# 001700035604
Unscheduled inspection
Start date: 2017-08-22, end date: 2017-08-24, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order for the legal entity to comply with the previously issued instruction on the elimination of identified violations dated 21042017 1210145plP00942017
# 00170802242277
Unscheduled inspection
Start date: 2017-08-22, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ensuring the fulfillment by a legal entity of the instruction on the elimination of identified violations dated 21042017 1210145plP00942017, the deadline for which has expired
# 00170802225148
Unscheduled inspection
Start date: 2017-08-22, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ensuring the fulfillment by a legal entity of the instruction on the elimination of identified violations dated 21042017 1210145plP00942017, the deadline for which has expired
# 671903587602
Unscheduled inspection
Start date: 2019-09-19, end date: —, duration: —
Authority: —
Purpose of inspection:
# 671902993969
Unscheduled inspection
Start date: 2019-08-23, end date: 2019-08-28, duration: —
Authority: Departament gosudarstvennogo stroitelnogo i tehnicheskogo nadzora Smolenskoi oblasti
Purpose of inspection: This inspection is conducted in order to carry out regional state construction supervision in the Smolensk Region in accordance with the inspection program dated March 06, 2019. The objectives of this inspection are to prevent and suppress violations of legislation on urban development, including technical regulations, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer. project documentation
# 671902725574
Unscheduled inspection
Start date: 2019-05-24, end date: 2019-05-29, duration: —
Authority: Departament gosudarstvennogo stroitelnogo i tehnicheskogo nadzora Smolenskoi oblasti
Purpose of inspection: This inspection is conducted in order to carry out regional state construction supervision in the Smolensk Region in accordance with the inspection program dated March 06, 2019. The objectives of this inspection are to prevent and suppress violations of legislation on urban development, including technical regulations, committed by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer. project documentation
# 671902558672
Unscheduled inspection
Start date: 2019-03-05, end date: 2019-03-07, duration: —
Authority: Departament gosudarstvennogo stroitelnogo i tehnicheskogo nadzora Smolenskoi oblasti
Purpose of inspection: This inspection is carried out in order to verify the information specified in the notice of the start of construction of the legal entity Polymer Limited Liability Company FROM 007 dated 01032019. The objectives of this inspection are to prevent and suppress violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as the person carrying out construction on the basis of a contract with the developer or the customer. Documentation
# 67170802959535
Unscheduled inspection
Start date: 2017-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001700035604
Unscheduled inspection
Start date: 2017-08-22, end date: 2017-08-24, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: in order for the legal entity to comply with the previously issued instruction on the elimination of identified violations dated 21042017 1210145plP00942017
# 00170802242277
Unscheduled inspection
Start date: 2017-08-22, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ensuring the fulfillment by a legal entity of the instruction on the elimination of identified violations dated 21042017 1210145plP00942017, the deadline for which has expired
# 00170802225148
Unscheduled inspection
Start date: 2017-08-22, end date: —, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ensuring the fulfillment by a legal entity of the instruction on the elimination of identified violations dated 21042017 1210145plP00942017, the deadline for which has expired
# 67160701096259
Unscheduled inspection
Start date: 2016-10-31, end date: —, duration: —
Authority: —
Purpose of inspection: