# 002004306841
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated January 13, 2020 13 "On conducting inspections of compliance with mandatory requirements by subjects of the electric power industry, heat supply organizations, heating grid organizations and consumers of electric energy in 2020" on the basis of an instruction from the Government of the Russian Federation dated December 30, 2019 DKP911542 The objectives of this inspection is to establish the fact compliance with non-compliance with the requirements of legislation in the established field of activity The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 00180803061306
Unscheduled inspection
Start date: 2018-01-16, end date: 2018-01-16, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 00170802912252
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-05, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 00170802489736
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-19, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 00170701820676
Unscheduled inspection
Start date: 2017-07-24, end date: 2017-07-25, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 00170701736863
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-27, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 00170701623106
Unscheduled inspection
Start date: 2017-05-16, end date: 2017-06-13, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya Tyumenskoi oblasti
Purpose of inspection: verification of the execution of the instruction from 16032017 TO2404 for an apartment building 140 on Internatsionalnaya street, Tyumen, Prevention of detection and suppression of violations of mandatory requirements, compliance with the instructions of state control and supervision bodies
# 00170701622748
Unscheduled inspection
Start date: 2017-05-16, end date: 2017-06-13, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya Tyumenskoi oblasti
Purpose of inspection: verification of the execution of the order from 16032017 TO2404 for an apartment building 140 on Internatsionalnaya Street in Tyumen prevention detection and suppression of violations of mandatory requirements compliance with the instructions of state control and supervision bodies
# 00170701419125
Unscheduled inspection
Start date: 2017-02-27, end date: 2017-03-27, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya Tyumenskoi oblasti
Purpose of inspection: consideration of the application from 15022017 1178zh17 for an apartment building at 140 Internatsionalnaya Street in Tyumen
# 00160701194319
Unscheduled inspection
Start date: 2016-12-05, end date: 2016-12-20, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the fulfillment of paragraphs 13 of the regulation dated 29082016 576070P issued by the North Ural Department of Rostechnadzor. The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Ural Heating Grid Company Joint Stock CompanyThe subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 00160700936873
Unscheduled inspection
Start date: 2016-10-03, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160700679276
Unscheduled inspection
Start date: 2016-09-16, end date: 2016-10-13, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the fulfillment of paragraphs 49 of the regulation dated 29082016 576070P issued by the North Ural Department of Rostechnadzor. The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Joint Stock Company Ural Heating Grid Company FLA Tyumen Thermal NetworksThe subject of this audit is to note the necessary compliance with the instructions of the state control bodies supervision of municipal control bodies
# 00160601719121
Unscheduled inspection
Start date: 2016-08-02, end date: 2016-08-29, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the progress of preparation of electric and heat supply organizations for work in the autumn-winter period of 2016-2017. The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts. The subject of this audit is compliance with mandatory requirements or requirements established by legal acts.
# 00150601351285
Unscheduled inspection
Start date: 2015-12-03, end date: 2015-12-23, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 04092015 g 574788P issued by the North Ural Department of Rostechnadzor
# 00150600027731
Unscheduled inspection
Start date: 2015-08-10, end date: 2015-09-04, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation of electric and heat supply organizations for work in the autumn-winter period 20152016
# 002004306841
Unscheduled inspection
Start date: 2020-03-02, end date: 2020-03-30, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out in order to comply with the order of the Federal Service for Environmental Technological and Nuclear Supervision dated January 13, 2020 13 "On conducting inspections of compliance with mandatory requirements by subjects of the electric power industry, heat supply organizations, heating grid organizations and consumers of electric energy in 2020" on the basis of an instruction from the Government of the Russian Federation dated December 30, 2019 DKP911542 The objectives of this inspection is to establish the fact compliance with non-compliance with the requirements of legislation in the established field of activity The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts
# 742004208162
Unscheduled inspection
Start date: 2020-01-15, end date: 2020-01-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1960892 of 19112019
# 721904277941
Unscheduled inspection
Start date: 2019-12-10, end date: 2019-12-13, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out state construction supervision on the basis of a notice of completion of construction reconstruction of a capital construction facility dated 29112019. The objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer during the reconstruction of the capital construction facility construction "Reconstruction of a transport interchange at different levels at the intersection of the Moskvavladok railway with Melnikaite street, Tyumen Correction" Stage 6" located at the address Russian Federation Tyumen region, Tyumen city The subject of this inspection is compliance with mandatory requirements
# 741903970146
Unscheduled inspection
Start date: 2019-11-13, end date: 2019-11-19, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1949772 of 30092019
# 721904270974
Unscheduled inspection
Start date: 2019-10-02, end date: 2019-10-15, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: This inspection is carried out in order to carry out state construction supervision on the basis of a notice on the completion dates of works subject to inspection during the construction of a capital construction facility dated 17092019the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer, as well as the person carrying out construction on the basis of an agreement with the developer or the customer during the construction of the capital construction facility "Reconstruction of the transport interchange at different levels at the intersection of the Moskvavladyok railway with Melnikaite street, Tyumen, Correction "Stage 6" located at the address Russian Federation, Tyumen region, Tyumen city, the subject of this inspection is compliance with mandatory requirements
# 741903622449
Unscheduled inspection
Start date: 2019-09-18, end date: 2019-09-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2874 of 31052019
# 741903625000
Unscheduled inspection
Start date: 2019-09-23, end date: 2019-09-30, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 193858 3885 of 30072019
# 721902887142
Unscheduled inspection
Start date: 2019-07-23, end date: 2019-08-05, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: this inspection is carried out in order to carry out state construction supervision on the basis of a notice of the beginning of construction reconstruction of a capital construction facility dated 12072019the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by a person carrying out construction on the basis of an agreement with the developer or the customer during the construction of a capital construction facility construction "Reconstruction of a transport interchange at different levels at the intersection of the Moskvavladok railway with Melnikaite street, Tyumen Correction" Stage 6" located at the address Russian Federation, Tyumen region, Tyumen city, the subject of this check is the compliance of the information contained in the notification of the commencement of certain types of entrepreneurial activity with mandatory requirements
