# 72170701712571
Unscheduled inspection
Start date: 2017-06-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72170701568346
Unscheduled inspection
Start date: 2017-04-25, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 72170701414914
Unscheduled inspection
Start date: 2017-02-20, end date: 2017-03-22, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program dated January 27, 2017. Verification of compliance of the work performed and the building materials used during construction, as well as the results of such work, with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used during the construction of the capital construction facility "Perekladka gravity sewer collector d600 mm with an increase in diameter to 800 mm along Montazhnikov St. through Shirotnaya St. approximate length 500 m" located at 92 Montazhnikov St., Tyumen region, Russian Federation