# 771801998473
Unscheduled inspection
Start date: 2018-09-06, end date: —, duration: —
Authority: —
Purpose of inspection:
# 501800354665
Unscheduled inspection
Start date: 2018-05-10, end date: 2018-05-23, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: proverka ustraneniya narushenii izveschenie ob ustranenii narushenii P001596330940112607171 ot 25042018 v ramkah predpisaniya 0977021600505 ot 30032018 so srokom vypolneniya do 10052018
# 77180803124814
Unscheduled inspection
Start date: 2018-04-18, end date: 2018-05-18, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used
# 50170802937329
Unscheduled inspection
Start date: 2017-12-04, end date: —, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection:
# 50170802856130
Unscheduled inspection
Start date: 2017-10-23, end date: 2017-10-31, duration: —
Authority: Glavnoe upravlenie gosudarstvennogo stroitelnogo nadzora Moskovskoi oblasti
Purpose of inspection: proverki ustraneniya narushenii izveschenie ob ustranenii narushenii P00197864872878763060 ot 11102017 v ramkah predpisaniya 0977021600503 ot 11092017 so srokom vypolneniya do 11102017 ocenka sootvetstviya vypolnyaemyh rabot trebovaniyam tehnicheskih reglamentov i proektnoi dokumentacii na obekte kapitalnogo stroitelstva ZHiloi dom so vstroennymi pomescheniyami detskogo sada i nezhilymi pomescheniyami pervogo etazha po adresu Moskovskaya oblast g Reutov mkr 9 A
# 77170701891278
Unscheduled inspection
Start date: 2017-08-14, end date: —, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection:
# 77170701561844
Unscheduled inspection
Start date: 2017-04-24, end date: 2017-05-12, duration: —
Authority: Komitet gosudarstvennogo stroitelnogo nadzora goroda Moskvy
Purpose of inspection: compliance of the work and construction materials used in the process of construction reconstruction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements for equipping the capital construction facility with metering devices for energy resources used