# 221904041541
Unscheduled inspection
Start date: 2019-11-29, end date: 2019-12-02, duration: 2
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: s celyu proverki svedenii soderzhaschihsya v izveschenii ot 15112019 5 vh ot 15112019 62VP6028 o srokah zaversheniya rabot podlezhaschih proverke pri stroitelstveZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh licom osuschestvlyayuschim stroitelstvo narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii proektnoi dokumentaciiPredmetom nastoyaschei proverki yavlyaetsya pp 1 ch2 st54 GrK RF sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva a takzhe rezultatov takih rabot trebovaniyam utverzhdennoi v sootvetstvii s ch 15 152 i 153 st 48 GrK RF proektnoi dokumentacii vypolnenie trebovanii ch 2 3 31 st 52 GrK RF
# 221902854570
Unscheduled inspection
Start date: 2019-07-10, end date: —, duration: —
Authority: —
Purpose of inspection:
# 221902792975
Unscheduled inspection
Start date: 2019-06-17, end date: 2019-06-18, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: nastoyaschaya proverka provoditsya s celyu proverki svedenii soderzhaschihsya v izveschenii o srokah zaversheniya rabot podlezhaschih proverke 3 ot 28052019 vh 62VP3997 ot 31052019 a imenno proverka etapov rabot vypolnenie rabot po montazhu vozvedeniyu konstrukcii nadzemnoi chasti vypolnenie rabot po ustroistvu vnutrennih setei inzhenernotehnicheskogo obespecheniya inzhenernyh sistem i oborudovaniyaZadachami nastoyaschei proverki yavlyayutsya preduprezhdenie vyyavlenie i presechenie dopuschennyh narushenii zakonodatelstva o gradostroitelnoi deyatelnosti v tom chisle trebovanii proektnoi dokumentacii Predmetom nastoyaschei proverki yavlyaetsya p1 ch2 st54 GrK RF proverka sootvetstviya vypolneniya rabot i primenyaemyh stroitelnyh materialov v processe stroitelstva obekta kapitalnogo stroitelstva a takzhe rezultatov takih rabot trebovaniyam proektnoi dokumentacii
# 221902623071
Unscheduled inspection
Start date: 2019-04-04, end date: —, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection:
# 221902491677
Unscheduled inspection
Start date: 2019-02-20, end date: —, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection:
# 221902515765
Unscheduled inspection
Start date: 2019-02-22, end date: —, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection:
# 22170701321449
Unscheduled inspection
Start date: 2017-01-23, end date: —, duration: —
Authority: —
Purpose of inspection:
# 22160701020406
Unscheduled inspection
Start date: 2016-10-20, end date: 2016-10-20, duration: —
Authority: Inspekciya stroitelnogo i zhilischnogo nadzora Altaiskogo kraya
Purpose of inspection: the purpose of the program of inspections is to prevent identify and suppress violations of legislation on urban development activities the subject is to verify the completed construction of the facility, verify compliance of the work and construction materials used in the construction of the capital construction facility as well as the results of such work with the requirements of technical regulations of project documentation, including energy efficiency requirements and requirements of equipment of the capital construction facility with metering devices used compliance with the mandatory requirements for a construction permit and the requirements of Parts 2 and 3 of Article 52 of the Urban Planning Code of the Russian Federation