# 342100236592
Unscheduled inspection
Start date: 2021-05-25, end date: —, duration: —
Authority: —
Purpose of inspection:
# 342100059086
Unscheduled inspection
Start date: 2021-03-12, end date: 2021-04-08, duration: 20
Authority: Upravlenie Federalnoi sluzhby po nadzoru v sfere zaschity prav potrebitelei i blagopoluchiya cheloveka po Volgogradskoi oblasti
Purpose of inspection: The inspection is carried out in order to: verify the execution of the instruction on the elimination of identified violations of mandatory requirements No. 487-08-20 dated 03/11/2020.
The objectives of the audit are: monitoring (supervision) of compliance by a legal entity with mandatory requirements established by the legislation of the Russian Federation in the field of sanitary and epidemiological welfare of the population.
The subject of the audit is the fulfillment of the instructions of the state control (supervision) bodies, municipal control bodies
# 342004313175
Unscheduled inspection
Start date: 2020-02-26, end date: —, duration: —
Authority: —
Purpose of inspection:
# 341903385674
Unscheduled inspection
Start date: 2019-09-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 341902612628
Unscheduled inspection
Start date: 2019-04-01, end date: 2019-04-04, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: the inspection is carried out in order to assess the compliance of the Object with the requirements of regulatory legal acts and project documentation the task of this inspection is to ensure that the Object complies with the requirements of regulatory legal acts and project documentation The subject of this inspection is compliance with mandatory requirements regarding the compliance of construction works with their results and applied building materials with the requirements of regulatory legal acts and project documentation
# 001902546328
Unscheduled inspection
Start date: 2019-02-28, end date: 2019-03-04, duration: —
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: this audit is carried out in order to fulfill the requirements of EcoTON LLC in paragraphs 1 to 2 of the previously issued regulation of the NizhnEvolzhsky Rostechnadzor Department 161611rpP dated 07052018. The purpose of this audit is to verify the completeness and timeliness of eliminating violations of industrial safety requirements and requirements and conditions in the implementation of the licensed type of activity identified by the Nizhnevolzhsky Rostechnadzor Department and specified in the previously issued regulation 161611rpP from 07052018, the subject of this audit is the fulfillment of the instructions of the state control and supervision bodies
# 341902534539
Unscheduled inspection
Start date: 2019-02-26, end date: 2019-02-28, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: the inspection is carried out in order to assess the compliance of activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection fire safety requirements and sanitary and epidemiological welfare of the population as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for used energy resources of project documentation b the purpose of this inspection is to prevent identify and suppress violations of legislation The subject of this audit is compliance with mandatory requirements regarding a compliance of construction works, their results and applied building materials with the requirements of design documentation b availability of a construction permit c compliance with the requirements established by Parts 2 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 341802162462
Unscheduled inspection
Start date: 2018-11-20, end date: —, duration: —
Authority: —
Purpose of inspection:
# 001800374571
Unscheduled inspection
Start date: 2018-04-27, end date: 2018-05-07, duration: —
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: the inspection is carried out in order to comply with the previously issued order dated 22012018 1511rpP issued by the Nizhnevolzhsky Department of Rostechnadzor, the deadline for which expired 15032018 The task of this inspection is the execution of EcoTON LLC of the order dated 22012018 1511rpP issued by the Nizhnevolzhsky Department of Rostechnadzor
# 00180803053340
Unscheduled inspection
Start date: 2018-01-16, end date: 2018-01-22, duration: —
Authority: NizhneVolzhskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this audit is carried out in order to comply with the previously issued prescription 28082017 295111rpP issued by the Nizhnevolzhsky Department of Rostechnadzor, the deadline for which has expired, the task of this audit is to comply with EcoTON LLC's prescription of 28082017 295111rpP issued by the Nizhnevolzhsky Department of Rostechnadzor
# 34160700089715
Unscheduled inspection
Start date: 2016-09-02, end date: 2016-09-09, duration: —
Authority: Inspekciya gosudarstvennogo stroitelnogo nadzora Volgogradskoi oblasti
Purpose of inspection: The purpose is to comply with the activities carried out at the Facility with the requirements of urban planning legislation of the Russian Federation legislation of the Russian Federation in the field of environmental protection fire safety requirements and sanitary and epidemiological welfare of the population as well as energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used, including technical regulations and project documentation tasks prevention detection and suppression of violations of the legislation of the Russian Federation in including technical regulations and design documentationsubject compliance with mandatory requirements in relation to the compliance of construction works with their results and applied building materials with the requirements of technical regulations of design documentationand the availability of a construction permit and compliance with established requirements for admission to construction work