# 022101197026
Unscheduled inspection
Start date: 2021-10-08, end date: —, duration: 20
Authority: Gosudarstvennyi komitet Respubliki Bashkortostan po zhilischnomu i stroitelnomu nadzoru
Purpose of inspection: conducting an inspection on the notice of completion of the capital construction facility No. 4 dated 09/29/2021, (ex. No. 26174 dated 30.09.2021) sent by JSC "SZ ISC Ufa".
# 022101213207
Unscheduled inspection
Start date: 2021-10-04, end date: —, duration: 20
Authority: Gosudarstvennyi komitet Respubliki Bashkortostan po zhilischnomu i stroitelnomu nadzoru
Purpose of inspection: identification, prevention and suppression of violations of legislation on urban development, including technical regulations and project documentation
# 022100534158
Unscheduled inspection
Start date: 2021-08-18, end date: —, duration: —
Authority: —
Purpose of inspection:
# 022004389055
Unscheduled inspection
Start date: 2020-02-21, end date: 2020-02-28, duration: —
Authority: Gosudarstvennyi komitet Respubliki Bashkortostan po zhilischnomu i stroitelnomu nadzoru
Purpose of inspection: conducting an inspection on the notification of the beginning of construction of the capital construction facility 1 from 17022020 bx 4122 from 17022020
# 021902627865
Unscheduled inspection
Start date: 2019-04-05, end date: 2019-05-07, duration: —
Authority: Gosudarstvennyi komitet Respubliki Bashkortostan po zhilischnomu i stroitelnomu nadzoru
Purpose of inspection: conducting an inspection of the facility on the notification of JSC "SZ ISC GO gUfa RB" on the elimination of violations dated 01042019 3 vx 8450 dated 01042019
# 021902451302
Unscheduled inspection
Start date: 2019-01-23, end date: 2019-02-19, duration: —
Authority: Gosudarstvennyi komitet Respubliki Bashkortostan po zhilischnomu i stroitelnomu nadzoru
Purpose of inspection: conducting an inspection of the facility on the notification of JSC "SZ ISC GO gUfa RB" on the completion dates of the works to be checked from 15012019 2 vx 657 from 15012019