# 002005205058
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-16, duration: 10
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including project documentation. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in the event of their identification and prosecution of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts, the subject of this audit is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation with taking into account the changes made to the design documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of Article 52 The Urban Planning Code of the Russian Federation
# 002004474772
Unscheduled inspection
Start date: 2020-08-05, end date: 2020-08-18, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 001902480455
Unscheduled inspection
Start date: 2019-02-07, end date: 2019-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out in order to control the execution of the order dated May 23, 2018 366G3327X60
# 00160601462900
Unscheduled inspection
Start date: 2016-01-11, end date: 2016-02-09, duration: —
Authority: Federalnaya antimonopolnaya sluzhba
Purpose of inspection: Prevention and suppression of violations of the requirements established by legislative and other regulations in the field of public health
# 772100310768
Unscheduled inspection
Start date: 2021-06-28, end date: —, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection:
# 772100175817
Unscheduled inspection
Start date: 2021-05-11, end date: 2021-02-20, duration: 5
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu, tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This inspection is carried out in order to implement the inspection program approved by the Deputy head of Rostechnadzor MTU A.A. Kulakov on March 16, 2021.
The objectives of this audit are:
to monitor the measures taken to ensure that a legal entity complies with the mandatory requirements of legislation
on urban planning during construction, reconstruction of a capital construction facility;
prevention, detection and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation;
taking measures to eliminate violations of mandatory requirements
(if they are identified) and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts.
The subject of this audit is:
compliance of the work performed and the construction materials used in the construction process, reconstruction of the capital construction facility, as well as the results of such work with the requirements of the project documentation approved
in accordance with Parts 15, 15.2 and 15.3 of Article 48 of the Urban Planning Code of the Russian Federation (taking into account the changes made to the project documentation in accordance with Parts 3.8 and 3.9 of Article 49 of the Urban Planning Code of the Russian Federation),
including energy efficiency requirements (with the exception of capital construction projects, to which energy efficiency requirements do not apply) and the requirements for equipping a capital construction facility with metering devices for energy resources used;
availability of a building permit;
compliance with the requirements established by Parts 2, 3 and 3.1 of Article 52 of the Urban Planning Code of the Russian Federation
# 002005205058
Unscheduled inspection
Start date: 2020-11-02, end date: 2020-11-16, duration: 10
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is carried out in order to prevent violations of legislation on urban development activities, including project documentation. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to eliminate violations of mandatory requirements in the event of their identification and prosecution of persons who have committed violations of the requirements of Federal laws and other regulatory legal acts, the subject of this audit is the compliance of the work performed and the construction materials used in the construction process of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation project documentation with taking into account the changes made to the design documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of Article 52 The Urban Planning Code of the Russian Federation
# 002005206854
Unscheduled inspection
Start date: 2020-11-09, end date: 2020-11-17, duration: 7
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the Deputy head of Rostechnadzor MTU AA Kulakov on August 3, 2020. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to elimination of violations of mandatory requirements in case of their detection and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts, the subject of this audit is the compliance of the work performed and the construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation The Federation of Project documentation, taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 articles 52 of the Urban Planning Code of the Russian Federation
# 002004474772
Unscheduled inspection
Start date: 2020-08-05, end date: 2020-08-18, duration: 10
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: Control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipment of the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work and construction materials used in the construction process of reconstruction of a capital construction facility, as well as the results of such work, with the requirements of the project documentation approved in accordance with parts 15 152 and 153 of Article 48 of the Urban Planning Code of the Russian Federation, taking into account the changes made in the design documentation in accordance with parts 38 and 39 of Article 49 of the Urban Planning Code of the Russian Federation and or the information model, including energy efficiency requirements, with the exception of capital construction projects for which energy efficiency requirements do not apply and the requirements for equipping a capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 of the article 52 of the Urban Planning Code of the Russian Federation