# 741902899415
Unscheduled inspection
Start date: 2019-07-24, end date: 2019-07-30, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2700 of 07062019
# 741902725194
Unscheduled inspection
Start date: 2019-06-03, end date: 2019-06-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1736 of 29032019
# 741902758478
Unscheduled inspection
Start date: 2019-05-30, end date: 2019-05-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1426 of 28032019
# 741902758459
Unscheduled inspection
Start date: 2019-05-30, end date: 2019-05-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1424 of 28032019
# 721902589197
Unscheduled inspection
Start date: 2019-03-18, end date: 2019-04-12, duration: —
Authority: Upravlenie Federalnoi sluzhby gosudarstvennoi registracii kadastra i kartografii po Tyumenskoi oblasti
Purpose of inspection: This audit is carried out in order to control the execution of the order to eliminate violations of land legislation issued by 23082018 161136r the objectives of this audit are to ensure that a legal entity complies with land legislation requirements for the protection and use of land The subject of this audit is compliance with mandatory requirements and or requirements established by municipal legal acts and compliance with the instructions of state control bodies supervision of municipal control bodies
# 741902591552
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-03-22, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 207 of 28.012019
# 741902591542
Unscheduled inspection
Start date: 2019-03-20, end date: 2019-03-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 275 of 31.012019
# 741902591530
Unscheduled inspection
Start date: 2019-03-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902553376
Unscheduled inspection
Start date: 2019-03-01, end date: 2019-03-05, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 6163 of 29122018
# 741902600983
Unscheduled inspection
Start date: 2019-03-22, end date: 2019-03-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 268 of 28.012019
# 741902601093
Unscheduled inspection
Start date: 2019-03-22, end date: 2019-03-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 267 of 28.012019
# 741902570742
Unscheduled inspection
Start date: 2019-03-25, end date: 2019-03-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 95 of 18012019
# 741902570729
Unscheduled inspection
Start date: 2019-03-25, end date: 2019-03-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 6047 of 29122018
# 741902477159
Unscheduled inspection
Start date: 2019-02-12, end date: 2019-02-15, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 1049 dated 22.012019
# 741902498023
Unscheduled inspection
Start date: 2019-02-07, end date: 2019-02-11, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 6121 of 28122018
# 741902343948
Unscheduled inspection
Start date: 2019-01-14, end date: 2019-01-15, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 21382 dated 17122018
# 741902439541
Unscheduled inspection
Start date: 2019-01-15, end date: 2019-01-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5055 of 19112018
# 741902437320
Unscheduled inspection
Start date: 2019-01-15, end date: 2019-01-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5370 of 22112018
# 741902437307
Unscheduled inspection
Start date: 2019-01-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902437437
Unscheduled inspection
Start date: 2019-01-15, end date: 2019-01-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 4951 of 12112018
# 741902437293
Unscheduled inspection
Start date: 2019-01-15, end date: 2019-01-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5543 of 30112018
# 741902437286
Unscheduled inspection
Start date: 2019-01-15, end date: 2019-01-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5545 of 30112018
# 741902448689
Unscheduled inspection
Start date: 2019-01-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902456503
Unscheduled inspection
Start date: 2019-01-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741902456494
Unscheduled inspection
Start date: 2019-01-22, end date: 2019-01-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5326 of 26112018
# 741902458199
Unscheduled inspection
Start date: 2019-01-23, end date: 2019-01-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5287 of 16112018
# 741902458179
Unscheduled inspection
Start date: 2019-01-23, end date: 2019-01-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5286 of 16112018
# 741802343921
Unscheduled inspection
Start date: 2018-12-24, end date: 2018-12-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5024 of 06112018
# 741802343916
Unscheduled inspection
Start date: 2018-12-24, end date: 2018-12-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 5138 of 12112018
# 741802295632
Unscheduled inspection
Start date: 2018-12-24, end date: 2018-12-27, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 20700 dated 04122018
# 741802296371
Unscheduled inspection
Start date: 2018-12-24, end date: 2018-12-25, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the application 20756 dated 04122018
# 741802145681
Unscheduled inspection
Start date: 2018-12-03, end date: 2018-12-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: consideration of the appeal 19308
# 741802394662
Unscheduled inspection
Start date: 2018-12-27, end date: 2018-12-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 205251 of 10122018
# 741802308726
Unscheduled inspection
Start date: 2018-12-27, end date: 2018-12-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 20656 dated 04122018
# 741802421192
Unscheduled inspection
Start date: 2018-12-28, end date: 2018-12-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 4317 of 08102018
# 741802183457
Unscheduled inspection
Start date: 2018-12-11, end date: 2018-12-14, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 19819 of 20112018
# 741802199419
Unscheduled inspection
Start date: 2018-12-14, end date: 2018-12-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 20111 dated 26112018
# 721802151897
Unscheduled inspection
Start date: 2018-11-20, end date: 2018-12-03, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notice dated 13112018 on the completion of construction of a capital construction facility Prevention detection and suppression of violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of Melnikaite Street section of Khabarovsk Street r Tura with a bridge crossing over r Tura Tyumen" Stage 1 Reconstruction of Melnikaite street section of Khabarovsk r Tura street including a transport interchange at different levels at the intersection of Melnikaite street with Dambovskaya street 2nd correction" located at the address Russian Federation Tyumen region Tyumen city
# 741802148410
Unscheduled inspection
Start date: 2018-11-20, end date: 2018-11-22, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741802145718
Unscheduled inspection
Start date: 2018-11-20, end date: 2018-11-26, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741802151612
Unscheduled inspection
Start date: 2018-11-21, end date: 2018-11-22, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741802151597
Unscheduled inspection
Start date: 2018-11-21, end date: 2018-11-22, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741802085938
Unscheduled inspection
Start date: 2018-11-22, end date: 2018-11-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 18730 dated 01112018
# 741802157619
Unscheduled inspection
Start date: 2018-11-23, end date: 2018-11-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741802173004
Unscheduled inspection
Start date: 2018-11-26, end date: 2018-11-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 4823 of 23102018
# 741802182751
Unscheduled inspection
Start date: 2018-11-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741802182719
