# 142100474682
Unscheduled inspection
Start date: 2021-08-11, end date: —, duration: 10
Authority: Gosudarstvennyi komitet po obespecheniyu bezopasnosti zhiznedeyatelnosti naseleniya Respubliki Saha (YAkutiya)
Purpose of inspection: nadzor za soblyudeniem obyazatelnyh trebovanii v oblasti zaschity naseleniya i territorii ot chrezvychainyh situacii prirodnogo i tehnogennogo haraktera
# 142005199859
Unscheduled inspection
Start date: 2020-10-30, end date: 2020-11-13, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 142005199558
Unscheduled inspection
Start date: 2020-10-30, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 142005199582
Unscheduled inspection
Start date: 2020-10-30, end date: 2020-11-13, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 142005199825
Unscheduled inspection
Start date: 2020-08-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004484792
Unscheduled inspection
Start date: 2020-08-25, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 142004484870
Unscheduled inspection
Start date: 2020-08-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004484789
Unscheduled inspection
Start date: 2020-08-25, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 142004484868
Unscheduled inspection
Start date: 2020-08-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004484866
Unscheduled inspection
Start date: 2020-08-25, end date: 2020-09-07, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 142004484780
Unscheduled inspection
Start date: 2020-08-25, end date: 2020-09-07, duration: 10
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 142004445066
Unscheduled inspection
Start date: 2020-06-22, end date: 2020-06-30, duration: 8
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 142004445063
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004445059
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004445054
Unscheduled inspection
Start date: 2020-06-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004314563
Unscheduled inspection
Start date: 2020-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004314562
Unscheduled inspection
Start date: 2020-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004314554
Unscheduled inspection
Start date: 2020-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004314553
Unscheduled inspection
Start date: 2020-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004314324
Unscheduled inspection
Start date: 2020-03-16, end date: 2020-03-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 142004314601
Unscheduled inspection
Start date: 2020-03-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004314598
Unscheduled inspection
Start date: 2020-03-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 142004220714
Unscheduled inspection
Start date: 2020-01-21, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection:
# 141904181160
Unscheduled inspection
Start date: 2019-11-01, end date: 2019-11-01, duration: —
Authority: Federalnaya sluzhba po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celyu proverki yavlyaetsya ispolnenie p 24 prilozheniya 1 k prikazu Lenskogo upravleniya Rostehnadzora 353 ot 13 avgusta 2019 g Zadachami nastoyaschei proverki yavlyayutsya ocenka gotovnosti Municipalnogo obrazovaniya «Nyurbinskii ulus» i naslegov poselenii vhodyaschih v sostav ukazannogo ulusa raiona k otopitelnomu periodu 2019 2020gg i soblyudenii imi trebovanii ukazannyh v p18 Pravil ocenki gotovnosti k otopitelnomu periodu utv Prikazom Minenergo RF ot 12 marta 2013 g 103 Predmetom proverki yavlyaetsya soblyudenie Municipalnymi obrazovaniyami obyazatelnyh trebovanii ustanovlennyh Federalnym zakonom ot 27 iyulya 2010 g 190 FZ «O teplosnabzhenii» i drugih normativno pravovyh aktov razrabotannyh v sootvetstvii s dannym zakonom
# 141904314582
Unscheduled inspection
Start date: 2019-11-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141904314561
Unscheduled inspection
Start date: 2019-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141904281002
Unscheduled inspection
Start date: 2019-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141904181179
Unscheduled inspection
Start date: 2019-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 141904181211
Unscheduled inspection
Start date: 2019-11-11, end date: 2019-11-14, duration: —
Authority: Federalnaya sluzhba po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Celyu proverki yavlyaetsya ispolnenie p 24 prilozheniya 1 k prikazu Lenskogo upravleniya Rostehnadzora 353 ot 13 avgusta 2019 g Zadachami nastoyaschei proverki yavlyayutsya ocenka gotovnosti Municipalnogo obrazovaniya «Nyurbinskii ulus» i naslegov poselenii vhodyaschih v sostav ukazannogo ulusa raiona k otopitelnomu periodu 2019 2020gg i soblyudenii imi trebovanii ukazannyh v p18 Pravil ocenki gotovnosti k otopitelnomu periodu utv Prikazom Minenergo RF ot 12 marta 2013 g 103 Predmetom proverki yavlyaetsya soblyudenie Municipalnymi obrazovaniyami obyazatelnyh trebovanii ustanovlennyh Federalnym zakonom ot 27 iyulya 2010 g 190 FZ «O teplosnabzhenii» i drugih normativno pravovyh aktov razrabotannyh v sootvetstvii s dannym zakonom
# 141904314574
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141904314573
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141903647806
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141903647804
Unscheduled inspection
Start date: 2019-09-25, end date: 2019-10-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141903647832
Unscheduled inspection
Start date: 2019-09-26, end date: 2019-10-09, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141903647827
Unscheduled inspection
Start date: 2019-09-26, end date: 2019-10-09, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo i zhilischnogo nadzora Respubliki Saha YAkutiya
Purpose of inspection: 1 compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made to the project documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements of energy efficiency and the requirements for equipping the capital construction facility with metering devices for used energy resources 2 availability of a construction permit 3 compliance with the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 141903435311
Unscheduled inspection
Start date: 2019-09-24, end date: —, duration: —
Authority: —
Purpose of inspection: