Found 22 inspections:

# 472005242117
Unscheduled inspection
Start date: 2020-11-25, end date: 2020-12-22, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Verification of the completion of work on the construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping a capital construction facility with metering devices for energy resources used to meet the requirements established by parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 472004415401
Unscheduled inspection
Start date: 2020-05-27, end date: 2020-06-24, duration: 5
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer technical customer on completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and the requirements for equipping the capital construction facility with metering devices for used energy resources compliance with the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out construction


# 471902662083
Unscheduled inspection
Start date: 2019-04-17, end date: 2019-05-21, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the execution of the issued instruction on the elimination of identified violations The subject of this audit is the fulfillment of the instructions of the Committee of State Construction Supervision and State expertise of the Leningrad Region the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations, and the design objectives of this audit are to prevent identify and suppress by the developer, the technical customer, the person carrying out the construction of violations of the legislation on urban planning activities, including technical regulations and project documentation


# 471802218647
Unscheduled inspection
Start date: 2018-12-05, end date: 2019-01-09, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 Articles 52 of the Urban Planning Code of the Russian Federation


# 471802150449
Unscheduled inspection
Start date: 2018-10-29, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 471800490336
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-07-18, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of works at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 471800283826
Unscheduled inspection
Start date: 2018-04-12, end date: 2018-05-14, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of work at the beginning of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used compliance with the requirements of parts 2 Articles 3 and 31 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 471800270397
Unscheduled inspection
Start date: 2018-04-05, end date: 2018-05-04, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the works specified in the inspection program The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the technical customer, the person carrying out the construction


# 471800168929
Unscheduled inspection
Start date: 2018-03-01, end date: 2018-03-30, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: verification of the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of the identified violations The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility implementation of the requirements of Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation the objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the developer, the technical customer, the person carrying out the construction, including technical regulations and project documentation


# 47170701621034
Unscheduled inspection
Start date: 2017-05-07, end date: 2017-06-05, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the citizen's application The subject of this audit is to comply with mandatory requirements, including compliance with the performance of work and the construction materials used during the construction of the reconstruction of the capital construction facility, as well as the results of such work, with the requirements of technical regulations, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, compliance with the requirements of Parts 2 and 3 of the article 52 of the Urban Planning Code of the Russian Federation


# 47170701589262
Unscheduled inspection
Start date: 2017-05-03, end date: 2017-06-01, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on the completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements equipment of the capital construction facility with metering devices for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47170701457629
Unscheduled inspection
Start date: 2017-03-16, end date: —, duration:
Authority:
Purpose of inspection:


# 47170701457675
Unscheduled inspection
Start date: 2017-03-15, end date: 2017-04-11, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of the identified violations. The subject of this check is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility metering devices for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47170701358533
Unscheduled inspection
Start date: 2017-02-06, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 47170701349840
Unscheduled inspection
Start date: 2017-02-02, end date: 2017-03-03, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverka zaversheniya rabot po osuschestvleniyu stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva ukazannogo v izveschenii zastroischika tehnicheskogo zakazchika ob okonchanii stroitelstva Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii v tom chisle sootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov vypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 47160701244434
Unscheduled inspection
Start date: 2016-12-16, end date: 2017-01-19, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverki ustraneniya narushenii obyazatelnyh trebovanii ukazannyh v izveschenii lica osuschestvlyayuschego stroitelstvo ob ustranenii vyyavlennyh narusheniiPredmetom nastoyaschei proverki yavlyaetsyasoblyudenie obyazatelnyh trebovanii v tom chislesootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstvapriborami ucheta ispolzuemyh energeticheskih resursovvypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 47160701213060
Unscheduled inspection
Start date: 2016-12-07, end date: 2017-01-10, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Cel proverka ustraneniya narushenii obyazatelnyh trebovanii ukazannyh v izveschenii lica osuschestvlyayuschego stroitelstvo ob ustranenii vyyavlennyh narushenii Predmetom nastoyaschei proverki yavlyaetsya soblyudenie obyazatelnyh trebovanii v tom chislesootvetstvie vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva rekonstrukcii obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursovvypolnenie trebovanii chastei 2 i 3 stati 52 Gradostroitelnogo kodeksa Rossiiskoi Federacii


# 47160701264461
Unscheduled inspection
Start date: 2016-12-23, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 47160701264456
Unscheduled inspection
Start date: 2016-12-23, end date: 2017-01-26, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose of checking the elimination of violations of the mandatory requirements specified in the notice of the person carrying out the construction on the elimination of the identified violations. The subject of this check is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and equipment requirements of the capital construction facility with appliances accounting for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47160701129280
Unscheduled inspection
Start date: 2016-11-18, end date: 2016-12-15, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose is to verify the completion of work on the construction of a capital construction facility specified in the developer's notice of completion of construction. The subject of this audit is compliance with mandatory requirements, including compliance with the performance of work and the construction materials used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency and equipment requirements the capital construction facility's metering devices for used energy resources comply with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47160701129241
Unscheduled inspection
Start date: 2016-11-18, end date: —, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection:


# 47160701112426
Unscheduled inspection
Start date: 2016-11-14, end date: 2016-12-09, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: The purpose is to verify the completion of work on the construction of a capital construction facility specified in the developer's notice of completion of construction. The subject of this audit is compliance with mandatory requirements, including compliance with the performance of work and the construction materials used during construction, reconstruction of the capital construction facility, as well as the results of such work with the requirements of technical regulations, project documentation, including energy efficiency and equipment requirements the capital construction facility's metering devices for used energy resources comply with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.