# 002004329801
Unscheduled inspection
Start date: 2020-03-10, end date: 2020-03-20, duration: —
Authority: Centralnoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: control of compliance of the work performed with the mandatory requirements of the design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used and other regulatory legal acts during the construction of the capital construction facility, the task of this audit is to prevent identify and suppress violations committed by the developer, the technical customer, as well as the person carrying out the reconstruction on the basis of an agreement with the developer or the technical customer legislation on urban planning activities, including design documentation of requirements for energy conservation and energy efficiency improvement, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the capital construction facility, as well as the results of such work, with the requirements of design documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used for construction, compliance with the requirements established by parts 2, 3 and 31 of Article 52 of the Urban Planning Code of the Russian Federation
# 002004163905
Unscheduled inspection
Start date: 2020-01-23, end date: 2020-01-30, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: This audit is conducted in order to implement the audit program approved by the Deputy head of Rostechnadzor MTU AA Kulakov on November 25, 2019. The objectives of this audit are to monitor the measures taken to comply with the mandatory requirements of legislation on urban development by a legal entity during the construction reconstruction of a capital construction facility, to prevent the identification and suppression of violations of mandatory requirements established by Federal laws and other regulatory acts of the Russian Federation and to take measures to to eliminate violations of mandatory requirements in case of their detection and to bring to justice persons who have committed violations of the requirements of Federal laws and other regulatory legal acts, the subject of this audit is the compliance of the work performed and the construction materials used during the construction of the reconstruction of the capital construction facility as well as the results of such work with the requirements approved in accordance with parts 15 15_2 and 15_3 of Article 48 of the Urban Planning Code of the Russian Federation The Federation of Project documentation, taking into account the changes made to the project documentation in accordance with parts 3_8 and 3_9 of Article 49 of the Urban Planning Code of the Russian Federation, including the requirements for energy efficiency, with the exception of capital construction facilities for which energy efficiency requirements do not apply and the requirements for equipping the capital construction facility with metering devices for energy resources used, the presence of a construction permit to comply with the requirements established by parts 2 3 and 31 articles 52 of the Urban Planning Code of the Russian Federation
# 261903854530
Unscheduled inspection
Start date: 2019-10-15, end date: 2019-11-12, duration: —
Authority: Upravlenie Stavropolskogo kraya gosudarstvennaya zhilischnaya inspekciya
Purpose of inspection: this inspection is carried out for the purpose of notification of completion of construction inspection program 15112010 dated 04052010 Final inspection the objectives of this inspection are to prevent identify and suppress violations of legislation on urban development activities committed by the developer, the technical customer, the person carrying out construction, including technical regulations and design documentation compliance with the procedure for conducting construction control, maintaining general and or special logs of work, executive documentation, drafting acts of inspection of works on structures of sections of engineering and technical support networks compliance with other requirements when performing work established by the design documentation, including requirements for energy efficiency and requirements for equipping a capital construction facility with metering devices for energy resources used compliance with mandatory requirements and or requirements established by municipal legal acts
# 001902730258
Unscheduled inspection
Start date: 2019-04-11, end date: 2019-05-15, duration: —
Authority: Federalnaya sluzhba po nadzoru v sfere zdravoohraneniya
Purpose of inspection: execution of the instruction of the Deputy Chairman of the Government of the Russian Federation Tagolikova dated 27032019 TGP123388 in connection with Varavin's appeal to
# 001902480455
Unscheduled inspection
Start date: 2019-02-07, end date: 2019-02-12, duration: —
Authority: Mezhregionalnoe tehnologicheskoe upravlenie Federalnoi sluzhby po ekologicheskomu tehnologicheskomu i atomnomu nadzoru
Purpose of inspection: To establish that this inspection is carried out in order to control the execution of the order dated May 23, 2018 366G3327X60
# 77170701551257
Unscheduled inspection
Start date: 2017-04-17, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160701105217
Unscheduled inspection
Start date: 2016-11-14, end date: —, duration: —
Authority: —
Purpose of inspection:
# 77160601700716
Unscheduled inspection
Start date: 2016-07-07, end date: —, duration: —
Authority: —
Purpose of inspection:
# 00160601462900
Unscheduled inspection
Start date: 2016-01-11, end date: 2016-02-09, duration: —
Authority: Federalnaya antimonopolnaya sluzhba
Purpose of inspection: Prevention and suppression of violations of the requirements established by legislative and other regulations in the field of public health
# 77160601457262
Unscheduled inspection
Start date: 2016-01-13, end date: 2016-02-09, duration: —
Authority: Glavnoe upravlenie MCHS Rossii po g Moskve
Purpose of inspection: Control over the execution of a previously issued prescription