Unscheduled inspection
Start date: 2018-11-28, end date: —, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection:
# 741802187941
Unscheduled inspection
Start date: 2018-11-29, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741802187928
Unscheduled inspection
Start date: 2018-11-29, end date: 2018-12-05, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 4586 of 10102018
# 741802086024
Unscheduled inspection
Start date: 2018-11-09, end date: 2018-11-12, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 4160 of 21092018
# 741802026570
Unscheduled inspection
Start date: 2018-11-09, end date: 2018-11-15, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 18012 dated 19102018
# 741802026528
Unscheduled inspection
Start date: 2018-11-09, end date: 2018-11-12, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 17828 dated 17102018
# 741802127645
Unscheduled inspection
Start date: 2018-11-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741802127633
Unscheduled inspection
Start date: 2018-11-15, end date: 2018-11-16, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3775 of 23082018
# 741802054701
Unscheduled inspection
Start date: 2018-11-16, end date: 2018-11-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 18321 dated 25102018
# 741802054686
Unscheduled inspection
Start date: 2018-11-16, end date: 2018-11-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 18255 dated 25102018
# 741802054650
Unscheduled inspection
Start date: 2018-11-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741801802236
Unscheduled inspection
Start date: 2018-10-01, end date: 2018-10-08, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3224 of 16082018
# 721802100456
Unscheduled inspection
Start date: 2018-10-24, end date: 2018-10-30, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notification dated 05102018 on the completion of construction of a capital construction facility Prevention detection and suppression of violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of a transport interchange at the intersection of Ul Montazhnikov and Shirotnaya Street" located at the address Russian Federation Tyumen region Tyumen city
# 721802100440
Unscheduled inspection
Start date: 2018-10-24, end date: —, duration: —
Authority: —
Purpose of inspection:
# 721802100376
Unscheduled inspection
Start date: 2018-10-24, end date: 2018-10-30, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notification dated 05102018 on the completion of construction of a capital construction facility Prevention detection and suppression of violations of legislation on urban planning activities, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section 4 along the street Tavrichesky from 4P9 towards 4C43 L= 564 m in two-tube calculation in 2Du600mm insulation foam" located at the address Russian Federation Tyumen region Tyumen city
# 721802100331
Unscheduled inspection
Start date: 2018-10-24, end date: 2018-10-30, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notification dated 05102018 on the completion of construction of a capital construction facility Prevention detection and suppression of violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section along Chaplin Street from pavilion 2P9 to the 4K30 thermal chamber with an increase in diameter of 2Du400mm by 2Du700mm L=466 m in two-tube calculation" located at Tyumen region Tyumen city
# 741802016278
Unscheduled inspection
Start date: 2018-10-24, end date: 2018-11-01, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 17910 dated 18102018
# 741801943458
Unscheduled inspection
Start date: 2018-10-24, end date: —, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection:
# 741801877137
Unscheduled inspection
Start date: 2018-10-02, end date: 2018-10-05, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3191 of 06082018
# 741801877126
Unscheduled inspection
Start date: 2018-10-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741801878518
Unscheduled inspection
Start date: 2018-10-02, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741801890414
Unscheduled inspection
Start date: 2018-10-03, end date: 2018-10-10, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2631 of 27072018
# 741801644900
Unscheduled inspection
Start date: 2018-10-03, end date: 2018-10-05, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 15495 of 10092018
# 741801644759
Unscheduled inspection
Start date: 2018-10-03, end date: 2018-10-08, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 15711 of 12092018
# 741802027717
Unscheduled inspection
Start date: 2018-10-26, end date: 2018-10-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: JSC UTSK
# 741802026552
Unscheduled inspection
Start date: 2018-10-26, end date: 2018-11-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3109 of 13082018
# 741802026505
Unscheduled inspection
Start date: 2018-10-26, end date: 2018-10-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3960 of 07092018
# 741801918446
Unscheduled inspection
Start date: 2018-10-05, end date: 2018-10-10, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3865 of 29082018
# 741801918437
Unscheduled inspection
Start date: 2018-10-05, end date: 2018-10-10, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3194 of 27082018
# 741801918423
Unscheduled inspection
Start date: 2018-10-05, end date: —, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection:
# 721802083584
Unscheduled inspection
Start date: 2018-10-09, end date: 2018-10-22, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program dated 28082018 Prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of Melnikaite Street section of Khabarovsk district with a bridge crossing through the district of Tura Tyumen" Stage 1 Reconstruction of Melnikaite street section of Khabarovsk r Tura street including a transport interchange at different levels at the intersection of Melnikaite street with Dambovskaya street 2nd correction" located at the address Russian Federation Tyumen region Tyumen city
# 741802094090
Unscheduled inspection
Start date: 2018-10-31, end date: 2018-11-02, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2767 of 06082018
# 741802054644
Unscheduled inspection
Start date: 2018-10-31, end date: 2018-10-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 16820 dated 03102018
# 741801936335
Unscheduled inspection
Start date: 2018-10-10, end date: 2018-10-16, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2840 of 07082018
# 741801993760
Unscheduled inspection
Start date: 2018-10-18, end date: 2018-10-23, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3756 of 04092018
# 741800982124
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-09-21, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2636 of 11072018
# 741800981512
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-09-21, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2634 of 11072018
# 741801378622
Unscheduled inspection
Start date: 2018-09-17, end date: 2018-09-21, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 934 of 28032018
# 741800983595
Unscheduled inspection
Start date: 2018-09-18, end date: 2018-09-21, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 14602 dated 28082018
# 741801696719
Unscheduled inspection
Start date: 2018-09-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 721801977258
Unscheduled inspection
Start date: 2018-09-03, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 741800664510
Unscheduled inspection
Start date: 2018-09-04, end date: 2018-09-10, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: consideration of the appeal 13994
# 741801091619
Unscheduled inspection
Start date: 2018-09-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741801231043
Unscheduled inspection
Start date: 2018-09-07, end date: 2018-09-13, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2781 of 26072018
# 741801645023
Unscheduled inspection
Start date: 2018-09-20, end date: 2018-09-25, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 3051 of 08082018
# 721800684167
Unscheduled inspection
