# 001904172181
Unscheduled inspection
Start date: 2019-12-16, end date: 2019-12-20, duration: —
Authority: Privolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: execution of the Rostechnadzor Order dated 01022019 44 "On conducting inspections of compliance with mandatory requirements by subjects of the electric power industry, heat supply organizations, heating grid organizations and consumers of electric energy in 2019" issued in accordance with the instruction of the Government of the Russian Federation dated 18012019 DKP9274 The tasks of this audit are to prevent the identification and suppression of violations of mandatory safety requirements established by federal laws and other regulatory acts of the Russian Federation in the field of electric power and heat supply
# 161902965119
Unscheduled inspection
Start date: 2019-07-31, end date: 2019-08-01, duration: —
Authority: Upravlenie Federalnoi sluzhby po veterinarnomu i fitosanitarnomu nadzoru po Respublike Tatarstan
Purpose of inspection: implementation of ASF measures
# 161902689442
Unscheduled inspection
Start date: 2019-04-25, end date: 2019-05-29, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: The purpose of the audit is to protect the rights and interests of employees on the basis of ch7 st360 of the Labor Code of the Russian Federation The tasks of the audit are to ensure compliance and protection of labor rights and freedoms of citizens ensuring compliance by the employer with labor legislation and other regulatory legal acts containing labor law norms The subject of the audit is compliance with mandatory requirements or requirements established by municipal legal acts
# 161801583498
Unscheduled inspection
Start date: 2018-09-14, end date: 2018-09-20, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the work performed, the construction materials used during the reconstruction of the capital construction facility, as well as the results of such work with the requirements of the technical regulations of the project documentation, including the requirements for energy efficiency and the requirements for equipping capital construction facilities with metering devices for energy resources used at the completion stage, as well as for the purpose of drawing up an act of verification of the completed reconstruction of the facility in accordance with with the notice received by the Inspection dated 05092018 6379 on the completion of the reconstruction of the capital construction facility, the objectives of this inspection are to prevent, identify and prevent violations of compliance by the developer, the customer, the person carrying out the reconstruction on the basis of a contract with the developer or the customer of the work performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation. The purpose of the audit is to select the required compliance with mandatory requirements and or requirements established by municipal legal acts
# 161800443076
Unscheduled inspection
Start date: 2018-06-09, end date: 2018-06-13, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This inspection is carried out in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the notice received by the Inspectorate dated 29052018 3726 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 24032017 1319009901 to 16042018 The objectives of this audit are to prevent as well as identify and suppress violations of compliance of works performed during the construction of a capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation committed by the developer, the customer or the person carrying out the reconstruction on the basis of a contract with the developer or the customer. 7 The subject of this audit is to select the necessary compliance with the requirements of state control bodies, supervision bodies, municipal control bodies
# 16170802692937
Unscheduled inspection
Start date: 2017-10-04, end date: 2017-10-31, duration: —
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Respublike Tatarstan Tatarstan
Purpose of inspection: The purpose of licensing activities in the field of the use of pathogens of infectious diseases of humans and animals, except if the specified activity is carried out for medical purposes and genetically modified organisms of III and IV degrees of potential danger carried out in closed systems, the task is to assess the fulfillment of mandatory requirements of the legislation of the Russian Federation when carrying out activities in the field of the use of pathogens of infectious diseases of humans and animals, except if the specified activity is carried out for medical purposes and genetically modified organisms of the III and IV degrees of potential danger carried out in closed systems, compliance with mandatory requirements and or requirements established by municipal legal acts, compliance with information contained in the application and documents of a legal entity or individual entrepreneur on granting legal status of a special permit license for the right to carry out certain types of activities or authorization approval for other legally significant actions if the conduct of an appropriate unscheduled inspection of a legal entity individual entrepreneur is provided for by the rules for granting the legal status of a special permit license permit approval of mandatory requirements as well as data on these legal entities and individual entrepreneurs contained in the unified state register of legal entities the unified state register of individual entrepreneurs and other federal information resources
# 16170701505237
Unscheduled inspection
Start date: 2017-04-03, end date: 2017-04-03, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: This audit is conducted in order to determine the fact of compliance with the order dated 24032017 1319009901, the deadline for which expired on 01082017, and to draw up an act based on the results of the audit. The objectives of this audit are to prevent, as well as identify and prevent violations of compliance by the developer, the customer, the person carrying out construction on the basis of a contract with the developer or the customer, of compliance with the requirements of technical regulations and other regulatory legal acts performed during the construction of a capital construction facility. acts and project documentation6 The subject of this audit is to select the necessary fulfillment of the Inspection regulations
# 16170701454526
Unscheduled inspection
Start date: 2017-03-16, end date: —, duration: —
Authority: —
Purpose of inspection:
# 16170701468428
Unscheduled inspection
Start date: 2017-03-20, end date: 2017-04-14, duration: —
Authority: Gosudarstvennaya inspekciya truda v Respublike Tatarstan
Purpose of inspection: protection of the rights and interests of employees
# 16160701051976
Unscheduled inspection
Start date: 2016-10-27, end date: 2016-10-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Respubliki Tatarstan
Purpose of inspection: in order to determine the compliance of the eliminated violations with the requirements of technical regulations, project documentation, other regulations, norms and rules, as well as to draw up an act on the elimination of violations based on the Inspection notification dated 18102016 9259 on the elimination of violations during the construction of the reconstruction of the capital construction facility, which was ordered to be eliminated within the time limit set by the regulation from 23092016 1319048401 to 23112016 tasks prevention and also, the identification and suppression of violations committed by the person carrying out construction on the basis of a contract with the developer or the customer of the compliance of the works performed during the construction of the capital construction facility with the requirements of technical regulations, other regulatory legal acts and project documentation, while eliminating previously identified violations, is subject to the requirements of the Inspection
# 16160700871422
Unscheduled inspection
Start date: 2016-09-15, end date: —, duration: —
Authority: —
Purpose of inspection: