Found 7 inspections:

# 782100764120
Unscheduled inspection
Start date: 2021-09-17, end date: —, duration: 10
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: compliance with the regulations of state control (supervision) bodies and municipal control bodies - compliance by organizations and citizens with fire safety requirements in buildings, premises, structures, linear objects, territories, and land plots owned and/or used by organizations and citizens and subject to fire safety requirements, as well as assessment of their compliance with fire safety requirements.


# 782100886996
Unscheduled inspection
Start date: 2021-09-22, end date: —, duration:
Authority:
Purpose of inspection:


# 782100611358
Unscheduled inspection
Start date: 2021-08-18, end date: —, duration:
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection:


# 782100362725
Unscheduled inspection
Start date: 2021-07-29, end date: —, duration:
Authority:
Purpose of inspection:


# 782100093662
Unscheduled inspection
Start date: 2021-03-25, end date: 2021-04-16, duration: 20
Authority: Glavnoe upravlenie MCHS Rossii po Leningradskoi oblasti
Purpose of inspection: control over the execution of an earlier issued prescription


# 47170701372248
Unscheduled inspection
Start date: 2017-02-09, end date: 2017-03-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on the completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements equipment of the capital construction facility with metering devices for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


# 47170701372245
Unscheduled inspection
Start date: 2017-02-09, end date: 2017-03-13, duration:
Authority: Komitet gosudarstvennogo stroitelnogo nadzora i gosudarstvennoi ekspertizy Leningradskoi oblasti
Purpose of inspection: Purpose verification of completion of work on the implementation of construction reconstruction of the capital construction facility specified in the notice of the developer of the technical customer on the completion of construction The subject of this audit is compliance with mandatory requirements, including compliance of the work and construction materials used in the construction process of reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements equipment of the capital construction facility with metering devices for used energy resourcescompliance with the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation


Information about inspections

This section displays information about planned and carried out inspections of control (supervision) bodies in accordance with Federal Law No. 294-FZ. Detailed information about the inspection can be obtained from the Unified Register of Inspections of the Prosecutor General's Office.