Found 5 inspections:

# 001801932933
Unscheduled inspection
Start date: 2018-10-02, end date: 2018-10-03, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Cel osuschestvlenie kontrolya za prinimaemymi yuridicheskim licom individualnym predprinimatelem merami po soblyudeniyu teplosetevymi i teplosnabzhayuschimi organizaciyami trebovanii bezopasnosti v sfere teplosnabzheniya vliyayuschih na vypolnenie trebovanii po gotovnosti k otopitelnomu periodu obyazatelnyh trebovanii v svyazi s istecheniem sroka ispolneniya predpisaniya ot 14082018 3450152535Pr Zadachi prinyatie predusmotrennyh zakonodatelstvom Rossiiskoi Federacii mer po presecheniyu i ustraneniyu narushenii obyazatelnyh trebovanii v sluchae ih vyyavleniya i po privlecheniyu k otvetstvennosti lic dopustivshih narusheniya trebovanii Federalnyh zakonov i inyh normativnyh pravovyh aktov Predmet vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora


# 00170701826871
Unscheduled inspection
Start date: 2017-07-28, end date: 2017-08-01, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the measures taken by a legal entity, an individual entrepreneur, to comply with heating grid and heat supply organizations with safety requirements in the field of heat supply that affect the fulfillment of mandatory requirements for readiness for the heating period, taking measures provided for by the legislation of the Russian Federation to prevent and eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and regulations other regulatory legal acts


# 001801932933
Unscheduled inspection
Start date: 2018-10-02, end date: 2018-10-03, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Cel osuschestvlenie kontrolya za prinimaemymi yuridicheskim licom individualnym predprinimatelem merami po soblyudeniyu teplosetevymi i teplosnabzhayuschimi organizaciyami trebovanii bezopasnosti v sfere teplosnabzheniya vliyayuschih na vypolnenie trebovanii po gotovnosti k otopitelnomu periodu obyazatelnyh trebovanii v svyazi s istecheniem sroka ispolneniya predpisaniya ot 14082018 3450152535Pr Zadachi prinyatie predusmotrennyh zakonodatelstvom Rossiiskoi Federacii mer po presecheniyu i ustraneniyu narushenii obyazatelnyh trebovanii v sluchae ih vyyavleniya i po privlecheniyu k otvetstvennosti lic dopustivshih narusheniya trebovanii Federalnyh zakonov i inyh normativnyh pravovyh aktov Predmet vypolnenie predpisanii organov gosudarstvennogo kontrolya nadzora


# 001800612819
Unscheduled inspection
Start date: 2018-08-09, end date: 2018-08-14, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to control the preparation of heat supply facilities for the heating period in accordance with the Rostechnadzor Order "On monitoring the progress of preparation of heat supply facilities for operation in the autumn-winter period of 2018 2019" dated 16072018 308 issued in accordance with the instruction of Deputy Prime Minister of the Russian Federation Vladimir Mutko dated 26062018 VMP93773 vx 01161905 dated 16072018 Tasks to monitor the decisions taken by a legal entity as an individual entrepreneur measures to ensure that heating grid and heat supply organizations comply with safety requirements in the field of heat supply that affect the fulfillment of mandatory requirements for readiness for the heating period, taking measures provided for by the legislation of the Russian Federation to prevent and eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory legal acts. activities related to the operation of power plants and heat supply facilities are a set of mandatory requirements that affect readiness for the heating period


# 00170701826871
Unscheduled inspection
Start date: 2017-07-28, end date: 2017-08-01, duration:
Authority: SeveroZapadnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control over the measures taken by a legal entity, an individual entrepreneur, to comply with heating grid and heat supply organizations with safety requirements in the field of heat supply that affect the fulfillment of mandatory requirements for readiness for the heating period, taking measures provided for by the legislation of the Russian Federation to prevent and eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and regulations other regulatory legal acts


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.