Found 11 inspections:

# 001801923317
Unscheduled inspection
Start date: 2018-10-30, end date: —, duration:
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:


# 001800664283
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility based on the inspection program approved by the Deputy Head of the Siberian Directorate of Rostechnadzor dated 10072018 286 The objectives of this audit are to prevent identify and suppress violations committed by the developer customer as well as by a person carrying out construction on the basis of a contract with a developer or customer hereinafter referred to as the contractor for violations of urban planning legislation, including the requirements of the technical regulations of the project documentation, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and equipment capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements of parts 23 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 00170701423487
Unscheduled inspection
Start date: 2017-02-22, end date: 2017-03-10, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the execution of orders to eliminate identified offenses that have expired tasks prevention detection and suppression of violations of the law on urban development activities committed by the person carrying out the construction, including technical regulations and project documentationsubject the execution of the order of the state construction supervision authority


# 00160601643819
Unscheduled inspection
Start date: 2016-05-31, end date: —, duration:
Authority:
Purpose of inspection:


# 001801980125
Unscheduled inspection
Start date: 2018-10-29, end date: 2018-11-26, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to implement the Inspection Program, an adjustment approved by and about the Deputy Head of the Siberian Rostechnadzor Department Gayenko AP dated 10072018 286, the objectives of this inspection are to prevent, identify and suppress violations of legislation on urban development by the developer, the customer, as well as by the person carrying out construction on the basis of a contract with the developer or the customer, hereinafter referred to as the contractor. The subject of this inspection is the compliance of the work and the construction materials used and the results during the construction of the capital construction facility "Reconstruction of technological facilities of the Federal State Institution Mars Plant of Rosreserv", as well as the results of such work, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, construction permits, compliance with the requirements of Parts 2 3 and 3_1 of Article 52 of the Urban Planning Code. The Code of the Russian Federation


# 001801923317
Unscheduled inspection
Start date: 2018-10-30, end date: 2018-11-27, duration:
Authority: Dalnevostochnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out in order to carry out federal state construction supervision within the competence of Rostechnadzor during the construction and reconstruction of all facilities specified in paragraph 51 of Article 6 of the Urban Planning Code of the Russian Federation on the basis of the expiration of the deadline for the elimination of violations from 13042018 057916640401, which should be notified to SEC LLC in accordance with the established procedure within 24 hours prior to the start of the inspection The objectives of this audit are to prevent identify and suppress violations of urban planning legislation, including technical regulations and project documentation, committed by the developer, the technical customer, as well as by the person carrying out construction on the basis of a contract with the developer or the technical customer, hereinafter referred to as the contractor. The subject of this audit is the actual implementation of the regulation on the elimination of violations dated 13042018 057916640401


# 001800664283
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-09-21, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation with the requirements for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility based on the inspection program approved by the Deputy Head of the Siberian Directorate of Rostechnadzor dated 10072018 286 The objectives of this audit are to prevent identify and suppress violations committed by the developer customer as well as by a person carrying out construction on the basis of a contract with a developer or customer hereinafter referred to as the contractor for violations of urban planning legislation, including the requirements of the technical regulations of the project documentation, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements of energy efficiency and equipment capital construction facility with metering devices for used energy resources availability of a construction permit compliance with the requirements of parts 23 and 3_1 of Article 52 of the Urban Planning Code of the Russian Federation


# 00170701423487
Unscheduled inspection
Start date: 2017-02-22, end date: 2017-03-10, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The purpose is to monitor the execution of orders to eliminate identified offenses that have expired tasks prevention detection and suppression of violations of the law on urban development activities committed by the person carrying out the construction, including technical regulations and project documentationsubject the execution of the order of the state construction supervision authority


# 00160701107798
Unscheduled inspection
Start date: 2016-11-14, end date: 2016-12-09, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: objectives monitoring the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation requirements for energy conservation and energy efficiency improvement tasks prevention identification and suppression of violations of urban planning legislation committed by the person carrying out construction on the basis of a contract with the developer or technical customer, including the requirements of technical regulations of project documentationsubject compliance of work and applied building materials as well as the results of such work meet the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping a capital construction facility with metering devices for energy resources used, the availability of a construction permit, and compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 00160601782471
Unscheduled inspection
Start date: 2016-08-22, end date: 2016-09-16, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: In order to control the compliance of completed works with the mandatory requirements of technical regulations and other regulatory legal acts of project documentation for energy conservation and energy efficiency improvement during the reconstruction of a capital construction facility, the objectives of this audit are to prevent identify and suppress violations of legislation on urban development by the developer and technical customer, including the requirements of technical regulations for project documentation. The subject of this audit is the compliance of the work performed and the applied construction materials and results in the process of reconstruction of the capital construction facility, as well as the results of such work, requirements of technical regulations, project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources, availability of construction permits, compliance with the requirements of parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 00160601643819
Unscheduled inspection
Start date: 2016-05-31, end date: 2016-06-28, duration:
Authority: Sibirskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: compliance of completed works


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.