# 761902765222
Unscheduled inspection
Start date: 2019-06-07, end date: 2019-06-14, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: proverka provoditsya s celyu na osnovanii izvescheniya ob okonchanii stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva ot 27052019 Vh 57Zadachami nastoyaschei proverki yavlyayutsya opredelenie sootvetstviya postroennogo obekta kapitalnogo stroitelstva trebovaniyam tehnicheskih reglamentov norm i pravil inyh normativnyh pravovyh aktov i proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsyasoblyudenie obyazatelnyh trebovanii
# 761902719354
Unscheduled inspection
Start date: 2019-05-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 761902615789
Unscheduled inspection
Start date: 2019-03-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 761902529834
Unscheduled inspection
Start date: 2019-02-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 761802150830
Unscheduled inspection
Start date: 2018-11-23, end date: 2018-11-23, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements
# 761800609630
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-08-07, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements
# 761800445157
Unscheduled inspection
Start date: 2018-06-08, end date: 2018-06-08, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora YAroslavskoi oblasti
Purpose of inspection: The audit is carried out in order to determine, on the basis of the audit program, the objectives of this audit are to determine whether the work performed during the construction of a capital construction facility meets the requirements of technical regulations norms and rules of other regulatory legal acts and project documentation. The subject of this audit is compliance with mandatory requirements