# 772100014244
Unscheduled inspection
Start date: 2021-02-11, end date: 2021-02-11, duration: 1
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ispolneniya ranee vydannogo predpisaniya ot 14 fevralya 2020 g. № P-RP-200-186-o;
zadachami nastoyaschei proverki yavlyayutsya:
osuschestvlenie kontrolya za prinyatymi yuridicheskim licom merami po ispolneniyu predpisaniya i soblyudeniyu obyazatelnyh norm i pravil raboty v energoustanovkah;
prinyatie mer po ustraneniyu narushenii obyazatelnyh trebovanii (v sluchae ih vyyavleniya) i po privlecheniyu k otvetstvennosti lic, dopustivshih narusheniya trebovanii Federalnyh zakonov i inyh normativnyh pravovyh aktov.
# 772004364169
Unscheduled inspection
Start date: 2020-03-16, end date: 2020-03-20, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu kontrolya ranee vydannogo predpisaniya 3311 ot 25 fevralya 2019 goda ob ustranenii narushenii trebovanii pozharnoi bezopasnosti
# 002004310999
Unscheduled inspection
Start date: 2020-02-10, end date: 2020-02-14, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: The audit is conducted in order to comply with the instructions of the Government of the Russian Federation dated December 30, 2019, DKP911542, Order of the Federal Service for Environmental Technological and Nuclear Supervision dated January 15, 2020, 15, Order of the Interregional Technological Directorate of the Federal Service for Environmental Technological and Nuclear Supervision dated September 10, 2019 3016r, The objectives of this audit are to monitor the measures taken to comply with legal a person who is an individual entrepreneur of mandatory safety requirements in the electric power industry prevention identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation in the field of safety in the electric power industry taking measures to eliminate violations of mandatory requirements if they are identified and to bring to justice persons who have violated the requirements of Federal laws and other regulatory acts The subject of this audit is compliance with mandatory requirements
# 771902533839
Unscheduled inspection
Start date: 2019-02-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77180803049902
Unscheduled inspection
Start date: 2018-01-15, end date: 2018-02-12, duration: —
Authority: Gosudarstvennaya inspekciya truda v gorode Moskve
Purpose of inspection: Zaschita prav i interesov rabotnikov v svyazi s postupleniem v Inspekciyu obrascheniya rabotnika ot 17112017 g 74259617OB po voprosam oplaty truda oformleniya i rastorzheniya trudovogo dogovora
# 771800024660
Unscheduled inspection
Start date: 2018-01-23, end date: —, duration: —
Authority: Departament zdravoohraneniya goroda Moskvy
Purpose of inspection:
# 77170802816992
Unscheduled inspection
Start date: 2017-11-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77170701665895
Unscheduled inspection
Start date: 2017-06-08, end date: 2017-07-06, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: control of a previously issued prescription for the elimination of violations of mandatory fire safety requirements