Start date: 2018-08-15, end date: 2018-09-04, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program from 26072018 Prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section along Chaplin Street from Pavilion 2P9 to thermal 4K30 cameras with an increase in diameter of 2Du400mm by 2Du700mm L=466 m in two-tube calculation" located at Tyumen region, Tyumen city
# 741800638831
Unscheduled inspection
Start date: 2018-08-15, end date: 2018-08-21, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741800604363
Unscheduled inspection
Start date: 2018-08-15, end date: 2018-08-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 12628 of 25072018
# 741800651062
Unscheduled inspection
Start date: 2018-08-17, end date: 2018-08-23, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: consideration of the application 12787
# 741800651047
Unscheduled inspection
Start date: 2018-08-17, end date: 2018-08-22, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741800800809
Unscheduled inspection
Start date: 2018-08-30, end date: 2018-09-10, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2662 of 18072018
# 741800800621
Unscheduled inspection
Start date: 2018-08-30, end date: 2018-09-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2274 of 18072018
# 741800651700
Unscheduled inspection
Start date: 2018-08-30, end date: 2018-09-04, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: consideration of the appeal 13658
# 741800661240
Unscheduled inspection
Start date: 2018-08-31, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800626853
Unscheduled inspection
Start date: 2018-08-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800626837
Unscheduled inspection
Start date: 2018-08-10, end date: 2018-08-13, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: consideration of the appeal 13267
# 741800593263
Unscheduled inspection
Start date: 2018-08-10, end date: 2018-08-17, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 12601 dated 24072018
# 741800633448
Unscheduled inspection
Start date: 2018-08-13, end date: 2018-08-16, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741800577121
Unscheduled inspection
Start date: 2018-08-03, end date: 2018-08-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 11826 dated 12072018
# 741800681278
Unscheduled inspection
Start date: 2018-08-27, end date: 2018-08-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741800616499
Unscheduled inspection
Start date: 2018-08-07, end date: 2018-08-13, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of regulation 1822
# 721800623677
Unscheduled inspection
Start date: 2018-08-09, end date: 2018-08-13, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of notification dated 30072018 on the beginning of construction of the reconstruction of the capital construction facility Prevention detection and suppression of violations of the legislation on urban planning activities, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the section of the heating main 5 along the street Power engineers from the 5K9 thermal chamber to the 5C2 chamber with a diameter of 2Du800 L =139 m in two-tube calculation" located at the address Tyumen region, Tyumen, Energetikov street tp1
# 741800589520
Unscheduled inspection
Start date: 2018-08-09, end date: 2018-08-15, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 12323 dated 20072018
# 721801938282
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program dated 26072018 Prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Construction of a transport interchange at the intersection of Montazhnikov Street and Shirotnaya Street" located at the address Russian Federation Tyumen region Tyumen city
# 721801938214
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program from 26072018 Prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section 4 along Tavrichesky Street from 4P9 towards 4C43 L =564 m in two-tube calculation in PU insulation 2Du600mm" located at the address Russian Federation Tyumen region Tyumen city
# 721801938146
Unscheduled inspection
Start date: 2018-08-20, end date: 2018-09-14, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program from 06082018 Prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the section of the heating main 5 along Energetikov Street from the heat chamber 5K9 to the chamber 5C2 with a diameter of 2Du800 L = 139 m in two-tube calculation" located at the address Tyumen region, Tyumen, Energetikov Street tp1
# 741800620091
Unscheduled inspection
Start date: 2018-08-21, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800664526
Unscheduled inspection
Start date: 2018-08-22, end date: 2018-08-27, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741800664475
Unscheduled inspection
Start date: 2018-08-22, end date: 2018-08-30, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 741800626800
Unscheduled inspection
Start date: 2018-08-23, end date: 2018-08-27, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: consideration of the appeal 13087
# 741800674037
Unscheduled inspection
Start date: 2018-08-24, end date: 2018-08-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: verification of the execution of the prescription
# 721800620988
Unscheduled inspection
Start date: 2018-08-02, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 721800620898
Unscheduled inspection
Start date: 2018-08-02, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 721800620959
Unscheduled inspection
Start date: 2018-08-02, end date: 2018-08-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the notification dated 19072018 on the beginning of construction of the reconstruction of the capital construction facility Prevention identification and suppression of violations of the legislation on urban development, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section 4 on the street" committed by the developer, the customer and the person carrying out construction on the basis of an agreement with the developer or the customer Tavrichesky from 4P9 towards 4C43 L= 564 m in two-tube calculation in 2Du600mm insulation foam" located at the address Russian Federation Tyumen region Tyumen city
# 741800604425
Unscheduled inspection
Start date: 2018-08-02, end date: 2018-08-08, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2198 of 15062018
# 741800571644
Unscheduled inspection
Start date: 2018-08-02, end date: 2018-08-09, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 12016 dated 16072018
# 741800561958
Unscheduled inspection
Start date: 2018-07-17, end date: 2018-07-19, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1680 of 25052018
# 741800525785
Unscheduled inspection
Start date: 2018-07-17, end date: 2018-07-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 10989 dated 26062018
# 741800568977
Unscheduled inspection
Start date: 2018-07-19, end date: 2018-07-26, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1887 of 07062018
# 741800591172
Unscheduled inspection
Start date: 2018-07-30, end date: 2018-08-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 2097 of 20062018
# 741800566480
Unscheduled inspection
Start date: 2018-07-31, end date: 2018-08-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 11759 of 11072018
# 741800545885
Unscheduled inspection
Start date: 2018-07-11, end date: 2018-07-30, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1758 of 28052018
# 741800515292
Unscheduled inspection
Start date: 2018-07-13, end date: 2018-07-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 10798 dated 21062018
# 741800556397
Unscheduled inspection
Start date: 2018-07-26, end date: 2018-07-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 11421 dated 04072018
# 741800492093
Unscheduled inspection
Start date: 2018-07-05, end date: 2018-07-12, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 10308 of 18062018
# 741800495164
Unscheduled inspection
Start date: 2018-07-06, end date: 2018-07-10, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 10196 dated 13062018
# 741800536529
Unscheduled inspection
Start date: 2018-07-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800536464
Unscheduled inspection
Start date: 2018-07-09, end date: 2018-07-11, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of the regulation 1948 of 25052018
