM 676780 INV 500297 Pipe replacement km 734km 73516 DN 1200 Reconstruction" located at the address Tomsk region Tomsk district based on the inspection program dated 111018 385
# 001801693122
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-10-12, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to monitor the fulfillment by JSC TRANSNEFT Central Siberia of previously issued regulations 071820MT paragraphs 235 and 081820MT paragraphs 1 to 2 dated 31052018. The objectives of this inspection are to verify compliance by JSC Transneft Central Siberia with the requirements of legislation in the field of industrial safety during the operation of explosive and fire-hazardous production facilities, technical devices of buildings and structures. The subject of this inspection is compliance with the regulations of state bodies. control supervision of municipal control bodies
# 701801272269
Unscheduled inspection
Start date: 2018-09-24, end date: 2018-10-19, duration: —
Authority: Glavnaya inspekciya gosudarstvennogo stroitelnogo nadzora Tomskoi oblasti
Purpose of inspection: Purpose prevention and detection and suppression of violations of urban planning legislation during an unscheduled on-site inspection based on the inspection program 218PP1 dated 30012018 notice of completion 03091 dated 03092018 Task prevention and detection and suppression of violations of urban planning legislation Subject to compliance with mandatory requirements or requirements established by municipal legal acts of conformity of work and applied building materials during construction reconstruction the capital construction facility as well as the results of such work meet the requirements of technical regulations, project documentation, construction permits, and compliance with the requirements of Parts 2, 3, and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 001800632929
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of the Alexandrovsko-Anzherosudzhensk capital construction facility km 260355 INV 500285 Pipe replacement km 31802km 32705 DN 1000 Reconstruction located at the address Tomsk region Kargasok district on the basis of the completion notice dated 010718g 3181
# 001800632928
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of the capital construction facility "MN "Alexandrovskoangerosudzhensk" km 325km159 inv 500164 Pipe replacement km 733km 7393 km 7735km 7853 DU1200RESTRUCTION" located at the address Tomsk region Alexandrovsky district Alexandrovskoye rural settlement on the basis of a notice of completion construction from 170718 781
# 001802032099
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of the Alexandrovsko-Anzherosudzhensk capital construction facility km 260355 INV 500285 Pipe replacement km 31802km 32705 DN 1000 Reconstruction located at the address Tomsk region Kargasok district on the basis of the completion notice dated 010718g 3181