# 001902525885
Unscheduled inspection
Start date: 2019-01-29, end date: 2019-02-11, duration: 10
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu proverki vypolneniya meropriyatii predusmotrennyh punktami ranee vydannogo proveryaemomu licu predpisaniya ot 14012019g 09219 ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii srok ispolneniya kotoryh istekaet 121118g V svyazi s postupivshim izvescheniem 23012019 526581 vh 5257 ot 24012019 g ot zastroischika ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva Predmetom nastoyaschei proverki yavlyaetsya proverka vypolneniya predpisaniya organa gosudarstvennogo stroitelnogo nadzora ot 14012019g 09219
# 001800585587
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-24, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the implementation of state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates of works that are subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development activities committed by the person carrying out construction, including technical regulations and project documentation The subject of this audit The purpose of the audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 001800221034
Unscheduled inspection
Start date: 2018-03-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00170701658718
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-07-03, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka vypolneniya ranee vydannogo proveryaemomu licu predpisaniya ot 28042017 09219 ob ustranenii vyyavlennyh rannee narushenii srok ispolneniya kotorogo istekaet 02062017
# 242004318847
Unscheduled inspection
Start date: 2020-03-16, end date: 2020-04-10, duration: —
Authority: Gosudarstvennaya inspekciya truda v Krasnoyarskom krae
Purpose of inspection: ensuring compliance with and protection of labor rights and freedoms of citizens ensuring compliance by employers with labor legislation and other regulatory legal acts containing labor law norms
# 241902908987
Unscheduled inspection
Start date: 2019-08-05, end date: —, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Krasnoyarskomu krayu
Purpose of inspection:
# 001902525885
Unscheduled inspection
Start date: 2019-01-29, end date: 2019-02-11, duration: 10
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu proverki vypolneniya meropriyatii predusmotrennyh punktami ranee vydannogo proveryaemomu licu predpisaniya ot 14012019g 09219 ob ustranenii vyyavlennyh narushenii obyazatelnyh trebovanii srok ispolneniya kotoryh istekaet 121118g V svyazi s postupivshim izvescheniem 23012019 526581 vh 5257 ot 24012019 g ot zastroischika ob ustranenii narushenii pri stroitelstve rekonstrukcii obekta kapitalnogo stroitelstva Predmetom nastoyaschei proverki yavlyaetsya proverka vypolneniya predpisaniya organa gosudarstvennogo stroitelnogo nadzora ot 14012019g 09219
# 001802323347
Unscheduled inspection
Start date: 2018-12-19, end date: 2019-01-23, duration: 20
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Nastoyaschaya proverka provoditsya v ramkah gosudarstvennogo stroitelnogo nadzora pri stroitelstve rekonstrukcii kapitalnom remonte obektov ukazannyh v punkte 51 stati 6 Gradostroitelnogo kodeksa Rossiiskoi Federacii za isklyucheniem obektov v otnoshenii kotoryh osuschestvlenie gosudarstvennogo stroitelnogo nadzora ukazami Prezidenta Rossiiskoi Federacii vozlozheno na inye federalnye organy ispolnitelnoi vlasti reestrovyi 10001515438 v svyazi s postupivshim izvescheniem ot 11122018 bn vh 94107 ot 11122018 g ot zastroischika ob okonchanii stroitelstva obekta kapitalnogo stroitelstva Zadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh zastroischikom narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle tehnicheskih reglamentov i proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya 1 proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam tehnicheskih reglamentov proektnoi dokumentacii v tom chisle trebovaniyam energeticheskoi effektivnosti i trebovaniyam osnaschennosti obekta kapitalnogo stroitelstva priborami ucheta ispolzuemyh energeticheskih resursov
# 241801713047
Unscheduled inspection
Start date: 2018-10-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 241800590907
Unscheduled inspection
Start date: 2018-08-21, end date: 2018-09-17, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Krasnoyarskomu krayu
Purpose of inspection: Kontrol ispolneniya ranee vydannyh predpisanii ot 15092017 995113 ob ustranenii narushenii trebovanii pozharnoi bezopasnosti srok ispolneniya kotoryh istekaet 20 iyulya 2018 goda
# 001800585587
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-24, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the implementation of state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates of works that are subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility The objectives of this audit are to prevent identify and suppress violations of the legislation on urban development activities committed by the person carrying out construction, including technical regulations and project documentation The subject of this audit The purpose of the audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 241800219596
Unscheduled inspection
Start date: 2018-04-10, end date: 2018-05-10, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Krasnoyarskomu krayu
Purpose of inspection: Ustanovit chto nastoyaschaya proverka provoditsya s celyu proverki vypolneniya predpisaniya 3070s ot 27062017 g vydannogo dolzhnostnym licom Upravleniya Rospotrebnadzora po Krasnoyarskomu krayu so srokom ustraneniya narushenii do 09042018 g zadachami nastoyaschei proverki yavlyayutsya osuschestvlenie gosudarstvennogo nadzora i kontrolya za ispolneniem trebovanii zakonodatelstva Rossiiskoi Federacii po preduprezhdeniyu vrednogo vozdeistviya na cheloveka faktorov sredy obitaniya profilaktika infekcionnyh i massovyh neinfekcionnyh zabolevanii otravlenii naseleniya Predmetom nastoyaschei proverki yavlyaetsya proverka vypolneniya predpisaniya vydannogo dolzhnostnym licom Upravleniya Rospotrebnadzora po Krasnoyarskomu krayu
# 001800221034
Unscheduled inspection
Start date: 2018-03-22, end date: 2018-04-18, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the implementation of state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates of works that are subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility The objectives of this audit are to prevent identify and suppress violations of the legislation on urban planning activities committed by the person carrying out the construction, including technical regulations and project documentation The subject of this audit The purpose of the audit is to verify the compliance of the work performed and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 00170802706906
Unscheduled inspection
Start date: 2017-10-11, end date: 2017-11-08, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: implementation of state construction supervision during the construction of the specified capital construction facility in connection with the onset of completion dates of works that are subject to verification in accordance with the approved program of inspections during the construction of the capital construction facility
# 24170701847284
Unscheduled inspection
Start date: 2017-08-21, end date: 2017-09-15, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po Krasnoyarskomu krayu
Purpose of inspection: kontrol ispolneniya ranee vydannyh predpisanii ot 23082017 1065113 ob ustranenii narushenii trebovanii pozharnoi bezopasnosti srok ispolneniya kotoryh istekaet 20 avgusta 2017 goda
# 00170701658718
Unscheduled inspection
Start date: 2017-06-05, end date: 2017-07-03, duration: —
Authority: Eniseiskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Proverka vypolneniya ranee vydannogo proveryaemomu licu predpisaniya ot 28042017 09219 ob ustranenii vyyavlennyh rannee narushenii srok ispolneniya kotorogo istekaet 02062017