# 741800536422
Unscheduled inspection
Start date: 2018-07-20, end date: 2018-07-25, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 11135 dated 28062018
# 741800535916
Unscheduled inspection
Start date: 2018-07-20, end date: 2018-07-27, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 11297 dated 03072018
# 741800524095
Unscheduled inspection
Start date: 2018-07-02, end date: —, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po CHelyabinskoi oblasti
Purpose of inspection:
# 741800480344
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-04, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 8776 dated 18052018
# 741800480332
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-04, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the application 10060 from 09062018
# 741800473699
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1708 of 16052018
# 741800473692
Unscheduled inspection
Start date: 2018-07-02, end date: 2018-07-23, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1707 of 16052018
# 741800550049
Unscheduled inspection
Start date: 2018-07-25, end date: 2018-07-31, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 11314 dated 03072018
# 741800519995
Unscheduled inspection
Start date: 2018-07-03, end date: 2018-07-10, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1894 of 23052018
# 741800484216
Unscheduled inspection
Start date: 2018-07-03, end date: 2018-07-05, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the application 10050 from 09062018
# 741800480295
Unscheduled inspection
Start date: 2018-07-03, end date: 2018-07-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 10192 dated 13062018
# 741800431378
Unscheduled inspection
Start date: 2018-06-18, end date: 2018-06-20, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 9269 dated 28052018
# 741800442975
Unscheduled inspection
Start date: 2018-06-06, end date: 2018-06-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1250 of 12042018
# 741800473580
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-07-04, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the application 9984 dated 07062018
# 741800473573
Unscheduled inspection
Start date: 2018-06-29, end date: 2018-07-03, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 9904 dated 06062018
# 741800453008
Unscheduled inspection
Start date: 2018-06-08, end date: 2018-06-15, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1460 of 24042018
# 741800416895
Unscheduled inspection
Start date: 2018-06-09, end date: 2018-06-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the application 9059 of 25052018
# 741800482983
Unscheduled inspection
Start date: 2018-06-20, end date: 2018-06-21, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1345 of 18042018
# 741800448750
Unscheduled inspection
Start date: 2018-06-21, end date: 2018-06-26, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 9450 of 30052018
# 741800393006
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 8468 of 15052018
# 741800392436
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 8150 dated 11052018
# 741800392356
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-08, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 8467 oo 15052018
# 741800392414
Unscheduled inspection
Start date: 2018-06-01, end date: 2018-06-08, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 8569 of 16052018
# 721800429434
Unscheduled inspection
Start date: 2018-05-30, end date: 2018-06-05, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Verification of compliance with urban planning norms and rules during the construction of reconstruction "Reconstruction of the section of the heating main 3 along Kharkov street from the thermal chamber 3K6 to the thermal chamber 3K7" at the address Tyumen region gTyumen Kharkov street on the basis of an appeal from Poluikov WB 18052018 Prevention detection and suppression of violations committed by the developer by the customer as well as by the person carrying out construction on the basis of an agreement with the developer or the customer legislation on urban planning activities, including technical regulations and design documentation for the construction of reconstruction "Reconstruction of the section of the heating main 3 along Kharkov street from the thermal chamber 3K6 to the thermal chamber 3K7" at the address Tyumen region, Tyumen, Kharkov street
# 741800385318
Unscheduled inspection
Start date: 2018-05-31, end date: 2018-06-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 81471 of 11052018
# 741800362719
Unscheduled inspection
Start date: 2018-05-10, end date: 2018-05-16, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 877 of 29032018
# 741800362689
Unscheduled inspection
Start date: 2018-05-10, end date: 2018-05-16, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 832 of 26032018
# 741800393705
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-05-23, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 965 of 03042018
# 741800353039
Unscheduled inspection
Start date: 2018-05-21, end date: 2018-05-24, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 7285 of 27042018
# 741800357924
Unscheduled inspection
Start date: 2018-05-22, end date: 2018-05-25, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 7511 from 03052018
# 741800401158
Unscheduled inspection
Start date: 2018-05-23, end date: 2018-05-25, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 1080 of 13042018
# 741800401122
Unscheduled inspection
Start date: 2018-05-23, end date: 2018-05-25, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 967 of 06042018
# 741800370956
Unscheduled inspection
Start date: 2018-05-24, end date: 2018-05-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 7544 from 03052018
# 741800370986
Unscheduled inspection
Start date: 2018-05-25, end date: 2018-05-30, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 7713 from 04052018
# 741800310809
Unscheduled inspection
Start date: 2018-05-04, end date: 2018-05-08, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the application 6064 dated 11042018
# 741800310787
Unscheduled inspection
Start date: 2018-05-04, end date: 2018-05-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 5869 dated 09042018
# 741800310832
Unscheduled inspection
Start date: 2018-04-19, end date: 2018-04-24, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 364 of 26022018
# 741800285942
Unscheduled inspection
Start date: 2018-04-11, end date: 2018-04-18, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 142 of 06022018
# 741800332572
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-03, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 531 of 02032018
# 741800332559
Unscheduled inspection
Start date: 2018-04-26, end date: 2018-05-03, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 571 of 06032018
# 741800270071
Unscheduled inspection
Start date: 2018-04-05, end date: 2018-04-12, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 4944 of 23012018
# 741800270216
Unscheduled inspection
Start date: 2018-04-05, end date: 2018-04-12, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 140 of 06022018
# 741800270197
Unscheduled inspection
Start date: 2018-04-05, end date: 2018-04-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 509 of 01032018
# 741800232398
Unscheduled inspection
Start date: 2018-04-05, end date: 2018-04-11, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 4175 of 20032018
# 741800236747
Unscheduled inspection
Start date: 2018-04-06, end date: 2018-04-13, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 4119 of 19032018
# 741800215641
Unscheduled inspection
Start date: 2018-03-30, end date: 2018-04-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Verification of regulation 264 of 12022018
# 741800215595
Unscheduled inspection
Start date: 2018-03-30, end date: 2018-04-03, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 3632 of 12032018
# 741800109051
Unscheduled inspection
Start date: 2018-03-13, end date: 2018-02-16, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 2539 of 20022018
# 741800169730
Unscheduled inspection
Start date: 2018-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800183793
Unscheduled inspection
Start date: 2018-03-20, end date: 2018-03-21, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 2798 of 22022018
# 741800192642
Unscheduled inspection
Start date: 2018-03-22, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800196894
Unscheduled inspection
Start date: 2018-03-23, end date: 2018-03-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 3178 from 02032018
# 741800091266
Unscheduled inspection
Start date: 2018-03-02, end date: 2018-03-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 2023 from 09022018
# 741800091544
Unscheduled inspection
Start date: 2018-03-02, end date: 2018-03-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 2137 of 12022018
# 741800205605
Unscheduled inspection
Start date: 2018-03-26, end date: 2018-03-28, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 3021 of 28022018
# 741800211214
Unscheduled inspection
Start date: 2018-03-28, end date: 2018-03-29, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 20581 of 12022018
# 741800167135
Unscheduled inspection
Start date: 2018-03-07, end date: 2018-03-07, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 2617 of 20022018
# 741800054761
Unscheduled inspection
Start date: 2018-02-16, end date: 2018-02-26, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 1372 of 30012018
# 741800026428
Unscheduled inspection
Start date: 2018-02-09, end date: —, duration: —
Authority: —
Purpose of inspection:
# 741800081233
Unscheduled inspection
Start date: 2018-02-27, end date: 2018-03-01, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 1731 from 05022018
# 741800085265
Unscheduled inspection
Start date: 2018-02-28, end date: 2018-03-02, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 1757 of 06022018
# 741800023061
Unscheduled inspection
Start date: 2018-02-07, end date: 2018-02-13, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 722 dated 18012018
# 741800006021
Unscheduled inspection
Start date: 2018-01-31, end date: 2018-02-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of appeal 187 dated 11012018
# 741800006143
Unscheduled inspection
Start date: 2018-01-31, end date: 2018-02-06, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 323 dated 12012018
# 00180803061306
Unscheduled inspection
Start date: 2018-01-16, end date: 2018-01-16, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 74170803044703
Unscheduled inspection
Start date: 2017-12-29, end date: 2018-01-23, duration: —
Authority: Glavnoe upravlenie Gosudarstvennaya zhilischnaya inspekciya CHelyabinskoi oblasti
Purpose of inspection: Consideration of the appeal 21483 dated 26/122017
# 00170802941210
Unscheduled inspection
Start date: 2017-12-07, end date: 2017-12-08, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 72170803031752
Unscheduled inspection
Start date: 2017-12-27, end date: 2018-01-10, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Verification of the elimination of violations according to the order of 07112017 1417pl during the construction of the reconstruction of an object of capital construction on the basis of the notification of 19122017 on the elimination of violations during the construction of the reconstruction of an object of capital construction Prevention identification and suppression of violations of the legislation on urban development, including technical regulations and project documentation, committed by the developer, the customer and the person carrying out construction on the basis of an agreement with the developer or the customer during the reconstruction of the capital construction facility, the reconstruction of the section of the heating main 6 along Energetikov Street from 6K11 to 6C9 in PU insulation 2Du600mm L = 300 m in two-pipe calculation located at Tyumen region Tyumen EnergetikovTP2 Tyumen region Tyumen Energetikovtp3
# 00170802912252
Unscheduled inspection
Start date: 2017-12-04, end date: 2017-12-05, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 72170802707373
Unscheduled inspection
Start date: 2017-10-05, end date: 2017-11-01, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notice dated 25092017 on the completion of construction reconstruction of a capital construction facility, prevention of detection and suppression of violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the construction of a capital construction facility "Construction of a supply pipeline from PNC3 2Du700 mm L=140 m in two-pipe calculation" located at the address Tyumen region, Tyumen city
# 72170802699389
Unscheduled inspection
Start date: 2017-10-02, end date: 2017-10-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notification dated 21092017 on the completion of construction of a capital construction facility, Prevention of detection and suppression of violations of legislation on urban planning, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section 9 along Shirotnaya Street from 2C30 to 9P3A in PU insulation 2Du1020 Lk=246 m in two-tube calculation" located at Tyumen region, Tyumen, Shirotnayatp2 street
# 72170802775960
Unscheduled inspection
Start date: 2017-10-20, end date: 2017-11-17, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notice dated 10102017 on the completion of construction of a capital construction facility, prevention of detection and suppression of violations of legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Modernization of PNC3 with the installation of pumping units on the supply pipeline of Tyumen Parkovaya street d 2 page 1" located at Tyumen region Tyumen city Parkovaya street d 2 building 1
# 72170802769721
Unscheduled inspection
Start date: 2017-10-13, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 72170802707483
Unscheduled inspection
Start date: 2017-10-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00170802489736
Unscheduled inspection
Start date: 2017-09-18, end date: 2017-09-19, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 72170802612717
Unscheduled inspection
Start date: 2017-09-15, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72170802612739
Unscheduled inspection
Start date: 2017-09-15, end date: 2017-09-28, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notice dated 29082017 on the completion of construction of a capital construction facility Prevention detection and suppression of violations of legislation on urban planning activities, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section 2 along the street Permyakova from 2C9 to 2P5A in PU insulation Dn800 mm L =153 m in two-tube calculation" located at the address Tyumen region Tyumen Permyakova street tp2
# 72170701896553
Unscheduled inspection
Start date: 2017-08-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72170701889051
Unscheduled inspection
Start date: 2017-08-09, end date: 2017-08-15, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: implementation of state construction supervision on the basis of the notification of the beginning of construction of the reconstruction of the capital construction facility dated 28072017. Prevention of detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the construction of the capital construction facility "Construction of the supply pipeline from PNC3 2Du700 mm L=140 m in two-pipe calculation" located at Tyumen region, Tyumen city
# 72170802542576
Unscheduled inspection
Start date: 2017-08-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72170701863896
Unscheduled inspection
Start date: 2017-08-01, end date: 2017-08-28, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program from 28062017 Prevention of detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the section of the heating main 2 along Permyakova Street from 2C9 to 2P5A in PU insulation DN800 mm L=153 m in two-tube calculation" located at the address Tyumen region, Tyumen, Permyakova street tp2
# 72170701864009
Unscheduled inspection
Start date: 2017-08-01, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 72170701861948
Unscheduled inspection
Start date: 2017-07-17, end date: 2017-08-11, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program from 15062017 Prevention detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer during the reconstruction of the capital construction facility "Modernization of PNC3 with the installation of pumping units on the supply pipeline of Tyumen Parkovaya street d2 page 1" located at Tyumen region Tyumen city Parkovaya street d 2 building 1
# 72170701862190
Unscheduled inspection
Start date: 2017-07-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00170701822706
Unscheduled inspection
Start date: 2017-07-25, end date: 2017-08-18, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this inspection is carried out in order to verify the progress of preparation of electric and heat supply organizations for work in the autumn-winter period 2017-2018 Order of the Federal Service for Environmental Technological and Nuclear Supervision dated 10072017 256 the objectives of this inspection are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts The subject of this inspection is to ensure compliance with mandatory requirements or requirements established by legal acts
# 72170701819406
Unscheduled inspection
Start date: 2017-07-04, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72170701807388
Unscheduled inspection
Start date: 2017-07-04, end date: 2017-07-07, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of notification dated 23062017 on the beginning of construction of the reconstruction of the capital construction facility, Prevention of detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section 2 on Permyakova Street from 2C9 to 2P5A in PU insulation Dn800 mm L =153 m in two-tube calculation" located at the address Tyumen region, Tyumen, Permyakova street tp2
# 00170701820676
Unscheduled inspection
Start date: 2017-07-24, end date: 2017-07-25, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 72170701712539
Unscheduled inspection
Start date: 2017-06-09, end date: 2017-06-16, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notification dated 31052017 on the beginning of construction reconstruction of a capital construction facility, verification of compliance of work and construction materials used during construction, as well as the results of such work, with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used during reconstruction of the facility capital construction "Reconstruction of the section of the heating main 9 along Latitudinal street from 2C30 to 9P3A in PU insulation 2Du1020 Lk = 246 m in two-pipe calculation" located at Tyumen region, Tyumen, Latitudinal street 2
# 00170701736863
Unscheduled inspection
Start date: 2017-06-26, end date: 2017-06-27, duration: —
Authority: Uralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: issuance of a permit for the commissioning of power plants
# 72170701679155
Unscheduled inspection
Start date: 2017-06-02, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 72170701754659
Unscheduled inspection
Start date: 2017-06-23, end date: 2017-07-13, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program from 19052017, prevention of detection and suppression of violations of legislation on urban planning, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the section of the heating main 3 on Dzerzhinsky Street from 3K14 to 5K27 in PU insulation Du500mm L=515 m in two-tube calculation" located at the address Tyumen region, Tyumen, Dzerzhinsk str. 1
# 72170701754731
Unscheduled inspection
Start date: 2017-06-23, end date: —, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection:
# 72170701754692
Unscheduled inspection
Start date: 2017-06-23, end date: 2017-07-13, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the inspection program dated 29052017, prevention of detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the heating main section 4 along Volgogradskaya Street from 4K14 to 4P8 in PU insulation Du600mm L=433 m in two-tube calculation" located at the address Tyumen region, Tyumen, Tavrichesky str. 1
# 72170701727057
Unscheduled inspection
Start date: 2017-06-21, end date: 2017-06-27, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of notification dated 09062017 1 on the beginning of construction of the reconstruction of the capital construction facility, verification of compliance of the work and the construction materials used during construction as well as the results of such work with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used during reconstruction the capital construction project "Modernization of PNC3 with the installation of pumping units on the supply pipeline Tyumen Parkovaya str. d2 page 1" located at Tyumen region Tyumen Parkovaya str. d 2 building 1
# 00170701623106
Unscheduled inspection
Start date: 2017-05-16, end date: 2017-06-13, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya Tyumenskoi oblasti
Purpose of inspection: verification of the execution of the instruction from 16032017 TO2404 for an apartment building 140 on Internatsionalnaya street, Tyumen, Prevention of detection and suppression of violations of mandatory requirements, compliance with the instructions of state control and supervision bodies
# 00170701622748
Unscheduled inspection
Start date: 2017-05-16, end date: 2017-06-13, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya Tyumenskoi oblasti
Purpose of inspection: verification of the execution of the order from 16032017 TO2404 for an apartment building 140 on Internatsionalnaya Street in Tyumen prevention detection and suppression of violations of mandatory requirements compliance with the instructions of state control and supervision bodies
# 72170701678524
Unscheduled inspection
Start date: 2017-05-30, end date: 2017-06-13, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of notification dated 15052017 1 on the beginning of construction of the reconstruction of the capital construction facility, Prevention of detection and suppression of violations of the legislation on urban development, including technical regulations and design documentation, committed by the developer, the customer, as well as by the person carrying out construction on the basis of an agreement with the developer or the customer, including technical regulations and design documentation during the reconstruction of the capital construction facility "Reconstruction of the section of the heating main 6 along the street Power engineers from 6K11 to 6C9 in PU insulation 2Du600mm L=300 m in two-tube calculation" located at Tyumen region Tyumen EnergetikovTP2 Tyumen region Tyumen Energetikovtp3
# 72170701647763
Unscheduled inspection
Start date: 2017-05-26, end date: 2017-06-08, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of notification dated 12052017 on the beginning of construction reconstruction of the capital construction facility, Verification of compliance of the work and construction materials used during construction as well as the results of such work with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used during the reconstruction of the facility capital construction "Reconstruction of the section of the heating main 3 along the Uldzerginsky from 3K14 to 5K27 in PU insulation Du500mm L=515 m in two-pipe calculation" located at the address Tyumen region, Tyumen, Dzerzhinskogotp1
# 00170701419125
Unscheduled inspection
Start date: 2017-02-27, end date: 2017-03-27, duration: —
Authority: Gosudarstvennaya zhilischnaya inspekciya Tyumenskoi oblasti
Purpose of inspection: consideration of the application from 15022017 1178zh17 for an apartment building at 140 Internatsionalnaya Street in Tyumen
# 74170701287345
Unscheduled inspection
Start date: 2017-01-12, end date: 2017-01-18, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The actual condition of the object2the presence of a construction permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74170701318070
Unscheduled inspection
Start date: 2017-01-27, end date: 2017-02-24, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of the completed construction object2the receipt of a construction permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 00160701194319
Unscheduled inspection
Start date: 2016-12-05, end date: 2016-12-20, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the fulfillment of paragraphs 13 of the regulation dated 29082016 576070P issued by the North Ural Department of Rostechnadzor. The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Ural Heating Grid Company Joint Stock CompanyThe subject of this audit is the fulfillment of the instructions of the state control bodies supervision of municipal control bodies
# 72160701064765
Unscheduled inspection
Start date: 2016-11-01, end date: 2016-11-29, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notice of completion of construction reconstruction of a capital construction facility dated 21102016 Verification of compliance of work and construction materials used during construction as well as the results of such work with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used during reconstruction the capital construction project "Reconstruction of the section of the heating main 1 Odesskaya street from chamber 11P1 to chamber 1P2 with an increase in diameter of 2Du700 mm by Du1000 mm L =900 m in two-pipe calculation adjustment" located at Tyumen region Tyumen Energetikov TP2 street
# 74160700992561
Unscheduled inspection
Start date: 2016-10-11, end date: 2016-11-08, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of a capital construction facility completed 2 Availability of a construction permit 3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 00160700936873
Unscheduled inspection
Start date: 2016-10-03, end date: 2016-11-14, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: purpose verification of compliance with the regulation of 22052015 571701 Task verification of elimination of violations of industrial safety requirements
# 74160700604845
Unscheduled inspection
Start date: 2016-09-27, end date: 2016-10-17, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Verification of a capital construction facility completed 2The receipt of a construction permit 3The fulfillment of the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 72160700142607
Unscheduled inspection
Start date: 2016-09-05, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160700072491
Unscheduled inspection
Start date: 2016-09-05, end date: 2016-09-30, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to verify the fulfillment of paragraphs 1316 of the regulation dated 04092015 g 574788P issued by the North Ural Department of Rostechnadzor The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Joint Stock Company "Ural Heating Grid Company" The subject of this audit is to note the necessary compliance with the instructions of state control bodies supervision of municipal control bodies
# 74160700124866
Unscheduled inspection
Start date: 2016-09-07, end date: —, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection:
# 72160700867576
Unscheduled inspection
Start date: 2016-09-28, end date: —, duration: —
Authority: —
Purpose of inspection:
# 72160700867251
Unscheduled inspection
Start date: 2016-09-28, end date: 2016-10-18, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of the notice of completion of construction reconstruction of the capital construction facility dated 15092016 Verification of compliance of the work and the construction materials used during construction as well as the results of such work with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used during reconstruction the capital construction project "Reconstruction of the section of the heating main 2 along Permyakova Street from 2C11 to 2K11 in PU insulation 2Du800 L =398 m in two-pipe calculation" located at the address Tyumen region Tyumen Permyakova street tp3
# 72160700422691
Unscheduled inspection
Start date: 2016-09-12, end date: 2016-09-23, duration: —
Authority: Upravlenie gosudarstvennogo stroitelnogo nadzora po Tyumenskoi oblasti Glavnogo upravleniya stroitelstva Tyumenskoi oblasti
Purpose of inspection: Implementation of state construction supervision on the basis of a notice of completion of construction reconstruction of a capital construction facility dated 01092016 Verification of compliance of work and construction materials used during construction as well as the results of such work with the requirements of technical regulations and other regulatory legal acts of project documentation, including energy efficiency requirements and requirements for equipping a capital construction facility with metering devices for energy resources used during reconstruction the capital construction project "Reconstruction of the tm 2 section along 30 Let Pobedy Street from 2K9 to 10K2 in PU insulation 2Du530 Lk =440 m in two-pipe calculation" located at Tyumen region, Tyumen, 30 let Pobedy Street tp 3
# 00160700679276
Unscheduled inspection
Start date: 2016-09-16, end date: 2016-10-13, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the fulfillment of paragraphs 49 of the regulation dated 29082016 576070P issued by the North Ural Department of Rostechnadzor. The tasks of this audit are to verify the elimination of violations of the requirements identified by the North Ural Department of Rostechnadzor during the audit in relation to the Joint Stock Company Ural Heating Grid Company FLA Tyumen Thermal NetworksThe subject of this audit is to note the necessary compliance with the instructions of the state control bodies supervision of municipal control bodies
# 00160601719121
Unscheduled inspection
Start date: 2016-08-02, end date: 2016-08-29, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to verify the progress of preparation of electric and heat supply organizations for work in the autumn-winter period of 2016-2017. The objectives of this audit are to prevent identify and suppress violations of mandatory requirements of regulatory documents and legislative acts. The subject of this audit is compliance with mandatory requirements or requirements established by legal acts.
# 74160700084061
Unscheduled inspection
Start date: 2016-08-31, end date: 2016-09-06, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1The compliance of the work on the installation of the transition channel of the 2D377X8PP pipe with the installation of the TC installation of the UEC system and the construction materials used during the construction reconstruction of the capital construction facility as well as the results of such work with the requirements of the technical regulations of the project documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 74160601775949
Unscheduled inspection
Start date: 2016-08-10, end date: 2016-08-16, duration: —
Authority: Ministerstvo stroitelstva i infrastruktury CHelyabinskoi oblasti
Purpose of inspection: 1 Compliance of the work on dismantling the existing 2D 350mm steel pipe and the construction materials used during the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of the project documentation2 Availability of a construction permit 3 Compliance with the requirements of hh 23 st52 of the Urban Planning Code of the Russian Federation
# 72160601478033
Unscheduled inspection
Start date: 2016-02-01, end date: 2016-02-29, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Tyumenskoi oblasti
Purpose of inspection: Federal Law No. 294 FZ dated 26122008 "On the protection of the Rights of Legal Entities and Individual Entrepreneurs in the implementation of State Control supervision and Municipal Control" Federal Law No. 30031999g 52 FZ "On Sanitary and Epidemiological Welfare of the Population Collection of Legislation of the Russian Federation 1999g 14 st1650" Law of the Russian Federation dated 07021992g 23001 "On Consumer Protection" SanPiN 221211120003 "Sanitary protection zones and sanitary classification enterprises of structures and other facilities" New edition
# 00150601351285
Unscheduled inspection
Start date: 2015-12-03, end date: 2015-12-23, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: verification of the execution of the order dated 04092015 g 574788P issued by the North Ural Department of Rostechnadzor
# 00150600027731
Unscheduled inspection
Start date: 2015-08-10, end date: 2015-09-04, duration: —
Authority: SeveroUralskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Checking the progress of preparation of electric and heat supply organizations for work in the autumn-winter period 20152016